It might not be the right time, but is it entirely hypothetical to consider that there might be further legal implications? You suggest that because it is hypothetical you have not considered those implications.
Official Report · Committee
Section 23 Reports
“Edinburgh trams interim report”
Speakers
Choose an MSP to read only their contributions- Donald McGougan City of Edinburgh Council 52
- Hugh Henry Lab 40
- Richard Jeffrey TIE 31
- Sue Bruce City of Edinburgh Council 24
- George Foulkes Lab 24
- Jamie Hepburn SNP 23
- Murdo Fraser Con 14
- Dave Anderson City of Edinburgh Council 12
- Shirley-Anne Somerville SNP 10
- Nicol Stephen LD 7
- Alastair Maclean City of Edinburgh Council 7
- Anne McLaughlin SNP 5
- Frank McAveety Lab 2
- Willie Coffey SNP 2
The record
253 contributions · showing 201–253The council and TIE are looking at every avenue and option that is open to them. I am afraid that it is not appropriate in this meeting, as we go into mediation, to dwell on that. I am sure that the Auditor General himself has pointed out that we should not do that. As I understand it, he excluded from his report the contractual arrangements and disputes. So, if you do not mind, I do not want to be drawn on that.
I am not going into the detail. It might not be appropriate—I accept what you say—but that is different from saying that it is hypothetical, is it not?
It is hypothetical because right now we do not want to look backwards. The team here are committed to looking forward to try to get a resolution for the benefit of the public purse.
We may differ in our interpretation of the word hypothetical, so we will leave it there.
link
I want to ask Richard Jeffrey some questions about TIE and the context for the project. I appreciate that you have been with TIE for only about 18 months, Mr Jeffrey, but I am sure that you will be familiar with the background.
I have been with TIE for almost two years.
link
Am I correct in saying that when TIE was originally set up it had four projects? There was the Stirling-Alloa-Kincardine rail line, the Edinburgh congestion charge, the Edinburgh airport rail link and the tram project. As we know, the Stirling-Alloa-Kincardine railway line project was transferred to Transport Scotland and the congestion charge did not proceed. That left the EARL project and the tram project, but of course the EARL project was dropped in 2007 by the Scottish Government, which left only the tram project. Am I right in saying that the tram project is now the only one that TIE is taking forward and that it consumes all the work of the people within TIE?
That is correct, apart from a minor role that we still have. Technically, we are still the statutory undertaker for the EARL project. Although the Government decided not to proceed with the project, it has never been formally cancelled, so, legally, it still exists and we therefore have a role as the statutory undertaker.
link
That is helpful. So, from the summer of 2007, the jobs of all the people who have worked within TIE—you and your predecessors—have depended on the continuance of the tram project. Did that lead to a culture within TIE of wanting to see the tram project continue, come what may?12:15
I do not think that it did. To an extent, what you say is speculation about people’s motives.What always impresses me is the dedication and commitment of my team to seeing the tram project built. I recently held a number of small focus groups with all my staff to talk about what the future might hold. There is wide recognition that the bulk of the people who work for me have what you might call nomadic careers, in that they move from project to project. The vast majority of them know that when this project comes to an end they will move on to other projects with almost certainly different employers. What motivates them is being part of delivering infrastructure that will be here for generations to come and which will make a difference to the city.Is there a passion and belief among the team that the trams are a good thing and they want to see them built? Absolutely. Are they motivated by their own job security? I do not believe so, because the bulk of them are used to moving from employer to employer as projects come and go.
link
Could that passion to see the project completed have led to TIE putting a more optimistic spin on the project’s prospects in reports to the council or Transport Scotland?
Again you are speculating about what people’s motives might be. There are 60 people in TIE who are all individuals and have their own motives and approaches.
link
But what I suggested could have been the case.
Many things in life are possible. You are speculating about what people’s motives may or may not be.
link
Am I right that the annual running costs of TIE are around £12 million?
Yes, but that would be a high year. Typically, we would expect the running costs to be just under £10 million. That is a combination of our internal staff costs, fairly extensive use of external legal professionals at the moment because of the level of dispute, external construction specialists and the usual raft of overheads such as insurance and rent and rates. We also pay for the council staff who are engaged in the project and pay Lothian Buses for the time it contributes to the project.
link
Okay. The project is currently around two years late and it may well run later than that. For every year that goes by we are running up additional costs for the running of TIE that are over and above all the other costs involved with construction, so that is a factor that clearly must be borne in mind.I will give you an opportunity to respond to a question that was put earlier to the council. Can you give us an update on the likely total cost of the project or on likely completion dates?
