Agenda item 3 is an evidence-taking session on the Auditor General for Scotland’s report, “The Scottish Government’s purchase of Glasgow Prestwick Airport”. I am delighted to welcome Caroline Gardner, the Auditor General for Scotland, and from Audit Scotland, Brian Howarth, assistant director; Graeme Greenhill, senior manager; and Ursula Lodge, audit manager.
I understand that the Auditor General wishes to make a brief statement about the report.
Thank you for that opening statement, Auditor General. I will start with a couple of questions about the report.
Paragraph 2 of the report contains some detail about the challenges that the Government faced in relation to the six-week timescale that you have mentioned and notes that some forecasts could not be made because of the time constraints. In the private sector, takeovers happen every day; in fact, they are happening as we speak. Why was the Government not able to make those forecasts in that six-week period? Surely resources would have been provided to the Government to allow it to do that, and it should not have been prevented from making those forecasts. From your experience, why could that not happen?
I appreciate that, but what prevented the Government from being able to make the forecasts during that period? We are talking about the commitment of a significant sum of public money. Were there resource implications with regard to the provision of information? Was some of the information not available during the period? Exactly what information was missing that prevented the Government from producing those forecasts?
It is important to recognise that a significant sum of public money has been spent. As we have seen, information was not made available to the Scottish Government until after the acquisition took place. Surely, given the sums involved, the potential implications and the need to ensure that the money can be returned and that the public purse can benefit, it is unacceptable that such information was not provided. Was the information available but not provided, or was it not asked for in the first place?
Surely, for the Government to understand the task that lay ahead of it and the potential expenditure on the project, it should have had some idea of the forecasts, and information should have been provided to allow it to take that decision. The Government was in the position of committing itself to the future of Prestwick airport, while understanding all the challenges that it faced in securing the 3,000 jobs attached to the airport. At the same time, it needed to be completely aware of the responsibilities that it was taking on board. Surely that information should have been sought or provided in some context.
Before I bring in Tavish Scott, I have a brief question on the six-week timescale, because it keeps coming up in the discussion. Who set the timescale?
Is there some way in which we can clarify whether that is the case? To be fair, it is pretty loose to say that we are not sure whether there is a viable contract in place or what the national arrangements are. Is that something that you could follow up? Perhaps you could write to the committee about it. It would help to have clarity—not about the contractual arrangement, but about the industry norm and whether a contract is usually a place or not. Could we get more information on that?
Mr Greenhill mentioned that the retail investment is part of the challenges that we face in the forecasts. I am sorry if I am wrong in saying this, but he gave the impression that that investment decision had been taken.
I just need clarity before we move on. When you say “work in progress”, has the money been committed to carry out the work? Drew Smith’s question is about why we are investing all this money in retail when we might not have the passenger numbers that we need. Has there been a capital investment commitment on the retail area in Prestwick airport?
Does that not slightly contradict Drew Smith’s point that we are investing in the retailer area to improve the customer experience when there might be challenges faced in increasing passenger growth?
In relation to Infratil’s exit strategy, there could have been costs associated with contractual obligations that it would have had if it had gone into receivership. I know that the Government purchased the airport for £1, but that could have been advantageous to the seller, because it might have had contractual obligations that it would have had to have met that could have cost much more. Was that taken into consideration?
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.