To ask the Scottish Government, in light of recent reports regarding the MV Argyll Flyer, what actions are being taken to deliver improvements on the Dunoon to Gourock ferry service. (S7O-00541)
Official Report · Chamber
General Question Time
link
To ask the Scottish Government, in light of recent reports regarding the MV Argyll Flyer, what actions are being taken to deliver improvements on the Dunoon to Gourock ferry service. (S7O-00541)
As Jenni Minto will know, the MV Argyll Flyer unfortunately had to come out of service on the back of storm Boelo, due to the fact that it collided with something in the water. I had conversations with officials once I realised that the vessel was out of service, and I think that it was a log. As I have said to Jenni Minto previously, the Government is seeking to ensure through its vessels and ports plan that the vessels that serve the route are replaced. I believe that the timeline for that is around 2031 to 2036.
link
Given the consistent issues with the two vessels that service the route and the lack of a relief vessel, local community councils are now proposing that a single-vessel timetable be maintained on the route until new vessels are delivered. That would ensure that any mechanical issues with the vessels did not impact the service and would provide some much-needed reliability. Will the cabinet secretary support that proposal in the short term, until the new vessels are delivered? Although I appreciate the pulls on his diary, will he consider meeting my constituents?
link
I thank Jenni Minto for her kind invitation in that regard. We will see what we can do in as early a course as possible.
The wider suggestion that has been made is a thoughtful and helpful contribution from the community, and I will ensure that my officials take that forward with CalMac Ferries accordingly.
link
The cabinet secretary will be aware that there is increasing frustration among the local community councils, which now believe that they are repeatedly being palmed off by the Government with the promise of new vessels. According to the local council, the original plan was that they would be delivered in 2025, but the minister is now saying that another decade could pass before the communities get them. Is there no way that that could be speeded up?
link
The vessels and ports plan was produced at the same time as the islands connectivity plan during the previous session of Parliament—I believe that it was in 2025. It is important that we stick to that plan and seek to deliver its objectives.
Across the wider network, we are in the process of renewing a third of the entire CalMac fleet. I am sure that the Parliament will join me in expressing its delight that the MV Loch Indaal came into Caledonian Maritime Assets Ltd’s ownership just the other day. We hope that we will have it sailing over to Scotland very soon.
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.