Written Question · S5W-32871 · Session 5
Further to the answer to question S5W-10494 by Roseanna Cunningham on 15 August 2017, which of the 42 formal flood protection schemes or en…
The question
To ask the Scottish Government, further to the answer to question S5W-10494 by Roseanna Cunningham on 15 August 2017, which of the 42 formal flood protection schemes or engineering works have been completed, broken down by (a) the number of properties being protected, (b) the completion date and (c) what the (i) initial forecast and (ii) final cost was of each.
The answer
Details are as follows:
Scheme
(a) Properties Protected
(b) Completion Date
(c)(i) Initial Cost
(£ million) (1)
(c) (ii) Estimated Final Cost
(£ million)
Huntly
63
2017
4.9
3.8
Newmill
18
2017
1.9
1.8
Dundee
200
2018
6.2
6.9
Kirkwall
750
2018
1.8
1.8
White Cart Water Phase 3
100
2019
5.9
7.2
Camlachie Burn
410
2019
1.2
1.7
Broxburn (Liggat Syke)
Not held
2019
Not held
Not held
New Cumnock Phase 1 Complete
Phase 2 Under construction
95
P1 2018
P2 July 2022
3.3
6.2
(1) Note: Initial costs as provided by local authorities in 2016-17.
Scheme
(a) Properties Protected
(b) Completion Date
(c)(i) Initial Cost
(£ million) (1)
(c) (ii) Estimated Final Cost
(£ million)
Huntly
63
2017
4.9
3.8
Newmill
18
2017
1.9
1.8
Dundee
200
2018
6.2
6.9
Kirkwall
750
2018
1.8
1.8
White Cart Water Phase 3
100
2019
5.9
7.2
Camlachie Burn
410
2019
1.2
1.7
Broxburn (Liggat Syke)
Not held
2019
Not held
Not held
New Cumnock Phase 1 Complete
Phase 2 Under construction
95
P1 2018
P2 July 2022
3.3
6.2
(1) Note: Initial costs as provided by local authorities in 2016-17.