Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S2W-18616 · Session 2

Further to the answer to question S2W-18253 by Tavish Scott on 18 August 2005, what the original deadline was for the completion of the roa…

Answered Asked by Alex Neil SNP Lodged 22 Aug 2005

The question

To ask the Scottish Executive, further to the answer to question S2W-18253 by Tavish Scott on 18 August 2005, what the original deadline was for the completion of the roadwork improvements to the Auchenkilns roundabout; whether there will be a delay in reaching this deadline, and, if so, what the reasons are for such a delay.

The answer

Answered by Tavish Scott on 15 Sep 2005 · 24 days after it was lodged, on time

The contract completion date is 26 September 2005. As I said in my reply to you on 18 August 2005, the contractor expects the new junction to be fully open to traffic at Christmas this year. The reason for the delay is due to structural failure.

In the Official Report

No contribution in the Official Report cites S2W-18616 by reference.