Written Question · S2W-18253 · Session 2
When it estimates that roadwork improvements to the Auchenkilns roundabout will be completed; what the original budget was for this project…
The question
To ask the Scottish Executive when it estimates that roadwork improvements to the Auchenkilns roundabout will be completed; what the original budget was for this project and what its latest estimate is of the cost of the current works.
The answer
The contractor expects the new junction to be fully open to traffic at Christmas 2005. The pre tender estimate for the construction of this scheme was £18.9 million. The tender price was more expensive than anticipated at £21.98 million. The contract is expected to cost £22.24 million, with the additional expenditure arising from the provision of additional sound insulation to contain traffic noise.