The question
To ask the Scottish Executive, further to the answer to question S3W-3854 by Stewart Stevenson on 18 September 2007, what the estimated costs would be, at 2006 prices, to convert one of the two proposed bored tunnels from road use to heavy rail use during the lifetime of the new Forth crossing.
The answer
The tunnel optionsunder consideration do not satisfy the gradients required for heavy rail to be incorporated,either during construction or at a later stage. As such, we have not estimated thecosts of converting one of the two bored tunnels from road use to heavy rail duringthe lifetime of the new Forth crossing.