In light of concerns regarding more extreme weather conditions, what most recent assessment it has carried out of the country's flood defences.

Started with S5W-10494 on 26 Jul 2017; latest 10 Jul 2025. Each later question says it follows up an earlier answer.

Follow-ups
29
longest chain 6 steps
Span
2,906 days
26 Jul 2017 to 10 Jul 2025
Answered
30 of 30
by Gillian Martin, Mairi McAllan, Roseanna Cunningham and others
Asked by
6
MSPs

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S5W-10494 26 Jul 2017 Mike Rumbles LD Answered

    To ask the Scottish Government, in light of concerns regarding more extreme weather conditions, what most recent assessment it has carried out of the country's flood defences.

    Roseanna Cunningham, 15 Aug 2017: SEPA undertook a National Flood Risk Assessment (NFRA) in 2011 and the resulting Flood Risk Management Strategies were published in December 2015. This gave us for the first time a national picture of the causes and consequences of flooding across Scotland. This is a major step forward in our understanding of flood ri…
  2. S5W-27521 19 Feb 2020 Mike Rumbles LD Answered

    Which of the 42 formal flood protection schemes or engineering works have been removed from the list of proposed works, broken down by the (a) number of properties that were expected to be protected, (b) reason for removal, and (c) (i) initial forecast cost of and (ii) amount that was spent on each.

    Mairi Gougeon, 4 Mar 2020: The only works that have so far been removed from the list of the 42 formal flood protection schemes or engineering works are those to the Greenock - Coves Burn which were to be taken forward by Inverclyde Council. The number of properties that were expected to be protected is not held by the Scottish Government, the …
  3. S5W-27523 19 Feb 2020 Mike Rumbles LD Answered follows S5W-10494

    How many floods have been recorded in each of the 42 formal flood protection schemes or engineering works' areas since January 2016, broken down by the (a) damage caused and (b) cost of each incident.

    Mairi Gougeon, 5 Mar 2020: Information on the location, damage and costs caused by individual flood incidents is not held by the Scottish Government but detailed information may be held by local authorities, emergency responders and the insurance industry. SEPA collect information on incidents of flooding from local authorities and also from me…
  4. S5W-27520 19 Feb 2020 Mike Rumbles LD Answered follows S5W-10494

    Which of the 42 formal flood protection schemes or engineering works are (a) under construction and (b) at the planning or other stage of development, broken down by (i) what the expected completion date is, and the reason for any date being beyond 2021, (ii) the number of properties that will be protected, and (iii) the (A) initial forecast and (B) final expected cost of each.

    Mairi Gougeon, 4 Mar 2020: The 14 Flood Risk Management Strategies published by the Scottish Environment Protection Agency (SEPA) in December 2015 set objectives and measures for the management of flood risk for potentially vulnerable areas. Local Flood Risk Management Plans, published in June 2022, set out in more detail how measures in the St…
  5. S5W-27519 19 Feb 2020 Mike Rumbles LD Answered follows S5W-10494

    Which of the 42 formal flood protection schemes or engineering works have been completed, broken down by (a) the number of properties being protected, (b) the completion date, and (c) what the (i) initial forecast and (ii) final cost was of each.

    Mairi Gougeon, 4 Mar 2020: Details are as follows: Scheme (a) Properties Protected (b) Completion Date (c)(i) Initial Cost (£ million) (1) (c) (ii) Estimated Final Cost (£ million) Huntly 63 2017 4.9 3.8 Newmill 18 2017 1.9 1.8 Dundee 200 2018 6.2 6.9 Kirkwall 750 2018 1.8 1.8 White Cart Water Phase 3 100 2019 5.9 7.2 Camlachie Burn 410 2019 1.…
  6. S5W-32874 27 Oct 2020 Mike Rumbles LD Answered follows S5W-10494

    How many floods have been recorded in each of the 42 formal flood protection schemes or engineering works' areas since January 2016, broken down by the (a) damage caused and (b) cost of each incident.

    Roseanna Cunningham, 11 Nov 2020: I refer the member to the answer to question S5W-27523 on 5 March 2020. All answers to written parliamentary questions are available on the Parliament's website, the search facility for which can be found at http://www.parliament.scot/parliamentarybusiness/28877.aspx .
  7. S5W-32872 27 Oct 2020 Mike Rumbles LD Answered follows S5W-10494

    Which of the 42 formal flood protection schemes or engineering works are (a) under construction and (b) at the planning or other stage of development, broken down by (i) what the expected completion date is, and the reason for any date being beyond 2021, (ii) the number of properties that will be protected and (iii) the (A) initial forecast and (B) final expected cost of each.

