We will now hear evidence from representatives of the Forth replacement crossing team in Transport Scotland. The aim of the session is to gain a brief overview of the project so far, and to hear updates on current and upcoming work. I welcome the witnesses, who are David Climie, the project director of the FRC team, and Lawrence Shackman, the project manager of the team. I invite them to make a brief opening statement.
Official Report · Committee
Forth Replacement Crossing
Speakers
Showing Maureen Watt only · show everyone- David Climie Transport Scotland 28
- Lawrence Shackman Transport Scotland 24
- Maureen Watt SNP 16
- Jamie Hepburn SNP 15
- Jackson Carlaw Con 12
- Neil Findlay Lab 8
- Malcolm Chisholm Lab 4
- Adam Ingram SNP 4
- Gordon MacDonald SNP 2
Maureen Watt’s contributions
16 contributionsThank you. Mr Shackman, do you want to add anything?
I wondered whether you were fishing for a trip.As there are no further general questions on the update on progress on the project, we will move on.10:30
I am not sure at what wind speed the current crossing must be shut. At what wind speed will the new crossing have to be shut, if at all?
Do you know at what wind speed the current bridge must be shut?
If no one else has any questions on that area, we will move on to community engagement. Jackson Carlaw has a question.
I think so.
What do you intend to do regarding the hours that are worked? One of the main problems encountered by communities that are affected by such projects involves disturbance at night. Will it be a 24-hour operation?
Have there been any problems with land acquisition?
We move on to traffic management during the construction of the Forth replacement crossing. Adam Ingram has some questions.
We move on to CO2 emissions. Our predecessor committee in the previous session of Parliament had some questions about emissions. Transport Scotland officials advised us:“As part of the tender process, we are asking contractors to give us their response on carbon. When we have that information, we will have a better figure with which to respond to your question.”—Official Report, Transport, Infrastructure and Climate Change Committee, 2 February 2010; c 2528.Transport Scotland officials indicated at their previous appearance before the committee that the release of that information would have to wait until the announcement of the successful bidders. Can you now give us an estimate of greenhouse gas emissions for the construction of the crossing?
Can you give us some idea of the cause of that difference?
Is that how you intend to offset CO2 emissions? If not, how will they be offset in the context of our climate change targets?
I think that we will return to that matter in future meetings.Will you say something about community benefit clauses in the contracts, the hiring of apprentices and the work that is going on with Skills Development Scotland, the Department for Work and Pensions and contractors to get into work people who might not have been in work recently?
As most members of the committee are new to the project, can you give some idea of how many people you estimate will be employed on it? I presume that a number of the bidders will use subcontractors. Where do they envisage getting their labour from?
I thank both witnesses for attending the meeting and providing us with an update on the most significant infrastructure project in Scotland. I hope that your biannual oral updates, which were introduced by our predecessor committee, will continue and be supplemented by written updates between the sessions. We would like an early indication of any problems or successes if anything major crops up in the project. We need to visit the site as soon as possible to get a visual idea of the project.Once the witnesses have left the room, we will continue in private as agreed under item 1.11:11 Meeting continued in private until 11:25.
In this meeting
Everything on 7 Sep 2011 →- 10:00 Decision on Taking Business in Private Procedure · 1
- 10:00 Forth Replacement Crossing Evidence session · 113
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.