Forth Replacement Crossing

Tuesday 23 June 2009 Transport, Infrastructure and Climate Change Committee Evidence session 116 contributions · 10 speakers

Speakers

Showing Des McNulty only · show everyone

Des McNulty’s contributions

16 contributions
Des McNulty Lab Clydebank and Milngavie
link

I have two, convener. It is always difficult to summarise such documents, but I tend to look at the numbers and focus on the concerns that were highlighted most frequently. The four highest figures relate to concerns about the display of inaccurate images at exhibitions; concerns about lack of consultation with residents of Dundas home farm, which was raised 19 times; concerns about the effectiveness and validity of the consultation process and whether views will be considered and feedback provided; and requests for information about why the proposals changed from those that were consulted upon in August 2008 and why those who would be affected were not consulted.The replies to those concerns are among the weakest responses that you came up with. Given that your own document shows that they are the main things that were thrown up, do you believe that your specific responses to those four points are adequate?

Des McNulty Lab Clydebank and Milngavie
link

The convener, Shirley-Anne Somerville, Margaret Smith and I attended a meeting in Queensferry that was attended predominantly by people from the Dundas home farm estate, who are concerned about the process that they have experienced and the project's impact on them. Their concerns have two strands. The first is that, as Mr Howison just said, the story kept changing and the impact that was presented in the first instance was not what was subsequently presented—it was perpetually modified. The second and more substantive point is that those people feel that the route choice and the road network fundamentally disadvantage them, and that less disadvantageous alternatives for them could have been considered. I simply ask whether, even at this late stage, an opportunity exists to fulfil their wish for the impact on them to be considered as part of a re-engineering or reorganisation of the access routes to the bridge.

Des McNulty Lab Clydebank and Milngavie
link

I wish to move on to budget issues. One or two of you might be able to relax; others can respond. The Scottish Government's current cost projections indicate that the new Forth crossing will cost between £1.7 billion and £2.3 billion, which suggests an area of uncertainty of £600 million. That is clearly a high level of uncertainty. How is that uncertainty being managed down, given the stage that you are at in defining the cost of the bridge? What risks are being removed as part of that process of refining the cost?

Des McNulty Lab Clydebank and Milngavie
link

No, your explanation has been reasonably straightforward. However, would it not be more sensible to publish the risk-adjusted spot price that you are more certain of and allow us to examine the substance of those costs? After all, providing 2016 costs for the bridge simply introduces unnecessary uncertainty and, as far as I understand it, is not the practice that you follow in other projects. For example, the costs for the Aberdeen western peripheral route reflect the point at which they were identified instead of being projected ahead.

Des McNulty Lab Clydebank and Milngavie
link

But according to your earlier explanation, you have a spot price that you can measure the risk on, known variables and so on. As a result, you have a number that you can be relatively definite about. However, with the 2016 costs that you have given us, there are areas about which you cannot be definite, which means that you are introducing unnecessary uncertainty. I am sorry, but I do not follow the logic of not giving us the price that you can quantify as close to certainty as is possible.

Des McNulty Lab Clydebank and Milngavie
link

Do you want to put them on the record? What is the actual cost, excluding inflationary assumptions for the future?

Des McNulty Lab Clydebank and Milngavie
link

Can you give the committee the actual costs as you have them, based on a more accurate measurement than that which produced the range of £1.7 billion to £2.3 billion?

Des McNulty Lab Clydebank and Milngavie
link

That would be useful. I will stipulate which bits of information we want—

Des McNulty Lab Clydebank and Milngavie
link

That would be useful. Can you give us a breakdown that includes the cost of the connected roads, the bridge construction costs, consultancy fees and so on? In the initial consultation, the figure that was given was about £3.7 billion. How on earth is it that you consulted on a bridge that in principle would cost £3.7 billion but you now think that the actual cost of the project, when you have sorted out the risk, will be £1.1 billion? That is not a minor adjustment, is it?

Des McNulty Lab Clydebank and Milngavie
link

You must accept that people will be concerned at a price that varies from £1.1 billion to between £1.7 billion and £2.3 billion, and then to £3.7 billion. I accept that the £3.7 billion figure is for a different design of project, but the variation is still very wide. The poor member of the public is left saying, "We're always comparing apples with pears, even though we're talking about the same bridge." You never provide us with a basis on which to compare costs. When we consider how the Danes, the Koreans or others are bridging estuaries, they seem to be able to do it more cost-effectively than we can—based on your previous figures. However, you now seem to be saying that the real figure is £1.1 billion, which might bear more comparison with what the Danes and Koreans are doing.

Des McNulty Lab Clydebank and Milngavie
link

When I consider other capital projects—perhaps not of the same scale as this project, but of the nearest scale, if I can put it that way—I see that a different accounting methodology is employed when it comes to time scales, or time base, in order to calculate the cost. The cost projections for the M74 extension, for the Aberdeen western peripheral route, for Borders rail and other projects are not estimated on a cost base that is seven or eight years ahead of now. They are projected either on a current time base or, sometimes, on an historical time base. That gives an accurate basis for calculations, and, as I said earlier, means that we do not have to make heroic assumptions about future inflation.With this project, it seems that a substantial element of the projected cost is based on inflation assumptions that may or may not turn out to be true. Surely a better way of understanding the cost of the bridge is likely to be based on knowledge that we have now about what the actual cost will be, based on matters about which we can be relatively certain. In the future, we might have to adjust the figure, perhaps if the assumptions turn out to be wrong or because of other circumstances, such as inflation. However, while the Scottish Government came up with 2016 prices for a range of projects—two bridges and a tunnel—the 2016 price for the current crossing has turned out to be way beyond what anyone now anticipates it will cost. You now tell us that the actual figure, based on current prices, for the bridge that you propose to build is roughly a quarter of that initial projected cost.I am not an accountant, but I have sat on Finance Committees for long enough to know that that is a strange way of doing things and a strange way of explaining the matter to the general public. We need defined and clear information that is based on what we know. We can then make comparisons and judgments about what you are doing, and you will not be able to hide behind assumptions or financial projections over which you have little or no control.

Des McNulty Lab Clydebank and Milngavie
link

Yes, but the baseline approach that you are adopting for the bridge project is different from the approach in other projects.

Des McNulty Lab Clydebank and Milngavie
link

If you look at the current cost projections for the Aberdeen western peripheral route or the M74 project, you will find that that is not the case. You might have to go away and consider the issue, but I have asked enough parliamentary questions about the way in which such projects are costed to know that the basis of the Forth bridge project is different. I cannot pursue the point further today, but it strikes me as strange that you have come up with such vastly different figures for the cost of a single bridge.

Des McNulty Lab Clydebank and Milngavie
link

One of the issues about the crossing is that the funding mechanism is not clear. I presume that the Government will have to come up with a proposition for how the project will be funded. The Government will have to say to the banks, the Westminster Government or other stakeholders, "This is what we want to do for this amount of money." Is the way in which you have set out the proposals the best way of establishing a funding mechanism and funding certainty for the people whom you seek to engage as partners?

  1. Scottish Parliament Transport, Infrastructure and Climate Change Committee Tuesday 23 June 2009 Committee business · 1
  2. Decision on Taking Business in Private Procedure · 2
  3. Road Safety Framework Committee business · 90
  4. Forth Replacement Crossing Evidence session · 116
  5. Budget Process 2010-11 Committee business · 7

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.