    Roseanna Cunningham, 11 Nov 2020: The 14 Flood Risk Management Strategies published by the Scottish Environment Protection Agency (SEPA) in December 2015 set objectives and measures for the management of flood risk for potentially vulnerable areas. Local Flood Risk Management Plans, published in June 2022, set out in more detail how measures in the St…
  8. S5W-32873 27 Oct 2020 Mike Rumbles LD Answered follows S5W-10494

    Which of the 42 formal flood protection schemes or engineering works have been removed from the list of proposed works, broken down by the (a) number of properties that were expected to be protected, (b) reason for removal, and (c) (i) initial forecast cost of and (ii) amount that was spent on each.

    Roseanna Cunningham, 11 Nov 2020: I refer the member to the answer to question S5W-27519 on 4 March 2020. All answers to written parliamentary questions are available on the Parliament's website, the search facility for which can be found at http://www.parliament.scot/parliamentarybusiness/28877.aspx .
  9. S5W-32871 27 Oct 2020 Mike Rumbles LD Answered follows S5W-10494

    Which of the 42 formal flood protection schemes or engineering works have been completed, broken down by (a) the number of properties being protected, (b) the completion date and (c) what the (i) initial forecast and (ii) final cost was of each.

    Roseanna Cunningham, 11 Nov 2020: Details are as follows: Scheme (a) Properties Protected (b) Completion Date (c)(i) Initial Cost (£ million) (1) (c) (ii) Estimated Final Cost (£ million) Huntly 63 2017 4.9 3.8 Newmill 18 2017 1.9 1.8 Dundee 200 2018 6.2 6.9 Kirkwall 750 2018 1.8 1.8 White Cart Water Phase 3 100 2019 5.9 7.2 Camlachie Burn 410 2019 1.…
  10. S6W-04900 3 Dec 2021 Alexander Burnett Con Answered follows S5W-10494

    Which of the 42 formal flood protection schemes or engineering works have been completed, broken down by (a) the number of properties being protected, (b) the completion date and (c) the (i) initial forecast and (ii) final cost of each.

    Mairi McAllan, 23 Dec 2021: The following formal flood protection schemes are complete. Scheme (a) Properties Protected (b) Completion Date (c)(i) Initial Cost (£ million) (1) (c) (ii) Estimated Final Cost (£ million) (2) Huntly 63 2017 4.9 3.8 Newmill 18 2017 1.9 1.8 Dundee 200 2018 6.2 6.9 Kirkwall 750 2018 1.8 1.8 White Cart Water Phase 3 100…
  11. S6W-04901 3 Dec 2021 Alexander Burnett Con Answered follows S5W-10494

    Which of the 42 formal flood protection schemes or engineering works are (a) under construction and (b) at the planning or other stage of development, broken down by (i) the expected completion date, including the reason for any date being beyond 2021, (ii) the number of properties that will be protected and (iii) the (A) initial forecast and (B) final expected cost of each.

    Mairi McAllan, 24 Dec 2021: The 2015 - 2021 Flood Risk Management Strategies included 42 formal flood protection schemes. Local authorities are expected to start work on development of these schemes by 2021. However as flood protection schemes can have significant impacts on individuals, communities and the environment, and so require careful an…
  12. S6W-05145 13 Dec 2021 Beatrice Wishart LD Answered follows S5W-10494

    Which of the 42 formal flood protection schemes or engineering works are (a) under construction and (b) at the planning or other stage of development, broken down by the (i) expected completion date, (ii) number of properties that will be protected and (iii) (A) initial forecast and (B) final expected cost of each.

    Mairi McAllan, 13 Jan 2022: I refer the member to the answer to question S6W-04901 on ? 24 December 2021. All answers to written parliamentary questions are available on the Parliament's website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers
  13. S6W-05146 13 Dec 2021 Beatrice Wishart LD Answered follows S5W-10494

    Which of the 42 formal flood protection schemes or engineering works have been removed from the list of proposed works since August 2017, broken down by the (a) number of properties that were expected to be protected, (b) reason for removal and (c) (i) initial forecast cost of and (ii) amount that was spent on each.

    Mairi McAllan, 12 Jan 2022: The only works that have been removed from the list of the 42 formal flood protection schemes or engineering works are those to the Greenock - Coves Burn which were to be taken forward by Inverclyde Council. The number of properties that were expected to be protected is not held by the Scottish Government, the removal…
  14. S6W-12673 25 Nov 2022 Liam McArthur LD Answered

    Which of the 42 formal flood protection schemes or engineering works have been removed from the list of proposed works since January 2022, broken down by the (a) number of properties that were expected to be protected, (b) reason for removal and (c) (i) initial forecast cost of and (ii) amount that was spent on each.

