Item 3 is an update on the Forth replacement crossing. During topical questions yesterday, Mr Brown confirmed that the opening of the Forth replacement crossing is likely to be delayed. The cabinet secretary contacted me yesterday to ask whether the committee would be prepared to hear further details on the matter in light of that confirmation.
I welcome Keith Brown, the Cabinet Secretary for Economy, Jobs and Fair Work. I also welcome back David Climie—despite the fact that when we last met I said that I hoped that I would not see him again until we were looking at a wash up of the project—Sally Cox, chair of Forth Crossing Bridge Constructors and Michael Martin, the project director.
Cabinet secretary, would you like to give a brief opening statement?
Thank you, cabinet secretary. I am sure that the committee will want to consider what it sees as appropriate intervals between reports from you on the bridge. We will discuss that later.
Can you confirm that it was on Monday 27 March that you first got an inkling that the bridge would not be open within the timescale that we were given on 8 March?
A lot of people in Scotland will believe that we have had one of the mildest and best winters that we have had for a long time—perhaps an open winter would be a better description of it. Can you give some idea, from a planning point of view, of how this winter’s weather conditions have been different from those of the past 10 years? Was it easier or less easy to work this winter than in previous winters? I am talking not only about wind but also snow, rain and the other types of weather that we have had less of this year.
David Climie, do you want to come in on that? Some people will be concerned that they still do not understand why, after such an open winter, there are further delays.
Can I push you a bit on that, cabinet secretary? I am assuming that you have no wish to once again come before the committee or, indeed, the Parliament to say that there will be a further delay. A wise man would say that delivery of the project and opening of the bridge to transport by the end of August was a 100 per cent possibility. I cannot believe that that is not the case. What possibility is there of completion in mid-July? Is that a 10 per cent possibility, or a 2 per cent possibility? Without criticising anyone for delays, people will know what the probability is that completion will fall at various points in the timescale.
When the first crane was taken down, were the other cranes no longer required? Could they not all have been taken down at the same time? I would have thought that that would be a reasonable question.
I thank all our witnesses for coming to the meeting. As I said in my opening remarks, I previously made the mistake of saying that I hoped that I would not be seeing you again. This time, I suspect that I might. Cabinet secretary, could the committee get back to you after the meeting to say when we would like to programme an update on the bridge, so that we can be kept apprised of how things develop?
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.