Written Question · S4W-29276 · Session 4

Further to the answer to question S4W-28956 by Shona Robison on 6 January 2016, if none of the additional £41.6 million being spent on the …

Answered Asked by Lewis Macdonald Lab Lodged 12 Jan 2016

The question

To ask the Scottish Government, further to the answer to question S4W-28956 by Shona Robison on 6 January 2016, if none of the additional £41.6 million being spent on the procurement of the new IT system is as a result of the system failure in October 2015, (a) what the reason is for the additional expenditure and (b) whether it will provide a breakdown of what the additional money is being spent on.

The answer

Answered by Shona Robison on 26 Jan 2016 · 14 days after it was lodged, on time

The delay of the implementation of the Future Programme from the original business case until October 2015 cost an additional £41.6 million which is broken down as follows:
Double running of legacy and new system
£11.7 million
Contract costs
£14.3 million
Implementation costs
£8 million
Scope and re-design costs
£7.6 million
Total additional costs
£41.6 million
The delay from October 2015 until the summer of 2016 will add a further £7.6 million of costs to the project. The main reasons for this further increase is additional double running costs and the costs associated with preparing for the 2016 re-launch.

In the Official Report

No contribution in the Official Report cites S4W-29276 by reference.