Written Question · S6W-24035 · Session 6
Further to the answer to question S5W-10494 by Roseanna Cunningham on 15 August 2017, which of the "42 formal Flood Protection Schemes or e…
The question
To ask the Scottish Government, further to the answer to question S5W-10494 by Roseanna Cunningham on 15 August 2017, which of the "42 formal Flood Protection Schemes or engineering works proposed for 2016-21" have been completed to date, broken down by (a) the number of properties being protected, (b) completion date and (c) the (i) initially forecast and (ii) final cost of each.
The answer
Information has been shared in response to similar questions many times (at least annually) since Roseanna Cunningham answered on 15 August 2017, most recently in response to Willie Rennie MSP on 9 November 2023.
The following formal flood protection schemes are complete.
Scheme
(a) Properties Protected
(b) Completion Date
(c)(i) Initial Cost
(£ million) (1)
(c) (ii) Estimated Final Cost
(£ million) (2)
Huntly
63
2017
4.9
3.8
Newmill
18
2017
1.9
1.8
Dundee
200
2018
6.2
6.9
Kirkwall
750
2018
1.8
1.8
White Cart Water Phase 3
100
2019
5.9
7.2
Camlachie Burn
410
2019
1.2
1.8
Smithton and Culloden
129
2021
15.2
10
Bouvrie Burn
Not held
2020
0.4
0.4
Broxburn (Liggat Syke) Phase 1
Not held
P1 2019
Not held
Not held
New Cumnock
95
2022
3.3
8.4
Broughty Ferry
450
2022
10
16.3
Drumnadrochit
35
2022
3.4
5.1
Stonehaven
376
2023
19.9
27.5
Arbroath
530
2023
11.4
13.5
Caol and Lochyside
290
2023
8.4
15.2
(1) Note: Initial costs as provided by local authorities in 2016-17.
(2) Note: Final Scheme costs are the latest estimates provided by local authorities. Differences between these latest estimates and initial cost estimates arise because flood protection schemes are put forward for prioritisation at various stages of their development to fit with Flood Risk Management Planning cycle set out in the FRM Act. Costs are revised over time as designs are finalised and more detailed investigations are carried out (e.g. site investigation, utility investigation, hydraulic modelling), and as new information emerges (e.g. new flood mapping, climate projections, new source of risk, landownership challenges). Outcomes from community engagement and changes to price and supply of materials may also require revisions to cost estimates.
The following formal flood protection schemes are complete.
Scheme
(a) Properties Protected
(b) Completion Date
(c)(i) Initial Cost
(£ million) (1)
(c) (ii) Estimated Final Cost
(£ million) (2)
Huntly
63
2017
4.9
3.8
Newmill
18
2017
1.9
1.8
Dundee
200
2018
6.2
6.9
Kirkwall
750
2018
1.8
1.8
White Cart Water Phase 3
100
2019
5.9
7.2
Camlachie Burn
410
2019
1.2
1.8
Smithton and Culloden
129
2021
15.2
10
Bouvrie Burn
Not held
2020
0.4
0.4
Broxburn (Liggat Syke) Phase 1
Not held
P1 2019
Not held
Not held
New Cumnock
95
2022
3.3
8.4
Broughty Ferry
450
2022
10
16.3
Drumnadrochit
35
2022
3.4
5.1
Stonehaven
376
2023
19.9
27.5
Arbroath
530
2023
11.4
13.5
Caol and Lochyside
290
2023
8.4
15.2
(1) Note: Initial costs as provided by local authorities in 2016-17.
(2) Note: Final Scheme costs are the latest estimates provided by local authorities. Differences between these latest estimates and initial cost estimates arise because flood protection schemes are put forward for prioritisation at various stages of their development to fit with Flood Risk Management Planning cycle set out in the FRM Act. Costs are revised over time as designs are finalised and more detailed investigations are carried out (e.g. site investigation, utility investigation, hydraulic modelling), and as new information emerges (e.g. new flood mapping, climate projections, new source of risk, landownership challenges). Outcomes from community engagement and changes to price and supply of materials may also require revisions to cost estimates.