Forth Crossing

Thursday 15 January 2009 Meeting of the Parliament Debate 120 contributions · 24 speakers

Speakers

Showing Des McNulty only · show everyone

Des McNulty’s contributions

5 contributions
Des McNulty Lab Clydebank and Milngavie
link
Mr Swinney and Mr Salmond are both on the record as claiming that the Scottish Futures Trust will be the funding mechanism for Scotland's biggest infrastructure project in a generation. Before the election, and for months afterwards, they claimed that the SFT would match Labour's investment in new schools brick for brick, and they repeatedly said that the SFT would be the preferred procurement method for those and other major capital projects.

On "Newsnight" yesterday, Mr Chris Bone, managing director of Bone Steel of Wishaw, who makes steel frames for new buildings, said that his company has been involved in the building of approximately 35 schools in Scotland in the past 18 to 24 months but that the lack of new projects in the pipeline—thanks to the Scottish National Party—means that the schools construction programme in Scotland is starting to decrease considerably and that his company is now working on some major education projects in the midlands and the south of England.

This is an issue not just for contractors and education authorities. The Deputy First Minister delivered her verdict on the SFT when she chose conventional procurement for the Southern general hospital, and now the architect of the SFT, Mr Swinney himself, has been forced to admit that the Scottish Futures Trust is not a suitable mechanism for the Forth replacement crossing.

It could be argued that Mr Swinney's comments about the SFT are coming to resemble Michael Palin's efforts to convince John Cleese that there is still life in the Norwegian blue in the Monty Python dead parrot sketch, but the consequences of the failure of the Scottish Futures Trust are unfortunately not a humorous matter.

During the debate that followed the statement on the Government's Forth replacement crossing, Jeremy Purvis and I asked whether ministers had been in dialogue with the UK Government. At the time, ministers dodged those questions but, later in the month, it emerged that they had written to Treasury ministers less than a fortnight before the strategy was announced to Parliament. Is that when they finally admitted to themselves that the SFT offered no way forward, or did they realise that much earlier and simply fail to take the necessary steps to secure prior agreement on the funding mechanism? Either way, the SNP has placed the project at unnecessary risk.

I am pleased that the Scottish Government will now have discussions with the UK Government, at the instigation of Jim Murphy, the Secretary of State for Scotland, and I agree with the Conservatives that the UK and Scottish Governments should work together constructively to deliver the project at the earliest opportunity.

Des McNulty Lab Clydebank and Milngavie
link
That does not necessarily ensure that the project will be delivered on time and to budget. A reasonable question to ask is why the Scottish Government did not hold back at least some of the £900 million reserve to which it had access when it came to power to fund the vital Forth replacement crossing. Ministers were well aware that substantial funding would be required, even if they did not know the precise amount, yet they cleaned out the kitty in pursuit of short-term political advantage and narrowed their funding options to the dead end of the Scottish Futures Trust. Now, with their flagship funding scheme in tatters, they have gone cap in hand to seek a huge advance.

As the Liberal Democrat amendment makes clear, the situation will have huge knock-on consequences for other capital projects. By far the best thing would be for the Government to be completely honest about what can and cannot be progressed and to set out a programme with costings and timescales. If discussions with the UK Government had been progressed earlier, we might have had much more certainty—the certainty to which Mr Swinney referred—about the Forth replacement crossing's impact on other transport projects.

Des McNulty Lab Clydebank and Milngavie
link
I will describe the paradoxes in the detail of the bridge strategy now. Labour's priorities are to avoid disruption to travellers across the Forth, ensure maximum flexibility in all transport modes, deliver value for money and provide a solution that meets longer-term as well as short-term requirements. In December 2007, the Government announced that its preferred option was a multimodal replacement bridge. Many people—especially engineering experts—thought that the costings were considerably out of line with outturn prices for similar bridges of an equivalent length elsewhere in the world.

We now have revised proposals for a "refined, sleeker replacement bridge" that will operate alongside the existing bridge in "a managed crossing strategy". Nearly £100 million has been spent on consultation and planning—most was on consultancy fees. Dr Iain Docherty told the Transport, Infrastructure and Climate Change Committee that professional expertise has been

"brought to the table from countries across Europe and the world that have dealt with similar problems"

and that robust peer review by senior engineers has taken place behind the scenes. I certainly hope that that is the case, but I am concerned by this comment:

"I believe that the long-term future of the existing bridge is still in doubt in some ways. Once the replacement crossing is up and running and we transfer the existing traffic to the new bridge, we will be in the same position in capacity terms as we are in today. We will then have to begin to think long and hard about the long-term future of the existing structure. It will take a long time to remediate it, and we will have to find the money to do that."

He said that it might be

"possible to extend the life of the bridge, but only if we reduce its physical capacity so that it has, for example, only two lanes rather than four for many years".—[Official Report, Transport, Infrastructure and Climate Change Committee, 6 January 2009; c 1233.]

