I will focus on funding and construction issues around the new Forth bridge, but I will first touch on other areas.
As our amendment makes clear, the priority must be to ensure that the new Forth bridge is constructed as soon as possible. Some people dispute the need for a new bridge, but it would be unacceptable to put at risk the entire economy of the east of Scotland in the belief that they might be correct. The project must be completed as a matter of urgency.
As we see in the Labour amendment, and as Des McNulty made clear in his remarks, concern has been expressed in some quarters about the design of the bridge. I assume that any changes to the design would add costs and perhaps lead to further delay, both of which we can ill afford.
We understand that Jim Murphy will raise the design of the bridge at his meeting with the Scottish Government on 27 January. The UK Government has an important role to play in relation to potential funding options for the bridge. However, the design of the new crossing should be a matter not for the Secretary of State for Scotland but for the Scottish Parliament and the Scottish Government. Indeed, issues around bridge design may have been raised as a smokescreen to shield from discussion the more fundamental issue of funding, to which I now turn.
If the Scottish Government is correct in its assessment of how a privately funded bridge, whether under PFI, PPP or SFT, would be treated in the Scottish Government's accounts, it is difficult to escape the conclusion that the only show in town for funding the bridge is the Scottish Government's budget. We have no ideological objection to that. The capital budget stands at more than £3.5 billion a year. In theory, the Scottish Government could fund the bridge in full from the budgets that we expect it to have. However, it is clear that the scale of the project is so large that it will inevitably displace many other capital infrastructure projects—whether national health service, transport or schools projects—across the country.
It may well be the case that, at the end of the day, there is no option other than to fund the bridge from the capital budget. We take the view that the Forth bridge must be built. It has to be the number 1 transport priority in Scotland. Whatever the funding method, some projects will be delayed while resource is provided to the bridge. The real question is about the scale of resource to be diverted from those projects and the length of time for which they will be delayed.
The new Forth road bridge project will be progressed after the next Scottish and UK general elections. Indeed, it might not be finished until after the next two Scottish and UK general elections. As such, it is right that it has an element of stability and certainty and, for that reason, the Conservatives have offered discussions between our shadow Treasury team and the Scottish Government. That constructive, positive offer is a sign of our willingness to discuss the question whether there are options to mitigate the impact of the construction of the bridge on other projects.
The Treasury's response to the Scottish Government's request can be characterised as conceding—almost, but not quite—that PPP is not a likely solution. It offers two alternatives: the switching of Scottish Government revenue spending to capital spending, and the use of accumulated underspends. The scale of underspends—£42 million last year—shows that unless there is a marked change they will not provide a meaningful sum towards the construction of the bridge. In any case, the Treasury has already suggested that underspends will compensate for the reduction in the capital budget from 2010-11. That money cannot be spent twice. It is certainly possible to switch revenue funding to capital funding, but to do so on a scale sufficient to offset significant delays in other programmes will require an appetite to reduce spending on those programmes over a sustained period of time, for which I do not think there is likely to be a parliamentary majority.
A critical issue with the construction of the bridge is that there is no inherent reason why the public sector cannot pay for the bridge using a fixed-price contract, with penalty clauses for delay. However, we know that public sector projects have a history of exceeding their budget and their timescale. That would be unacceptable for this project.
Managing the risk of cost overruns and delays is crucial, and it is essential to do so in a way that provides a cast-iron guarantee that none of the risk is passed back to the taxpayer. Ultimately, this is a project of high prestige to contractors. It will also be recognised as being too big to fail, and it will be too tempting for contractors to underbid, in the expectation that the Government will have to step in if things go wrong. That issue must be resolved in the contracting process.
The issue of tolls has been raised around the margins of the debate on funding. As the new bridge is to be a replacement, rather than additional, crossing, there is no logic in introducing tolls on it, having abolished them on the existing bridge. Indeed, the level of toll income from the existing bridge would be a drop in the ocean compared with the projected costs of the new bridge; a larger income would require tolls of a level that would be unacceptable on a route to which there is no ready alternative.
Although I accept what Iain Gray said today about tolls, both the Labour and Lib Dem amendments, in removing the part of the motion that addresses tolls, are unacceptable to the Conservatives. We accept, however, the concept of prioritising projects, as set out in the Lib Dem amendment, although that is a little ironic. In March 2007, Tavish Scott was asked to publish a list, in priority order, of the then Government's transport projects. His answer was:
"All these projects are considered as a priority, which is why they have been included in the programme".—[Official Report, Written Answers, 23 March 2007; S2W-32430.]
I expect that that answer will be repeated today by Mr Scott's successor.
I move amendment 3214.1, to insert at end:
"and calls on the Scottish and UK governments to work together to ensure that the new crossing is delivered at the earliest possible opportunity."
