SPCB Written Question · S1W-06118 · Session 1

What the cost is of the Holyrood project team, and whether this cost is included in the budget of #195 million.

Answered Asked by Brian Adam SNP Lodged 7 Apr 2000

The question

To ask the Presiding Officer what the cost is of the Holyrood project team, and whether this cost is included in the budget of #195 million.

The answer

Answered by David Steel on 19 Apr 2000 · 12 days after it was lodged, on time

In financial year 1999-2000, the Holyrood Project Team costs totalled £434,090 which comprised £401,422 staff costs and £32,668 non-staff costs. The costs are included in the Parliament's annual budget and therefore not included in the budget of £195 million.