How much has been spent on the procurement of the new IT system for NHS 24, including the cost of commissioning consultants.
Started with S4W-28718 on 27 Nov 2015; latest 12 Jan 2016. Each later question says it follows up an earlier answer.
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Government how much has been spent on the procurement of the new IT system for NHS 24, including the cost of commissioning consultants.
Shona Robison, 10 Dec 2015: The original business case cost the programme for replacement of the new system at £75.8 million. This has subsequently been revised and is now forecasted to cost £117.4 million. -
How much of the money spent on the procurement of the new IT system for NHS 24 was paid to external consultants.
Shona Robison, 6 Jan 2016: Of the £117.4 million total, contractor implementation costs are £36.8 million. -
How much of the additional £41.6 million spent on the procurement of the new IT system for NHS 24 is a direct result of the system failure in October 2015.
Shona Robison, 6 Jan 2016: None of the £41.6 million spent on the new system is a result of the pause to the phased implementation from October 2015. -
How much it has spent on running the old NHS 24 IT system since the new system failed in October 2015 in addition to the £117.4 million that is being spent on the procurement of the new IT system.
Shona Robison, 6 Jan 2016: The £117.4 million already includes an element of planned double running costs for the existing system as part of a phased transition to the new system. The additional cost of double running the existing system to the end of March 2016 is £1.0 million. -
If none of the additional £41.6 million being spent on the procurement of the new IT system is as a result of the system failure in October 2015, (a) what the reason is for the additional expenditure and (b) whether it will provide a breakdown of what the additional money is being spent on.
Shona Robison, 26 Jan 2016: The delay of the implementation of the Future Programme from the original business case until October 2015 cost an additional £41.6 million which is broken down as follows: Double running of legacy and new system £11.7 million Contract costs £14.3 million Implementation costs £8 million Scope and re-design costs £7.6 …
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.