Forth Replacement Crossing

Wednesday 29 March 2017 Rural Economy and Connectivity Committee About 10:30–11:15 Committee business 61 contributions · 13 speakers

Speakers

Showing Keith Brown only · show everyone

Keith Brown’s contributions

16 contributions
Keith Brown SNP The Cabinet Secretary for Economy, Jobs and Fair Work · Clackmannanshire and Dunblane
link

I will be as brief as I can, convener. I thank you for the opportunity to come to the committee at short notice.

On 8 March, I provided the committee with a brief update, which was followed by a more detailed progress report from Transport Scotland. At that time we advised the committee that the contractor, FCBC, was targeting a May completion date. Notwithstanding the regular assurances about completion received from FCBC, I challenged FCBC to provide a guarantee on the opening-to-traffic date, which the committee asked about when I appeared before it on 8 March.

As a result of the challenge, and as described in detail by David Climie in his evidence to the committee, FCBC carried out a further programme review based on the progress made and the impact of weather. As part of that challenge, Transport Scotland and I stressed to FCBC the continued focus on maintaining health and safety as a top priority—I know that it is at the forefront of everything that it does. In order for the review to be as robust as possible, FCBC brought in planners and experts from around the world. The review took full account of the likely weather impacts going forward and the implications of complex interrelated operations being carried out simultaneously.

Transport Scotland and I received the results of the review from FCBC on Monday 27 March. Since then, Transport Scotland has considered FCBC’s plans carefully and has discussed the matter with the FCBC board, led by Sally Cox, who is here today. I received Transport Scotland’s assessment last night and I will now share it with the committee.

Only nine weeks remain before the end of May and the review concluded that, even with the best weather—and we can see that the weather today is not the best—a May opening-to-traffic date is not now safely achievable. At this stage in the project, a day lost to weather cannot be recovered and that has a direct impact on any follow-on activities.

Since the start of 2017, there have been fewer clear weather windows than expected, particularly because of the wind. That has delayed weather-dependent activities, causing them to bunch together at the end of the programme to a much greater degree than was anticipated last May.

The effect is very visible in the removal of the tower cranes. The cranes can be dismantled only in wind speeds of less than 25mph. While crane removal is under way, it is not possible to safely work within a 50m radius of the crane itself, so that site activity alone has the effect of sterilising the deck beneath and preventing any work to the adjacent stay cables. It also has an impact on all deck-level activity, such as waterproofing and surfacing.

As anyone who crosses the Forth can attest, although recent good weather has helped, it has not yet been possible to bring down the cranes. In fact, I believe that on Monday this week, which to all of us was a glorious day, the wind speed was again too high to carry out operations at that height.

FCBC also acknowledges that, given the uniqueness of the project, the onerous conditions that have been experienced in working at height over the Forth have created more challenges than it had anticipated. At this stage in the project, all remaining activities are vulnerable to weather conditions. That vulnerability differs depending on the activity. Whereas tower crane removal and work on cable stays is sensitive to wind, waterproofing of the deck is sensitive to rain, and surfacing is sensitive to rain and very low temperatures.

FCBC’s May 2016 programme acknowledged that complexity. However, at that time, in order to maximise deck availability, the activities were sequential and largely independent of each other. Due to slippage during recent months, the activities are now interdependent and often simultaneous. Consequently, they are reliant on complex planning and favourable weather conditions. When the weather conditions are unsuitable for one activity, that has a compounding effect on the subsequent activity and the concurrent activities, many of which are critical.

Taking all that into account, FCBC is now advising that the opening-to-traffic date is more likely to be between mid-July and the end of August. To put that in context, it is around a four to 10-week delay on a six-year construction programme. The precise opening date will depend on the amount of weather down time that occurs during the coming weeks, with the latest date being based on weather similar to that which we have seen in February and March continuing to occur.

That would mean up to 75 per cent down time on the critical path activities that are particularly sensitive to wind speeds of 25mph or more, such as tower crane and tower falsework removal, and finishing works on the towers and stay cables. Although that level of down time is not anticipated at this time of year, past experience has shown that it is possible, so it should be taken into account. With so much simultaneous activity already under way, there are no opportunities to mitigate the effects of weather delays at this point in the construction programme.

FCBC has assured me that it is fully supporting Michael Martin, the project director, in providing the resource that is required to complete the project at the earliest possible date. That is clearly demonstrated by the fact that the site has never been busier, as a result of an additional 200 people being employed to help complete the bridge. More than 1,500 people are now working on the site, with operations continuing on a 24-hour basis, seven days per week, whenever the weather permits. Plant equipment and workers are being kept on standby, at considerable cost to the contractor, so that no weather window is missed.

It is very important to stress that the costs that are associated with the overrun will be fully covered by the contractor and so will not result in any increase to the overall cost to the taxpayer, which stands at £1.35 billion, as before. The £250 million of savings that have been released since the construction started are secure.

The potential overrun on the contractual completion date of between four and 10 weeks is a huge disappointment to me and to everybody who is involved with the project, but it should be kept in perspective in terms of infrastructure projects of this size and complexity. The Queensferry crossing will be completed in six years from the date that construction started and within 10 years of being first committed to by the Scottish Government in December 2007, at a considerable saving to the taxpayer.

