Written Question · S1W-24324 · Session 1

Further to the answer to question S1W-15440 by Sarah Boyack on 11 May 2001, whether the cost of the M74 northern extension will still be al…

Answered Asked by Murray Tosh Con Lodged 21 Mar 2002

The question

To ask the Scottish Executive, further to the answer to question S1W-15440 by Sarah Boyack on 11 May 2001, whether the cost of the M74 northern extension will still be allocated in the same proportions as indicated in that answer; whether a procurement method for the project has been selected; what the latest estimated cost of the project is, and what the projected date is for the commencement of the project.

The answer

Answered by Lewis Macdonald on 15 Apr 2002 · 25 days after it was lodged, 11 days after it was due

The cost of the project is still allocated in the same proportions as indicated in answer to question S1W-15440. The procurement method has still to be decided. The current estimated cost of the project is £245 million (at May 2000 prices). These costs exclude design costs and VAT if applicable. Construction of the scheme is projected to start in autumn 2005.