Written Question · S2W-25317 · Session 2
Further to the answer to question S2W-18253 by Tavish Scott on 18 August 2005 and whilst the Auchenkilns junction was opened to traffic by …
The question
To ask the Scottish Executive, further to the answer to question S2W-18253 by Tavish Scott on 18 August 2005 and whilst the Auchenkilns junction was opened to traffic by Christmas 2005, whether the contract was completed at this time or at a date subsequent to the junction opening to traffic.
The answer
The works were substantiallycomplete at that time but, as is customary, some ancillary works continued afterthat date. The contract is not due to end until 21 December 2010 when the fiveyear maintenance period ends.
In the Official Report
No contribution in the Official Report cites S2W-25317 by reference.