That is a lot of maybes and additional costs that have not been factored into the scheme that the minister presented. The replacement Forth crossing was deemed necessary because of uncertainty about the existing bridge's deterioration. Now, the replacement's design seems to be predicated on the assumption that the existing bridge's life can be extended indefinitely.

We cannot face both ways. If we build a road-only bridge that is intended for the use of private vehicles, are we accepting that public transport could be excluded from crossing the Forth if the existing bridge's deterioration cannot be prevented? Although the early indications from FETA show some slowing in the rate of deterioration, no explanation has been made thus far of why the condition of the current bridge presents an unacceptable risk to the continuity of provision for private vehicles but an acceptable risk for public transport. That is a crazy situation.

We need the fullest possible information on the Government's new crossing strategy and on the previous strategy that it has now discarded. It is unacceptable for ministers to argue that they know best or to say that we should leave things to the experts when ministers have so radically altered their stance in a short space of time—presumably on the basis of expert advice.

I want a solution that provides maximum flexibility and the greatest certainty—a solution that is future proofed, as far as it is possible to do so. Having spent £2 billion or more, we need to be sure that access across the Forth is at least as good as it is at present and under any foreseeable eventuality. It is for that reason that my amendment requires the new bridge—if that is what we are going to have—to be

"capable of operating on a multi-modal basis to ensure continuity of provision for public transport as well as private vehicles."

Even if it makes sense in the short term to separate out public and private vehicles, surely it must be possible to construct the new bridge so that all modes of transport can use it. I listened to what Mr Swinney said on the possibility of light rail using the new bridge. That possibility was not made sufficiently explicit in the documentation that I have seen thus far—that said, if it is a change of stance, it is probably welcome.

The argument that the price of the crossing has come down because of the approach that the Government has taken to funding is ridiculous. The bridge is narrower and considerable reductions in motorway and access road alterations that being incorporated into the scheme. Earlier this week, Mr Stevenson was either unable or unwilling to tell me what proportion of the cost reductions stemmed from changes to the bridge design and how much stemmed from changes to the associated road works. That approach has to change: we are all partners in the project and we are acting not on our own behalf but on behalf of future generations.

I move amendment S3M-3214.3, to leave out from "and welcomes" to end and insert:

"; expresses concern that the lack of prior consultation with the UK Government raises questions over the delivery of the project on time and on budget, and considers that the new bridge should be capable of operating on a multi-modal basis to ensure continuity of provision for public transport as well as private vehicles."

Des McNulty Lab Clydebank and Milngavie
link
The member was active in local government, so he will be aware that one way to deal with large capital projects is to put money aside for a certain amount of time and to balance that with the borrowing. Why does the Government not use the put aside money that it inherited as a down payment on the Forth crossing?

Motions, questions and votes

Linked from this item of the Official Report
  1. Scottish Parliament Thursday 15 January 2009 Debate · 1
  2. Health Boards (Membership and Elections) (Scotland) Bill: Stage 1 Bill debate · 64
  3. Health Boards (Membership and Elections) (Scotland) Bill: Financial Resolution Bill debate · 4
  4. Gaza Questions · 6
  5. Urban Woodland Questions · 6
  6. Transport Developments Questions · 6
  7. Electricity Supply Interruptions (Compensation for Small Businesses) Questions · 6
  8. Public Transport (Roxburgh and Berwickshire) Questions · 6
  9. Shop Workers (Redundancy Support) Questions · 6
  10. Engagements First Minister’s Questions · 11
  11. Secretary of State for Scotland (Meetings) First Minister’s Questions · 6
  12. Cabinet (Meetings) First Minister’s Questions · 15
  13. Financial Sector Jobs First Minister’s Questions · 8
  14. Homecoming Scotland 2009 (Funding) First Minister’s Questions · 4
  15. Unintentional Homelessness First Minister’s Questions · 4
  16. Presiding Officer's Statement Procedure · 3
  17. Housing Associations Questions · 12
  18. NHS Greater Glasgow and Clyde (Meetings) Questions · 8
  19. Poverty and Income Inequality Questions · 8
  20. Care Home Staff (Fife) Questions · 4
  21. Southern General Hospital Questions · 6
  22. Telehealth and Telemedicine Questions · 4
  23. GHA (Management) Ltd (Regulation) Questions · 4
  24. Specialist Nurses (Motor Neurone Disease) Questions · 4
  25. Alcohol Misuse Services (Aberdeen) Questions · 6
  26. National Health Service Dentists (Grampian) Questions · 6
  27. Repossessions (Homeowner Support) Questions · 6
  28. “Financial overview of the NHS in Scotland 2007/08” Questions · 8
  29. Forth Crossing Debate · 120
  30. Decision Time Decision time · 31
  31. Bull Hire Scheme Members’ business · 34

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.