Forth Replacement Crossing

Wednesday 7 September 2011 Infrastructure and Capital Investment Committee About 10:00 Evidence session 113 contributions · 9 speakers

Speakers

Showing Malcolm Chisholm only · show everyone

Malcolm Chisholm’s contributions

4 contributions
Malcolm Chisholm Lab Edinburgh Northern and Leith
link

Mr Climie said that the project is on time and on budget. I think that the biggest concern for the public, particularly given recent events in Edinburgh, is to what extent the contract will ensure that there is no great increase in the budget. What guarantees can you give about that? Obviously, there can be unforeseen circumstances, so to what extent has that risk been transferred? Is it still possible that there will be quite an increase in the amount of public money that will be required for the project?10:15

Malcolm Chisholm Lab Edinburgh Northern and Leith
link

Apart from inflation, what changes represent possible risks to the public purse?

Malcolm Chisholm Lab Edinburgh Northern and Leith
link

I might be repeating debates from the past, but is it critical that the new bridge be completed by 2016—based on information about the old bridge—or would delay beyond that date simply mean a risk of cost overruns?

Malcolm Chisholm Lab Edinburgh Northern and Leith
link

Is it true that the latest prediction is that the old bridge could be used until 2021 or have I been misinformed?

  1. 10:00 Decision on Taking Business in Private Procedure · 1
  2. 10:00 Forth Replacement Crossing Evidence session · 113

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.