As our amendment makes clear, the priority must be to ensure that the new Forth bridge is constructed as soon as possible. Some people dispute the need for a new bridge, but it would be unacceptable to put at risk the entire economy of the east of Scotland in the belief that they might be correct. The project must be completed as a matter of urgency.
As we see in the Labour amendment, and as Des McNulty made clear in his remarks, concern has been expressed in some quarters about the design of the bridge. I assume that any changes to the design would add costs and perhaps lead to further delay, both of which we can ill afford.
We understand that Jim Murphy will raise the design of the bridge at his meeting with the Scottish Government on 27 January. The UK Government has an important role to play in relation to potential funding options for the bridge. However, the design of the new crossing should be a matter not for the Secretary of State for Scotland but for the Scottish Parliament and the Scottish Government. Indeed, issues around bridge design may have been raised as a smokescreen to shield from discussion the more fundamental issue of funding, to which I now turn.
If the Scottish Government is correct in its assessment of how a privately funded bridge, whether under PFI, PPP or SFT, would be treated in the Scottish Government's accounts, it is difficult to escape the conclusion that the only show in town for funding the bridge is the Scottish Government's budget. We have no ideological objection to that. The capital budget stands at more than £3.5 billion a year. In theory, the Scottish Government could fund the bridge in full from the budgets that we expect it to have. However, it is clear that the scale of the project is so large that it will inevitably displace many other capital infrastructure projects—whether national health service, transport or schools projects—across the country.
It may well be the case that, at the end of the day, there is no option other than to fund the bridge from the capital budget. We take the view that the Forth bridge must be built. It has to be the number 1 transport priority in Scotland. Whatever the funding method, some projects will be delayed while resource is provided to the bridge. The real question is about the scale of resource to be diverted from those projects and the length of time for which they will be delayed.
The new Forth road bridge project will be progressed after the next Scottish and UK general elections. Indeed, it might not be finished until after the next two Scottish and UK general elections. As such, it is right that it has an element of stability and certainty and, for that reason, the Conservatives have offered discussions between our shadow Treasury team and the Scottish Government. That constructive, positive offer is a sign of our willingness to discuss the question whether there are options to mitigate the impact of the construction of the bridge on other projects.
The Treasury's response to the Scottish Government's request can be characterised as conceding—almost, but not quite—that PPP is not a likely solution. It offers two alternatives: the switching of Scottish Government revenue spending to capital spending, and the use of accumulated underspends. The scale of underspends—£42 million last year—shows that unless there is a marked change they will not provide a meaningful sum towards the construction of the bridge. In any case, the Treasury has already suggested that underspends will compensate for the reduction in the capital budget from 2010-11. That money cannot be spent twice. It is certainly possible to switch revenue funding to capital funding, but to do so on a scale sufficient to offset significant delays in other programmes will require an appetite to reduce spending on those programmes over a sustained period of time, for which I do not think there is likely to be a parliamentary majority.
A critical issue with the construction of the bridge is that there is no inherent reason why the public sector cannot pay for the bridge using a fixed-price contract, with penalty clauses for delay. However, we know that public sector projects have a history of exceeding their budget and their timescale. That would be unacceptable for this project.
Managing the risk of cost overruns and delays is crucial, and it is essential to do so in a way that provides a cast-iron guarantee that none of the risk is passed back to the taxpayer. Ultimately, this is a project of high prestige to contractors. It will also be recognised as being too big to fail, and it will be too tempting for contractors to underbid, in the expectation that the Government will have to step in if things go wrong. That issue must be resolved in the contracting process.
The issue of tolls has been raised around the margins of the debate on funding. As the new bridge is to be a replacement, rather than additional, crossing, there is no logic in introducing tolls on it, having abolished them on the existing bridge. Indeed, the level of toll income from the existing bridge would be a drop in the ocean compared with the projected costs of the new bridge; a larger income would require tolls of a level that would be unacceptable on a route to which there is no ready alternative.
Although I accept what Iain Gray said today about tolls, both the Labour and Lib Dem amendments, in removing the part of the motion that addresses tolls, are unacceptable to the Conservatives. We accept, however, the concept of prioritising projects, as set out in the Lib Dem amendment, although that is a little ironic. In March 2007, Tavish Scott was asked to publish a list, in priority order, of the then Government's transport projects. His answer was:
"All these projects are considered as a priority, which is why they have been included in the programme".—[Official Report, Written Answers, 23 March 2007; S2W-32430.]
I expect that that answer will be repeated today by Mr Scott's successor.
I move amendment 3214.1, to insert at end:
"and calls on the Scottish and UK governments to work together to ensure that the new crossing is delivered at the earliest possible opportunity."