No. I have consistently said that I will not engage in speculation about the potential cost of the programme, particularly until we have a resolution to the current disputes with the contractor. The Auditor General’s report accurately reflects the fact that for the vast majority of the project’s elements we feel confident about being able to predict final costs and outturn consequences. However, for the main infrastructure construction project, while we still have the dispute with the contractor it would not be sensible to start to speculate, because it all depends on what resolution we can reach through mediation or whatever other mechanism.
link
So we really have no idea at this stage when, or whether, the project will be completed or how much it could cost?
As I said, it depends on the outcome of the mediation.
link
I appreciate that you do not want to speculate about the date, but the report states:“It is possible that trams will not be operational until at least 2013.”I asked last week for clarification of what that means and was guided to today’s panel of witnesses, so I am looking to you to give me further information about what it means, even if you do not want to go any further.
I will pick up on a comment that one of my colleagues made earlier. It is obviously possible to look at the scope of work that is still to be completed and make an assessment as to how long it would take on the basis of a reasonable contractor working at reasonable productivity rates. Until we have certainty about the productivity rates that are going to be achieved, as opposed to those that are, if you like, technically achievable, it is hard to say how long the work will take.I use this analogy: we can estimate how long it will take us to drive from Edinburgh to Glasgow by considering the distance and our average speed, but if we do not know what speed we will be driving at, we do not know how long the journey will take.
link
When you considered what a reasonable contractor could do, were you thinking that the whole line or part of it could be completed by 2013?
We can extrapolate productivity rates for any part of the line or for the whole line.
link
Does the sentence,“It is possible that trams will not be operational until at least 2013”refer to the whole line or part of the line?
I think that it probably refers to part of the line but, as I said, the programme and the timescale will be a subject of mediation.
link
We heard that the council is now working to a ceiling of £600 million and we heard about the 10-year prudential borrowing analysis that it has been doing. Was the money that has been earmarked for prudential borrowing for the trams earmarked for other projects, or are we talking about new prudential borrowing that the council will take on?
I was talking about a provision in the long-term financial plan, which gives us spending capacity. That capacity was not earmarked for any other project, but it clearly carries with it an opportunity cost, in that it could have been used for other things.
link
Is £600 million the estimated cost of getting to St Andrew Square? In the analysis of City of Edinburgh Council’s prudential borrowing, are you assuming that you can deliver the tram only as far as St Andrew Square for that? Are you looking to do more prudential borrowing in future?
We did not come at the issue from the perspective of the cost to St Andrew Square. There is no connection with the potential cost to St Andrew Square. I was referring to a contingency plan, which the council determined on some eight months ago, which was based on a figure that was 10 per cent more than the funding envelope, so it was about seeing how we would get another £55 million, if that was required. That is all. We are not saying that the cost to St Andrew Square is £600 million.
link
I appreciate that. We are simply looking at a percentage increase in cost, but we have no idea whether that will get us to Haymarket, St Andrew Square or anywhere else. That was not the basis of the exercise; the council was simply considering how it would get to £600 million.
We were looking ahead and contingency planning up to £600 million. When we come out of the mediation we will need to review the prospects for timescale and cost.
link
There has been speculation in the press recently that the council or TIE will ask the next Government for more money. Has such a strategy been considered as part of contingency planning?
That is not part of the contingency planning at the moment, but I think that I said in answer to a previous question that we would be prepared to explore every avenue and to talk to the Scottish Futures Trust and Transport Scotland about the funding issues after we come out of mediation and see where we are in relation to timescales and cost.
link
We heard earlier that Lothian Buses has been identified as the operator of the trams. When did that happen?
When the project was conceived, there was a separation between the project and Lothian Buses, and Transdev, which is a private sector transport operator, was brought in. Around the end of 2009 we terminated the contract with Transdev and in effect brought the operation back in-house. One of the reasons for that was that after discussions with the then management of Lothian Buses it was clear to me that the expertise to operate the tram existed in Lothian Buses. At that point we concluded that we no longer needed the services of Transdev.Therefore, I guess that the idea was conceived—or, rather, acted on—at the end of 2009. Since then we have had a continuous process of working more and more closely with Lothian Buses, to ensure that when the trams are ready for operation the company is geared up to absorb them into its operation.
link
I do not represent the area and I do not have intimate knowledge of how Lothian Buses is structured, but am I right in saying that it is not owned wholly by City of Edinburgh Council but is owned by all the Lothians local authorities?