Although we have not met our original ambitious targets for opening, which was to open six months ahead of the contractual completion date of mid-June, it should be noted that the project remains an outstanding achievement for everyone involved, and it will provide the people of Scotland with a resilient structure that is fit for the 21st century. It is already a world record breaker. It is being built in weather that saw two heavy goods vehicles being blown over on its sister structure in the past two months alone. It is also significantly under budget.

The crossing has a design life of 120 years. I hope that committee members will be able to exercise a degree of perspective when they hear of a four to 10-week overrun into the summer period, on a six-year project that already had a year of contingency factored into its planning.

The bridge is a project that Scotland can be proud of. As we complete it, we will not compromise the extraordinary quality of the construction or the safety of the workforce. The important thing at this stage is that none of us push the contractor to compromise the safety of the workers who we trust to work in all weathers to deliver this high quality and iconic structure for us.

As I have said before, I want to ensure that members remain fully apprised of progress on the project and all other major transport projects, so I commit to providing a further update to the committee at the end of May. Of course, the committee can ask for updates at any time, but I will provide an update at the end of May on the progress that has been made during the next two months and an update on the opening-to-traffic date.

The bridge is substantially complete. It will stand for a century or more. It is frustrating that it will not be finished earlier, but my overriding priority is to have the bridge finished safely and to the highest standards of construction. It is already a stunning bridge. It has developed significantly since the committee last visited the site, which I think was last autumn. The committee might want to see the progress that has been made since then, and I am happy to ensure that that happens.

Keith Brown SNP Clackmannanshire and Dunblane
link

That is when I got the report from the contractor and met Sally Cox and others who are involved with the bridge.

Keith Brown SNP Clackmannanshire and Dunblane
link

Yes. That is when I got the written report.

Keith Brown SNP Clackmannanshire and Dunblane
link

I want to emphasise the wind factor. That is what has caused the problem. This year, we have had far fewer intervals. We have to see a 48-hour clear period coming for taking the cranes down from their current height, and we have not had those weather windows. Yesterday, in answer to the topical question in the chamber, I mentioned that it took 65 days to remove the one crane that has been taken down as opposed to the 15 days that it was supposed to take. That was because we have not had those windows with 48-hours notice. The weather forecast did not anticipate the fog today and it did not anticipate some of the wind that we had yesterday, which I believe stopped work on the towers. The consistency of the wind that we have had over that period has affected the crane removal in particular. It might be best if others come in on this issue, too, convener.

Keith Brown SNP Clackmannanshire and Dunblane
link

We have had this discussion before. It may be an uncomfortable fact for Mr Rumbles, but the project is nearly £0.25 billion below the budget that was set. Even that tender, when it came in, was substantially below the tender range that we set out for the project, which was from about £1.7 billion to £2.3 billion.

The current expected cost is £1.35 billion, which is a substantial reduction. Mike Rumbles quite rightly asked about the effect of inflation and forecast inflation, and I accept the point—inflation is a very big part of it. That would not be true in other projects, because the Government would not take on the risk of inflation—that would be done by other means and would rest with the contractor. We took the risk this time and we have had a big benefit from that, but very tight project management has added to those savings. We are about £200 million below budget.

Keith Brown SNP Clackmannanshire and Dunblane
link

The convener mentioned the fact that, at my previous meeting with the committee, I used the word “hope” a couple of times. Obviously, Transport Scotland talks regularly with the contractor as it works on the project and, as with other projects, the process is fairly straightforward. We asked the contractor to tell us what the programme is for the completion date, which the contractor produced on Monday, and at that point it was analysed by some specialist people employed by Transport Scotland for that purpose.

Only after that programme has been analysed and interrogated, which in this case was done in a very short space of time, do we agree to it. We do not just agree if a contractor comes forward to say that a project will be 10 months late. We do not just accept that and neither do we publish it at that time; we interrogate the programme and come to an agreed position with the contractor. That is the process that we have followed and it is the right way to do it. The contractor gives us in writing a programme of works that takes the project through to the completion date. That programme is properly analysed and we respond to that.

Keith Brown SNP Clackmannanshire and Dunblane
link

No. Discussions were going on all the time between Transport Scotland and the contractor. David Climie from Transport Scotland is on site all the time and he sees the issues—he will have seen the issue with the cranes. Of course, the question was whether the project could be finished by May, but the only way to answer that was to have the contractor’s programme properly analysed and brought back to us, which is what happened on Monday.

Keith Brown SNP Clackmannanshire and Dunblane
link

When I came to the Parliament last year, I was asked to guarantee the date of May this year and I did not do that, because I could not—weather is the master in this equation. There is a very high degree of certainty in the dates that have been provided to us of mid-July to August, but it is not absolute. We have just heard about the weather in March and April of last year and in January and February of this year. If the weather that we have been experiencing continues, of course it will have an impact on the programme, but the range of dates from mid-July to the end of August are the likely ones for when completion will fall. I have not given a specific date because of the variability of the weather. Rather than giving a specific date, we are taking the contractor’s confidence about when the bridge will be completed, which has been interrogated by Transport Scotland.

