When it estimates that roadwork improvements to the Auchenkilns roundabout will be completed; what the original budget was for this project and what its latest estimate is of the cost of the current works.

Started with S2W-18253 on 1 Aug 2005; latest 20 Apr 2006. Each later question says it follows up an earlier answer.

Follow-ups
4
longest chain 2 steps
Span
262 days
1 Aug 2005 to 20 Apr 2006
Answered
5 of 5
by Tavish Scott
Asked by
1
Alex Neil

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S2W-18253 1 Aug 2005 Alex Neil SNP Answered

    To ask the Scottish Executive when it estimates that roadwork improvements to the Auchenkilns roundabout will be completed; what the original budget was for this project and what its latest estimate is of the cost of the current works.

    Tavish Scott, 18 Aug 2005: The contractor expects the new junction to be fully open to traffic at Christmas 2005. The pre tender estimate for the construction of this scheme was £18.9 million. The tender price was more expensive than anticipated at £21.98 million. The contract is expected to cost £22.24 million, with the additional expenditure …
  2. S2W-18616 22 Aug 2005 Alex Neil SNP Answered

    What the original deadline was for the completion of the roadwork improvements to the Auchenkilns roundabout; whether there will be a delay in reaching this deadline, and, if so, what the reasons are for such a delay.

    Tavish Scott, 15 Sep 2005: The contract completion date is 26 September 2005. As I said in my reply to you on 18 August 2005, the contractor expects the new junction to be fully open to traffic at Christmas this year. The reason for the delay is due to structural failure.
  3. S2W-20283 2 Nov 2005 Alex Neil SNP Answered follows S2W-18253

    Whether there are any extra costs in addition to the estimated £22.24 million for the improvements to the Auchenkilns roundabout that have to be met by the contractor for the project and, if so, what these extra costs are.

    Tavish Scott, 17 Nov 2005: I understand that there will be extra costs which will be met by the contractor and his supply chain. The amount of these costs is not known to the Scottish Executive.
  4. S2W-21074 24 Nov 2005 Alex Neil SNP Answered

    Whether these extra costs that must be met by the contractor result from their contract with the Executive and, if so, whether it will provide details.

    Tavish Scott, 5 Dec 2005: Under the contract, the contractor is responsible for the design and construction of the works. As I said in my reply to you on 17 November 2005 the amount of any extra costs incurred by the contractor is not known to the Scottish Executive.
  5. S2W-25317 20 Apr 2006 Alex Neil SNP Answered follows S2W-18253

    And whilst the Auchenkilns junction was opened to traffic by Christmas 2005, whether the contract was completed at this time or at a date subsequent to the junction opening to traffic.

    Tavish Scott, 2 May 2006: The works were substantiallycomplete at that time but, as is customary, some ancillary works continued afterthat date. The contract is not due to end until 21 December 2010 when the fiveyear maintenance period ends.

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.