City of Edinburgh Council owns 91 per cent, and the balance of 9 per cent shareholdings is distributed across the three Lothians authorities, although not in exactly equal shares.
link
So it is virtually owned by City of Edinburgh Council. What has been the opinion of the other Lothians authorities on the prospects of Lothian Buses operating the trams?
Due diligence in relation to how everything will work has still to take place. It has been recorded again in public as recently as in the latest council report that the direction of travel is that Lothian Buses will take on the operation of the trams. A number of issues in relation to the governance of the operation and how it will be put in place are outstanding. That has still to be subject to legal due diligence. There has been some discussion with the other councils, who have small minority shareholdings in Lothian Buses, but no concrete proposals have yet been agreed with them.
There is logic behind the proposal and there are reasons why it is the right way forward. We have to consider the issue from the city’s perspective and passengers’ perspective. We have talked about integrated ticketing and integrated timetables, with a single fare structure across the whole combined tram and bus network and with the opportunity to integrate service patterns and so on. All those factors mean that the smart thing to do is integrate the tram and bus operations.
link
Mr Jeffrey said that the EARL legislation is still in place and that TIE has responsibilities there, but, on a de facto basis, EARL is not happening. Also, Lothian Buses seems to be the preferred operator for the trams. So the only project left to TIE—as was highlighted in the answer to Murdo Fraser’s question—is the delivery of the tram project. So what is the long-term future for TIE? Once the tram project is delivered—whenever it is delivered—what will your role be?
As you can imagine, that is a conversation that I have with my team all the time—because they want to know the answer as well. However, until the tram project is delivered, there is really no point in thinking about the longer term for TIE. We have the one project and we have to get it delivered. That has to be our focus.If, in the longer term, funding is available for other transport projects and it is deemed that TIE is the right organisation to take them forward, then so be it. If that does not happen, TIE’s purpose ceases to exist at the end of this project.
The need for investment in public transport infrastructure in this city has not gone away. The city is growing and it will require investment in infrastructure in future. It will require a body that is capable of developing new infrastructure and of finding methods of financing that new infrastructure. Whether or not that happens through TIE, the task will remain.
link
We could explore that point further, but I will not.I want to follow up on a couple of points that Mr Jeffrey made in response to Shirley-Anne Somerville and Murdo Fraser. You have said quite clearly that you will not speculate on the total costs of the project. Does that not offer no reassurance whatsoever to members of the public who, in essence, are paying for this project? Are you not giving the impression that there is a bottomless pit?
The uncertainty of the costing programme is understandably a source of frustration for everybody—politicians, members of the public, the media and so on. That is why one of the things that must come out of mediation is certainty.
link
You were also somewhat reluctant to give any concrete forecast for when the project is likely to be completed. I was very interested to hear you say that you could make a forecast with a reasonable contractor working at a reasonable rate. I may be paraphrasing you slightly, but was that a backhanded criticism of the current contractor?
No, it was simply a clarification of the assumptions that would need to go into the calculation of any programme.
link
So the current contractor is a reasonable contractor working at a reasonable rate.
Our differences of opinion with the contractor have been well publicised. Earlier, Shirley-Anne Somerville talked about the need to build relationships. I am not sure that it is helpful for me, in a public environment, to express again views that have been expressed in the past. The focus has to be on building relationships and finding a satisfactory resolution at mediation.
link
We may read about it in your autobiography.
This discussion has been quite wide-ranging and I am now going to draw it to a close. I thank the witnesses for coming to the meeting; I know that you were somewhat concerned about it because of the upcoming prospect of mediation. We appreciate your taking the time to come along.It will be interesting to hear what Transport Scotland has to say. Because we are so near to the dissolution of Parliament, it will be difficult for the committee to go into the depth that it might want to go into, but I am sure that this issue will come back either to a future audit committee of the Scottish Parliament or to a future transport committee. Thank you all very much for coming along.Item 5 is no longer on our agenda so we move to item 6, which will be taken in private.12:30 Meeting continued in private until 12:37.
In this meeting
Everything on 23 Feb 2011 →- 09:30 Decision on Taking Business in Private Procedure · 7
- 09:30 Section 23 Reports Committee business · 68
- 09:30 Section 23 Reports Committee business · 59
- 09:30 Section 23 Reports Committee business · 253
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.