SPCB Written Question · S1W-06283 · Session 1
Further to his answer to question S1W-6118 on 25 April 2000, what the estimated costs are of the Holyrood Project Team until the new Parlia…
The question
To ask the Presiding Officer, further to his answer to question S1W-6118 on 25 April 2000, what the estimated costs are of the Holyrood Project Team until the new Parliament building is completed.
The answer
The cost of the Holyrood Project Team whose members are staff of the Parliament, is met from Parliament's annual "running cost" budget which in 2000-01 amounts to around £38.7 million. The Holyrood Project Team budget for 2000-01 is just under £480,000. Future years' budgets will be determined in accordance with identified needs and resources available to the Parliament.
In the Official Report
No contribution in the Official Report cites S1W-06283 by reference.