Written Question · S3W-19910 · Session 3

Further to the answer to question S3W-18821 by Stewart Stevenson on 14 January 2009, whether the reduction in the cost estimate for the For…

Answered Asked by Alison McInnes LD Lodged 16 Jan 2009

The question

To ask the Scottish Executive, further to the answer to question S3W-18821 by Stewart Stevenson on 14 January 2009, whether the reduction in the cost estimate for the Forth Replacement Crossing is wholly attributable to the reduced width of the bridge, the use of ITS and more refined estimating in light of further detailed surveys, investigations and design development.

The answer

Answered by Stewart Stevenson on 6 Feb 2009 · 21 days after it was lodged, 7 days after it was due

The new proposals come within an outturn price range of £1.7 billion to £2.3 billion, an average saving of around £1.7 billion on the previous estimate of £3.2 billion to £4.2 billion.
This has come principally from:
1. the reduced cost for the new bridge, which with the use of the existing bridge for public transport, has allowed the full functionality originally announced for the crossing in a narrower structure [25% price reduction], and
2. a reduction in the extent of road construction through the use of Intelligent Transport Systems [50% price reduction].
The overall reduction to the base costing from these elements is 35% within a total reduction of 44%. The remaining savings come from refinements in risk and optimism bias which has been possible as a result of the additional survey, investigations and design which have been undertaken.