When construction of the Hardgrove to Kinmount improvement scheme will (a) commence and (b) be completed.

Answered Asked by Elaine Murray Lab Lodged 28 Jun 2012

The question

To ask the Scottish Executive when construction of the Hardgrove to Kinmount improvement scheme will (a) commence and (b) be completed.

The answer

Answered by Keith Brown on 27 Jul 2012 · 29 days after it was lodged, 1 day after it was due

The construction of the A75 Hardgrove to Kinmount scheme is currently scheduled to commence on site in early 2013 with an anticipated completion date early 2014.