Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S1W-15440 · Session 1

What the estimated cost is of the M74 northern extension between Parkhead and the Kingston Bridge and how this will be financed.

Answered Asked by Robert Brown LD Lodged 27 Apr 2001

The question

To ask the Scottish Executive what the estimated cost is of the M74 northern extension between Parkhead and the Kingston Bridge and how this will be financed.

The answer

Answered by Sarah Boyack on 11 May 2001 · 14 days after it was lodged, on time

The current estimated project cost for the M74 from Fullarton Interchange on the existing M74 to the M8 west of Kingston Interchange is £245 million at May 2000 prices. This cost excludes design costs and VAT, if applicable.The project costs have been allocated in the following amountsScottish Ministers £214 million
Glasgow City Council £21.8 million
South Lanarkshire Council £4.0 million
Renfrewshire Council £2.2 million
Other public/private sector funding £3.0 million

In the Official Report

No contribution in the Official Report cites S1W-15440 by reference.