Written Question · S5W-32872 · Session 5

Further to the answer to question S5W-10494 by Roseanna Cunningham on 15 August 2017, which of the 42 formal flood protection schemes or en…

Answered Asked by Mike Rumbles LD Lodged 27 Oct 2020

The question

To ask the Scottish Government, further to the answer to question S5W-10494 by Roseanna Cunningham on 15 August 2017, which of the 42 formal flood protection schemes or engineering works are (a) under construction and (b) at the planning or other stage of development, broken down by (i) what the expected completion date is, and the reason for any date being beyond 2021, (ii) the number of properties that will be protected and (iii) the (A) initial forecast and (B) final expected cost of each.

The answer

Answered by Roseanna Cunningham on 11 Nov 2020 · 15 days after it was lodged, on time

The 14 Flood Risk Management Strategies published by the Scottish Environment Protection Agency (SEPA) in December 2015 set objectives and measures for the management of flood risk for potentially vulnerable areas. Local Flood Risk Management Plans, published in June 2022, set out in more detail how measures in the Strategies will be delivered. Flood Risk Management in Scotland is reviewed every six years and the current Strategies and Plans are valid until 2021 and 2022, respectively.
SEPA prioritised 42 flood protection schemes for inclusion within Flood Risk Management Strategies published in 2015. Local authorities are expected to start work on development of the 42 schemes prioritised in this cycle but it is recognised that construction work may not be completed within that six-year timeframe.
Flood protection schemes can have impacts on individuals, communities and the environment, and require careful and thorough planning.
Schemes (a) under construction are as follows:
Scheme
(ii)
Properties protected
(i)
Completion
Date
(iii A)
Initial cost
(£ million) (1)
( iii B)
Estimated final cost
(£ million) (2)
Stonehaven
376
2021
19.9
27.5
Smithton and Culloden
129
December 2020
15.2
13.0
Hawick
900
Winter 2022/2023
37.4
80
Upper Garnock
470
2022
15.5
18.5
Broughty Ferry
450
2022
10.0
16.2

Schemes (b) under development are as follows:

Scheme
Stage
(ii) Properties protected
(iii A)
Initial cost
(£ million) (1)
( iii B)
Estimated Final Cost of Scheme (2)
Arbroath
Confirmed
530
11.4
12.5
Caol and Lochyside
Confirmed
296
8.4
9.8
Water of Leith (Coltbridge, Gorgie, Saughton) Phase 3
Confirmed
75
Not held
Not held
Kilmacolm – Glenmosston Burn
Confirmed
Not held
0.5
0.5
Port Glasgow
- Bouverie Burn
Confirmed
Not held
0.4
0.4
Quarrier’s Village
Confirmed
60
0.2
0.2
Drumnadrochit
Confirmed
24
3.4
3.7
Campbeltown
Confirmed
770
9.3
9.3
Dumfries
- Whitesands
Confirmed (subject to appeal period)
166
18.9
29.2
Kirkintilloch
- Park Burn
Under development
Not held
0.4
0.4
South Fords
Under development
58
1.4
1.4
Stranraer
Under development
360
0.4
1.0
Langholm
Under development
200
2.0
8.0
Newton Stewart/ River Cree
Under development
280
7.5
12.5
Musselburgh
Under development
2100
8.9
10.6
Haddington
Under development
370
8.5
8.5
Grangemouth FPS
Under development
3000
111.5
220
St Andrews
- Kinness Burn
Under development
133
3.2
3.2
Millport Coastal
Under development
657
12.1
27.5
Mill Burn Millport
Under development
124
1.1
1.1
Comrie
Under development
290
15.7
27.8
Milnathort
Under development
30
1.9
2.2
South Kinross
Under development
211
3.2
3.6
Scone
Under development
44
0.7
0.7
Bridge of Allan
Under development
Not held
4.4
6.1
Stirling
Under development
Not held
26.2
29.0
Callander
Under development
30
2.4
3.0
Dumbarton
- Gruggies Burn
Under development
370
14.5
15.0
(1) Note: Initial costs as provided by local authorities in 2016-17.
(2) Note: Final Scheme costs are the latest estimates provided by local authorities. Prioritisation occurs once every 6 years. As such, flood protections schemes and works are put forward for prioritisation at various stages of initial development. As further details become available through hydraulic modelling, site investigations etc. uncertainties are reduced and expected final costs will vary.
Schemes will only be taken forward for construction if they receive the necessary approvals so the expected completion date is not yet known.
More detailed information on each of the schemes can be obtained from the relevant Local Authorities.