When construction of the Hardgrove to Kinmount improvement scheme will (a) commence and (b) be completed.
Started with S4W-08399 on 28 Jun 2012; latest 14 Jul 2014. Each later question says it follows up an earlier answer.
Follow-ups
2
Span
746 days
Answered
3 of 3
Asked by
1
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Executive when construction of the Hardgrove to Kinmount improvement scheme will (a) commence and (b) be completed.
Keith Brown, 27 Jul 2012: The construction of the A75 Hardgrove to Kinmount scheme is currently scheduled to commence on site in early 2013 with an anticipated completion date early 2014. -
When construction of the A75 Hardgrove to Kinmount improvement scheme will start.
Keith Brown, 23 Jan 2013: Construction works are anticipated to start on the A75 Hardgrove to Kinmount improvement scheme by April 2013. -
For what reason the anticipated completion date of early 2014 for the A75 Hardgrove to Kinmount improvement scheme has not been met, and on what date it will be completed.
Keith Brown, 4 Aug 2014: The £9 million Hardgrove to Kinmount improvement project was opened to traffic on 27 June 2014. This was a significant achievement given its construction took place over one of the wettest winters in recent memory.
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.