Keith Brown SNP Clackmannanshire and Dunblane
link

I also think that people will understand about the variability of the weather. I take the point from earlier on about people having experienced a generally mild winter. However, the towers have a completely different weather system—I do not know whether the committee went up the towers but I think that you will know that from being on the deck. For example, people check the wind speed on the website, but that is measured from the deck of the Forth road bridge, not from a tower. It is a completely different environment that high up, and that is where we are working to get the cranes down. That is the reason that I am not being definitive, although I would like to be definitive.

Perhaps David Climie can answer in relation to the relative confidence in the dates. I have said right through this process that weather is the master in this project. That remains the case, even though those dates are being provided.

Keith Brown SNP Clackmannanshire and Dunblane
link

I have never given and cannot give a 100 per cent guarantee.

Keith Brown SNP Clackmannanshire and Dunblane
link

It is a fact that the bridge will be open when it is open.

We had a fatality on the bridge last year—Mr John Cousins, on 28 April. Earlier, I said that the bunching effect of the cranes not being taken down puts lots of pressure on activities on the deck of the bridge, as lots of simultaneous activities are going on there. There are 1,500 people working all over the project now, and we have to have safety very much in mind.

The date range that we have given, of between mid-July and August, is what we believe to be likely. Whatever the actual date is, it will be subject to weather and safety. As I have said to the committee before, Michael Martin interviews every person who is starting work on the bridge, and the first question he asks them is, “What is the most important thing?” They all say, “Finishing the bridge” or whatever, and he says, “No, it’s safety”. Considerations around safety, as much as the weather, will drive how we complete the bridge.

Keith Brown SNP Clackmannanshire and Dunblane
link

That subject is more into my remit and Humza Yousaf’s remit. The difficulty that we had last year with the existing Forth road bridge has been resolved, and it has had a full health check since then. Apart from two drivers who went across the bridge when they should not have done, that bridge is operating extremely well. There is no threat to it, and it will continue to operate during the time that we are waiting for the new bridge to be completed.

The delay is obviously frustrating because the Forth road bridge is to be a public transport corridor, and we want to see it being used for that. There will be advantages in terms of bus timings and so on, and we want to see those advantages as quickly as possible. However, there are no implications for the existing bridge.

There is the question of the tie-in of the new road networks coming through, which are substantially complete. Anybody who has travelled that route will have seen how complete they are—especially on the south side. A tie-in has to be done at the appropriate time. However, as far as I am aware, there are no implications for the existing bridge, which will continue to service all the traffic that is currently there.

11:15

Keith Brown SNP Clackmannanshire and Dunblane
link

I rely very much on the advice that is provided by the contractors, as interrogated by Transport Scotland, and the dates that I have given are what they believe to be the likely ranges. I suppose that the worst-case date that they are giving us just now is the end of August. Of course, it is possible that we could have extremely different weather that could push that date back, but that is not the advice that we have been given. Jamie Greene is right in saying that I do not want to keep coming back to the committee with another date, but that is what I am being told by the contractors.

Jamie Greene’s other point was about the quality of what is being done. I think that it is a great project. Committee members will have seen that with their own eyes when they visited the site. The danger arises when somebody tries to short-cut something or do it to a lower standard, which can happen if they are pushed and put under pressure. We have been keen not to do that, not just to ensure safety but to make sure that the bridge is completed in the correct way. I am told that we can ensure both of those things within a window between mid-July and the end of August.

Keith Brown SNP Clackmannanshire and Dunblane
link

David Climie might want to come back on the points that he raised at the previous committee meeting. We faced the prospect of taking down one of the cranes, which we thought would take 15 days. The crucial part was getting it down to deck level, which is where the contractors need wind speeds to be lower, and that could be done in 15 days. At that stage, plans were put in place to take down the other two tower cranes concurrently rather than one at a time. At the time, it was felt that that would be possible if the contractors had the 48-hour windows that were mentioned previously. That is where the contractors were 30 days ago. Perhaps David Climie can say something further.

Keith Brown SNP Clackmannanshire and Dunblane
link

It is only fair to let the contractors answer that question, as they are responsible for the project and the decision is theirs. I commend the contractors for the effort that they have put into the project at substantial cost to themselves. Perhaps they can answer that question.

On Gail Ross’s point about the tower, I am sure that FCBC and Transport Scotland can make that happen for those who are able and willing. I am very surprised to hear that our colleague Murdo Fraser actually did go up the tower, given the way that he blanched when I invited him to do so in the first place. It is a stunning experience to look down on the other two bridges. We will make sure that that happens for those committee members who want to do it.

Perhaps FCBC will answer the point about employees.

  1. 09:00 Subordinate Legislation Subordinate legislation · 168
  2. 10:30 Forth Replacement Crossing Committee business · 61
  3. 11:15 Transport (Update) Evidence session · 73
  4. 12:00 Subordinate Legislation Subordinate legislation · 27
  5. 12:15 Seat Belts on School Transport (Scotland) Bill: Stage 1 Bill debate · 83

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.