Parliament Workbench

Question thread · 2 questions

What the cost is of the Holyrood project team, and whether this cost is included in the budget of #195 million.

Started with S1W-06118 on 7 Apr 2000; latest 25 Apr 2000. Each later question says it follows up an earlier answer.

Follow-ups
1
longest chain 1 step
Span
18 days
7 Apr 2000 to 25 Apr 2000
Answered
2 of 2
by David Steel
Asked by
1
Brian Adam

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S1W-06118 7 Apr 2000 Brian Adam SNP Answered

    To ask the Presiding Officer what the cost is of the Holyrood project team, and whether this cost is included in the budget of #195 million.

    David Steel, 19 Apr 2000: In financial year 1999-2000, the Holyrood Project Team costs totalled £434,090 which comprised £401,422 staff costs and £32,668 non-staff costs. The costs are included in the Parliament's annual budget and therefore not included in the budget of £195 million.
  2. S1W-06283 25 Apr 2000 Brian Adam SNP Answered

    What the estimated costs are of the Holyrood Project Team until the new Parliament building is completed.

    David Steel, 11 May 2000: The cost of the Holyrood Project Team whose members are staff of the Parliament, is met from Parliament's annual "running cost" budget which in 2000-01 amounts to around £38.7 million. The Holyrood Project Team budget for 2000-01 is just under £480,000. Future years' budgets will be determined in accordance with ident…

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads