Depending on where one stands in the argument, one of the benefits or dangers of a bridge project is the fact that, unlike a road, train or trams project, a bridge project cannot stop halfway. You mentioned that you have world class road-building, bridge-building and civil engineering companies involved. I am pretty sure that the companies that were involved in the Edinburgh trams project would have described themselves similarly. What safeguards are there for the taxpayer to ensure that any conflict or disputes between the different parties that are involved will be resolved quickly and cheaply?
Official Report · Committee
Forth Replacement Crossing
Speakers
Showing Neil Findlay only · show everyone- David Climie Transport Scotland 28
- Lawrence Shackman Transport Scotland 24
- Maureen Watt SNP 16
- Jamie Hepburn SNP 15
- Jackson Carlaw Con 12
- Neil Findlay Lab 8
- Malcolm Chisholm Lab 4
- Adam Ingram SNP 4
- Gordon MacDonald SNP 2
Neil Findlay’s contributions
8 contributionsI also assume that you will be reporting back to the committee at regular intervals and that we will—I hope—be alerted to any such potential problems as the contract goes through.
I was not a member in the previous session of Parliament, but I assume that all the contractors have evidenced their competence and ability to deliver. What steps are being taken to future-proof the bridge? Equally important, what steps are being taken to ensure that it is not expensively overengineered?
In order to allow us to do some research, would you point to the bridge in Hong Kong as being a successful example of how such a project should be managed or would you suggest somewhere else?
I am talking about the management of the project and finding out how successful it was.
I am sure that the convener will arrange a trip to Washington for us.
On the issue of community liaison officers, in other projects that I have been involved in, a compliance officer who has been paid for by the contractor and appointed by the local authority, in consultation with the community, has worked with the community to ensure that all the community engagement aspects of the project that have been agreed by the contractor happen. This project seems different, as the community liaison officer is appointed by, and ultimately works for, the contractor. I would be more comfortable with a situation in which the contractor paid the money but the community liaison officer worked on behalf of people in the community to ensure that their concerns were addressed. Will you comment on that?
I do not doubt your sincerity; I am saying only that, in my experience of such projects in other areas, a lot of warm words are said but it is the action that proves whether the arrangements work. I am sure that your approach is genuine. We will see how the situation develops.
In this meeting
Everything on 7 Sep 2011 →- 10:00 Decision on Taking Business in Private Procedure · 1
- 10:00 Forth Replacement Crossing Evidence session · 113
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.