What the estimated cost is of the M74 northern extension between Parkhead and the Kingston Bridge and how this will be financed.
Started with S1W-15440 on 27 Apr 2001; latest 21 Mar 2002. Each later question says it follows up an earlier answer.
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Executive what the estimated cost is of the M74 northern extension between Parkhead and the Kingston Bridge and how this will be financed.
Sarah Boyack, 11 May 2001: The current estimated project cost for the M74 from Fullarton Interchange on the existing M74 to the M8 west of Kingston Interchange is £245 million at May 2000 prices. This cost excludes design costs and VAT, if applicable.The project costs have been allocated in the following amountsScottish Ministers £214 million G… -
Whether it will list the sources of the other public/private sector funding for the M74 northern extension, specifying the amount of funding from each source.
Sarah Boyack, 5 Oct 2001: The £3 million of other public/private sector funding for the project has still to be secured. I have agreed with my partners in this project, Glasgow, South Lanarkshire and Renfrewshire Councils that they will use their best endeavours to secure contributions from other public and private sector bodies as the project… -
Whether it will give a breakdown of the #3 million "other public/private sector funding" towards the M74 northern extension between Parkhead and the Kingston Bridge, detailing who the parties involved are.
Lewis Macdonald, 18 Feb 2002: I refer the member to the answer given to question S1W-18394 on 5 October 2001. It is too early to provide a breakdown of contributions or details of the parties involved. -
Whether the cost of the M74 northern extension will still be allocated in the same proportions as indicated in that answer; whether a procurement method for the project has been selected; what the latest estimated cost of the project is, and what the projected date is for the commencement of the project.
Lewis Macdonald, 15 Apr 2002: The cost of the project is still allocated in the same proportions as indicated in answer to question S1W-15440. The procurement method has still to be decided. The current estimated cost of the project is £245 million (at May 2000 prices). These costs exclude design costs and VAT if applicable. Construction of the sc…
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.