    Mairi McAllan, 13 Dec 2022: No further flood protection schemes or engineering works have been removed from the list of the 42 formal flood protection schemes since the answer to question S6W-05146.
  15. S6W-12674 25 Nov 2022 Liam McArthur LD Answered follows S6W-04901

    Whether it will provide an update on which of the 42 formal flood protection schemes or engineering works are (a) under construction and (b) at the planning or other stage of development, broken down by (i) the expected completion date, including the reason for any date being beyond the 2021 timeframe, (ii) the number of properties that will be protected and (iii) the (A) initial forecast and (B) final expected cost…

    Mairi McAllan, 14 Dec 2022: Local authorities are responsible for the development and delivery of flood protection schemes. The 2015-2021 Flood Risk Management Strategies included 42 formal flood protection schemes. Local authorities were expected to start work on development of these schemes by 2021. However as flood protection schemes can have…
  16. S6W-22487 26 Oct 2023 Willie Rennie LD Answered

    Whether it will provide an update on which of the 42 formal flood protection schemes or engineering works are (a) under construction and (b) at the planning or other stage of development, broken down by (i) the expected completion date, including the reason for any date being beyond the 2021 timeframe, (ii) the number of properties that will be protected and (iii) the (A) initial forecast and (B) final expected cost…

    Mairi McAllan, 9 Nov 2023: Local authorities are responsible for the development and delivery of flood protection schemes. The 2015-2021 Flood Risk Management Strategies included 42 formal flood protection schemes. Local authorities were expected to start work on development of these schemes by 2021. Flood protection schemes can have significan…
  17. S6W-24035 18 Dec 2023 Stephen Kerr Con Answered follows S5W-10494

    Which of the "42 formal Flood Protection Schemes or engineering works proposed for 2016-21" have been completed to date, broken down by (a) the number of properties being protected, (b) completion date and (c) the (i) initially forecast and (ii) final cost of each.

    Mairi McAllan, 16 Jan 2024: Information has been shared in response to similar questions many times (at least annually) since Roseanna Cunningham answered on 15 August 2017, most recently in response to Willie Rennie MSP on 9 November 2023. The following formal flood protection schemes are complete. Scheme (a) Properties Protected (b) Completion…
  18. S6W-24036 18 Dec 2023 Stephen Kerr Con Answered follows S5W-10494

    Which of the "42 formal Flood Protection Schemes or engineering works proposed for 2016-21" are currently (a) under construction and (b) at the planning or other stage of development, broken down by (i) expected completion date, including the reason for any date being beyond 2021, (ii) the number of properties that will be protected and (iii) the (A) initially forecast and (B) expected final cost of each.

    Mairi McAllan, 16 Jan 2024: Information has been shared in response to similar questions many times (at least annually) since Roseanna Cunningham answered on 15 August 2017, most recently in response to Willie Rennie MSP on 9 November 2023. Local authorities are responsible for the development and delivery of flood protection schemes. The 2015-2…
  19. S6W-24403 9 Jan 2024 Alexander Burnett Con Answered follows S6W-12674

    Whether it will provide an update on which of the 42 formal flood protection schemes or engineering works are (a) under construction and (b) at the planning or other stage of development, broken down by (i) the expected completion date, including the reason for any date being beyond the 2021 timeframe, (ii) the number of properties that will be protected and (iii) the (A) initial forecast and (B) final expected cost…

    Mairi McAllan, 28 Mar 2024: I refer the member to the answer to question S6W–24036 on? 16 January 2024. All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers
  20. S6W-30798 21 Oct 2024 Alexander Burnett Con Answered follows S6W-22487

     whether it will provide an update on which of the 42 formal flood protection schemes or engineering works are (a) under construction and (b) at the planning or other stage of development, broken down by the (i) expected completion date, including the reason for any date being beyond the 2021 timeframe, (ii) number of properties that will be protected and (iii) (A) initial forecast and (B) final expected cost of eac…

    Gillian Martin, 7 Nov 2024: The responsibility for development and delivery of flood protection schemes rests with individual local authorities, who are best placed to respond to local resilience needs.The first set of Flood Risk Management plans covering the period 2015-2021 included 42 prioritised flood protection schemes. Work was expected to…
  21. S6W-32194 11 Dec 2024 Alexander Burnett Con Answered

    Whether it will provide an update on the current status of Aberdeenshire Council’s application for funding under the flood protection scheme regarding Ballater, and where in the list of applicants it sits in prioritisation for funding.

