FETA and its chief engineer would be the authority on that, but we work closely with them.The problem with the existing bridge that captures most attention is the distress in the suspension cables, which have already lost about 10 per cent of their strength. The aim is to stabilise that deterioration through a dehumidification process. There are many other problems, however.The committee will be aware that, because of the heavy goods traffic on the bridge, the resurfacing—which takes a whole summer to do—lasts only about eight years. That situation is likely to get worse. There are things called half-joints between the main joints on the bridge, where one beam rests on another, and they are suffering extreme distress as a result of heavy goods vehicles. The committee is probably aware that a contract was to have been issued for the renewal of the main joints, but FETA decided to suspend that when the construction of the new bridge and the timetable for that was confirmed. That work will be done later, which will result in a considerable saving.There are operational disadvantages to the bridge as well. For example, it has no hard shoulder, so any traffic incident will cause a problem. For 30 to 40 days a year, it is closed to high-sided vehicles and, whenever a member of the public decides to climb up the cables—which I understand is quite easy to do because of the slope on the cables—the road is closed until the person is removed from the bridge.The question is: with all of those disadvantages, how satisfactory will it be for public transport? We have considered that from two angles. One is the issue of the loading of the bridge and the other is the articulation of the bridge.On loading, one must realise that the bridge uses about 85 per cent of its strength to keep itself up and about 15 per cent to cope with traffic loading. By removing general traffic from the bridge and using the bridge only for public transport, we will reduce the loading by such a degree that—if the cable stabilisation process is successful—we will be able to use the bridge for public transport without any further immediate concerns about the cables.What I have just said concerns public transport in the form of buses, but we also considered whether the bridge might be capable of accommodating light rail transit in the form of trams. We conducted an analysis of the effects of stripping off part of the existing deck and replacing it with the equipment that would be required by trams, and we concluded that that would be acceptable as far as loading was concerned. The majority of the options that we considered reduced the load. Further, because the number of trams on the bridge can be controlled, we can control the loading on the bridge more precisely than we can if heavy goods vehicles are using it.We are satisfied that, subject to stabilisation of the suspension cables, the bridge should be capable of carrying the live load of public transport as well as the dead load of the equipment that would be required if trams were using the bridge.We considered whether the articulation of the bridge—that is, the movement that is caused as a vehicle goes across the deck, under the towers and across to the other side—would be excessive for a tram, and we came to the conclusion that it would not be.The work that we have done, as we have reported on our website, satisfies us that the bridge will be satisfactory for public transport. Should the stabilisation work on the suspension cables not be successful, we believe that the cables can be replaced without interruption to public transport, as those vehicles could be concentrated on one carriageway. However, that would require additional work, and we would consider it only if the dehumidification were unsuccessful.Mike, would you like to add anything to that?