I want to ask about the connecting road network for the proposed new crossing. Why will the new crossing be connected to the existing road network by dual carriageway rather than by motorway-standard roads?
Official Report · Committee
Forth Replacement Crossing
Speakers
Showing Charlie Gordon only · show everyone- John Howison Transport Scotland 40
- Patrick Harvie Green 19
- Des McNulty Lab 16
- Charlie Gordon Lab 9
- Mike Glover Transport Scotland 8
- Kathryn McKee The BIG Partnership 7
- Margaret Smith LD 7
- Shirley-Anne Somerville SNP 6
- Frazer Henderson Transport Scotland 3
- Alison McInnes LD 1
Charlie Gordon’s contributions
9 contributionsSo it will be as close to motorway standard as is possible but, because of the necessity of having a junction, it will not be categorised as motorway.
Have you modelled the possible congestion impacts of that decision? If so, what were the results?
Will you model your proposals?
Can you comment on the current condition of the existing Forth road bridge and advise whether, in the long term, it will be able to cope with its proposed new role as a dedicated public transport corridor?
That was a comprehensive answer in relation to loading, but the other problem with the sole use of the bridge by public transport is the fact that 30 or 40 days a year can be lost due to wind conditions. Would that have an impact on public transport? It will be difficult to get people to leave their cars at home if their public conveyance might not be able to cross the Forth 30 or 40 days a year.
You can see my next question coming, I am sure. Will there be a similar diversionary route for trams?
For completeness, can you say anything about the role of park-and-ride facilities in the public transport scenarios that we are talking about?
Is it your understanding that the Scottish Government guarantees that the current Forth road bridge will not be reopened to general traffic following completion of the new Forth crossing, even if cross-Forth traffic congestion continues to increase?
In this meeting
Everything on 23 Jun 2009 →- Scottish Parliament Transport, Infrastructure and Climate Change Committee Tuesday 23 June 2009 Committee business · 1
- Decision on Taking Business in Private Procedure · 2
- Road Safety Framework Committee business · 90
- Forth Replacement Crossing Evidence session · 116
- Budget Process 2010-11 Committee business · 7
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.