The question

To ask the Scottish Executive, further to the answer to question S2W-18253 by Tavish Scott on 18 August 2005, whether there are any extra costs in addition to the estimated £22.24 million for the improvements to the Auchenkilns roundabout that have to be met by the contractor for the project and, if so, what these extra costs are.

The answer

Answered by Tavish Scott on 17 Nov 2005 · 15 days after it was lodged, 1 day after it was due

I understand that there will be extra costs which will be met by the contractor and his supply chain. The amount of these costs is not known to the Scottish Executive.