Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S2W-18253 · Session 2

When it estimates that roadwork improvements to the Auchenkilns roundabout will be completed; what the original budget was for this project…

Answered Asked by Alex Neil SNP Lodged 1 Aug 2005

The question

To ask the Scottish Executive when it estimates that roadwork improvements to the Auchenkilns roundabout will be completed; what the original budget was for this project and what its latest estimate is of the cost of the current works.

The answer

Answered by Tavish Scott on 18 Aug 2005 · 17 days after it was lodged, on time

The contractor expects the new junction to be fully open to traffic at Christmas 2005. The pre tender estimate for the construction of this scheme was £18.9 million. The tender price was more expensive than anticipated at £21.98 million. The contract is expected to cost £22.24 million, with the additional expenditure arising from the provision of additional sound insulation to contain traffic noise.

In the Official Report

No contribution in the Official Report cites S2W-18253 by reference.