Written Question · S4W-22123 · Session 4
Further to the answer to question S4W-08399 by Keith Brown on 27 July 2012, for what reason the anticipated completion date of early 2014 f…
The question
To ask the Scottish Government, further to the answer to question S4W-08399 by Keith Brown on 27 July 2012, for what reason the anticipated completion date of early 2014 for the A75 Hardgrove to Kinmount improvement scheme has not been met, and on what date it will be completed.
The answer
The £9 million Hardgrove to Kinmount improvement project was opened to traffic on 27 June 2014. This was a significant achievement given its construction took place over one of the wettest winters in recent memory.