Written Question · S4W-29276 · Session 4
Further to the answer to question S4W-28956 by Shona Robison on 6 January 2016, if none of the additional £41.6 million being spent on the …
The question
To ask the Scottish Government, further to the answer to question S4W-28956 by Shona Robison on 6 January 2016, if none of the additional £41.6 million being spent on the procurement of the new IT system is as a result of the system failure in October 2015, (a) what the reason is for the additional expenditure and (b) whether it will provide a breakdown of what the additional money is being spent on.
The answer
The delay of the implementation of the Future Programme from the original business case until October 2015 cost an additional £41.6 million which is broken down as follows:
Double running of legacy and new system
£11.7 million
Contract costs
£14.3 million
Implementation costs
£8 million
Scope and re-design costs
£7.6 million
Total additional costs
£41.6 million
The delay from October 2015 until the summer of 2016 will add a further £7.6 million of costs to the project. The main reasons for this further increase is additional double running costs and the costs associated with preparing for the 2016 re-launch.
Double running of legacy and new system
£11.7 million
Contract costs
£14.3 million
Implementation costs
£8 million
Scope and re-design costs
£7.6 million
Total additional costs
£41.6 million
The delay from October 2015 until the summer of 2016 will add a further £7.6 million of costs to the project. The main reasons for this further increase is additional double running costs and the costs associated with preparing for the 2016 re-launch.