Written Question · S1W-03514 · Session 1
Further to the answer to question S1W-2268 by Sarah Boyack on 22 November 1999, to provide a detailed breakdown of the #138,480 costs invol…
The question
To ask the Scottish Executive, further to the answer to question S1W-2268 by Sarah Boyack on 22 November 1999, to provide a detailed breakdown of the #138,480 costs involved in providing cycling facilities for the Parkhead to J13 Abington section of the M74.
The answer
This section was procured within the M74/A74(M) Design, Build, Finance & Operate Contract and a detailed cost breakdown is not available. The value of the scheme is based on securing 10.215km of cycleway at an estimated rate of £13.56 per metre length.