    Gillian Martin, 3 Jan 2025: Local authorities are responsible for the development and delivery of flood protection schemes in Scotland. Decisions on the allocation of funding for flood resilience are made jointly by Scottish Ministers and COSLA leaders, informed by SEPA flood risk assessment and a subsequent prioritisation process.SEPA has categ…
  22. S6W-36403 28 Mar 2025 Alexander Burnett Con Answered follows S6W-30798

    Where the annual reports required under section 52 of the Flood Risk Management Act (2009), can be accessed.

    Gillian Martin, 24 Apr 2025: Flood risk management implementation reports are available on the Scottish Government's website. Some reports have been completed for single years and some for multiple years.Relevant links are provided below:Report for years 2015-2018: Implementation of the Flood Risk Management (Scotland) Act 2009: report to the Sco…
  23. S6W-36404 28 Mar 2025 Alexander Burnett Con Answered follows S6W-30798

    Whether it will meet all final costs, regardless of any increase compared with the initial estimate. 

    Gillian Martin, 24 Apr 2025: As outlined in the answer to question S6W-30798 on 7 November, since 2016, the Scottish Government has allocated £570 million to local authorities for flood protection schemes and flood resilience. In this period, the estimated costs of cycle one schemes eligible for funding has risen.A joint Scottish Government/ COSL…
  24. S6W-36405 28 Mar 2025 Alexander Burnett Con Answered follows S6W-30798

    For what reason more schemes have not been confirmed, or begun the legal notification process towards confirmation, in light of £570 million being assigned for the period 2016-26, and only £408.8 million estimated to date as final costs.

    Gillian Martin, 24 Apr 2025: The £570 million referenced in the answer to question S6W-30798 on 7 November 2024 is provided by Scottish Government to local authorities to support a range of flood resilience actions, including cycle 1 Flood Protection Schemes. The development and delivery of Flood Protection Schemes is a local authority responsibi…
  25. S6W-36402 28 Mar 2025 Alexander Burnett Con Answered follows S6W-30798

    Whether the eight schemes stated as withdrawn and the one stated as no longer required were included in the 16 out of 33 remaining schemes marked as complete.

    Gillian Martin, 2 May 2025: The eight schemes highlighted in answer S6W-30798 on 7 November 2024 as withdrawn from the cycle one flood protection scheme funding programme, and the one scheme highlighted as no longer required, were not included in the list of 16 schemes complete at that time.18 schemes are now complete.
  26. S6W-36409 28 Mar 2025 Alexander Burnett Con Answered follows S6W-32194

    When it last met with COSLA.

    Gillian Martin, 24 Apr 2025: The Scottish Government and COSLA funding working group described in the answer to question S6W-32194 on 3 January 2025 last met on 6 March 2025.All answers to written Parliamentary Questions are available on the Parliament’s website, the search facility for which can be found at https://www.parliament.scot/chamber-an…
  27. S6W-36406 28 Mar 2025 Alexander Burnett Con Answered follows S6W-32194

    Where the minutes of meetings held between the Scottish Ministers and COSLA can be accessed.

    Gillian Martin, 24 Apr 2025: The answer to S6W-32194 referred to a Scottish Government and COSLA funding working group set up to consider both the affordability of the 2015 flood protection scheme programme and use lessons learned to inform the future funding and governance model for flooding. This group is not attended by Ministers but by Scotti…
  28. S6W-36408 28 Mar 2025 Alexander Burnett Con Answered follows S6W-32194

    Whether it will provide an update on the (a) current status (b) available funding and (c) expected costs for all flood protection schemes

    Gillian Martin, 22 Apr 2025: Since the answer given to question S6W-32194 on 3 January:1.The position on funding for new flood protection schemes has not changed since 3 January 2025.2.The total available funding to date for flood resilience including flood resilience schemes has not changed since 3 January 2025.3.Potential new Flood Protection S…
  29. S6W-36407 28 Mar 2025 Alexander Burnett Con Answered follows S6W-32194

    Whether SEPA's assessment of flood protection schemes completed for the 2021 Flood Risk Management Plans is available to view.

    Gillian Martin, 24 Apr 2025: This information is not published, however is available on request from SEPA.
  30. S6W-39337 10 Jul 2025 Alexander Burnett Con Answered follows S6W-36403

    In light of section 52(1)(b) of the Flood Risk Management (Scotland) Act 2009, whether the reports required under section 52 for years 2010 to 2012 were included in the Scottish Ministers' reports under section 26 of the Water Environment and Water Services (Scotland) Act 2003 for the calendar years concerned.

    Gillian Martin, 5 Aug 2025: Flood risk management implementation reports for the years 2010 to 2012 are available on the Scottish Government’s archive website. These reports are joint publications detailing progress in implementing both the Water Environment and Water Services (Scotland) Act 2003 and the Flood Risk Management (Scotland) Act 2009…

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.