How much has been spent on the procurement of the new IT system for NHS 24, including the cost of commissioning consultants.

Answered Asked by Lewis Macdonald Lab Lodged 27 Nov 2015

The question

To ask the Scottish Government how much has been spent on the procurement of the new IT system for NHS 24, including the cost of commissioning consultants.

The answer

Answered by Shona Robison on 10 Dec 2015 · 13 days after it was lodged, on time

The original business case cost the programme for replacement of the new system at £75.8 million. This has subsequently been revised and is now forecasted to cost £117.4 million.

In the Official Report