All the hats that I wear. I suppose that the primary motivation at the time was to try to get the project into some kind of settled state, where we could report with a degree of confidence on the design, cost and programme. We could not do that at the time. One comes across a huge amount of information on any given day on any subject, but especially on a major building project such as this, and it is always a question of judgment. One certainly does not offload everything. Even with the close order that the progress group maintains with the project, we must still agree with members of the group what we will pass on and what we will not pass on, and the basis on which they want it. There is a judgment to be made.In response to Paul Martin's point, there is only one major cost report, published at the end of August. A version of it was later produced, but it was effectively the same cost report—that was in August and September. As I understand it, the next cost report was not until February, and that report was revealed to the corporate body because it related to the redesign. I therefore had more confidence that it related to a design that the corporate body was prepared to sign up to. There was only one such report; you should not get the impression that there was a whole series of reports.
Official Report · Committee
Holyrood Project
Speakers
Choose an MSP to read only their contributions- Paul Grice Clerk and Chief Executive, Scottish Parliament 121
- Nick Johnston Con 39
- Brian Adam SNP 39
- Margo MacDonald SNP 21
- Martin Mustard Holyrood Project Team 16
- Karen Whitefield Lab 13
- Paul Martin Lab 12
- Euan Robson LD 11
- Annabel Goldie Con 10
- Cathie Craigie Lab 7
- Scott Barrie Lab 6
The record
298 contributions · showing 201–298I take that point. Paragraph 3.50 seems to criticise the project management for not reporting the cost overruns. Did project management think that, by making you aware of those cost estimates, they were making the corporate body aware of them?
No. They thought that they were making the chief officer of the Parliament aware, and they sought my approval to take certain actions, which are the ones that I have just explained. They wanted my advice on the judgment call that I have explained to you. I think that they felt, and rightly, that it was a judgment that I should make, as opposed to them.
There seems to be some doubt about the reporting mechanisms. Who set those mechanisms in place and how did they come about? Were there suggestions from the project team about how you might go about it, or was there Government guidance from elsewhere, following standard practice? Did you discuss the reporting mechanisms with the project team when you took it over, or did things just roll along as they had been doing prior to the handover?
I am trying to cast my mind back. I think that the project sponsor put forward specific proposals to the corporate body about how it would get information on the project. That covered a range of things, of course: not just notional costs, but all the issues surrounding the project. My recollection is that there was some discussion and that a standard set of reporting was proposed and agreed to. That is the basis on which we moved forward.
Could we have a note of any records that were kept of an agreement on the reporting mechanism?
I am not sure that I could dig any out, but I shall read back through the minutes and see if there is anything illuminating in them. My recollection is that there was some agreement very early on about the basis of reports that the corporate body would get, and it seemed reasonably happy with that. The fundamental plank of those reports was a report from the project sponsor to the corporate body.
This afternoon, you have referred on a number of occasions to the fact that there has been a substantial increase in the area of the building. You have given explanations for that and said how difficult it has been. However, the reality is that there has been almost a 50 per cent increase in the unit cost. How did the management exercise control over the underlying design changes that occurred?
The sequence of events is important. Value engineering is a technique that has been used at specific points in the project to deal with problems. In the new phase of the project, we are now trying to make it more integral and more of a day-to-day thing. That device can be used to drive down costs and re-examine them and we have certainly used it in the past. Beyond that, however, you need to start with a design that you are happy with, consider the cost, and ask yourself whether you are prepared to live with that cost for that design. If the answer is yes, you move into the scheme.You make a judgment; it is something of a one-off judgment. You have to ask whether it represents value for money. I think that the Auditor General has confirmed that this budget for that design represents reasonable value for money. That judgment was made by the corporate body as well, and endorsed by the Parliament back in April. Now, we have the responsibility and the capacity to manage that in quite a sophisticated way, with fortnightly cost reports and programme reports to the progress group, building risk management and value engineering into the process. It becomes part of the continuing project. You are constantly asking yourself questions about where costs can be stripped out, and looking ahead to see where risks can be managed out of the process. It is a project in two different phases.
We are aware from the report and the evidence that we have heard that one of the major contributing factors to the increased cost is the higher standard of materials that are to be used. What specific evidence can you give us that the increases in the cost really do represent value for money?
It is difficult with a unique building such as this. One assurance that I can give is that we have a major firm of cost consultants with a high reputation. They have advised us that nothing has been wasted or missed. It is always dangerous to look at comparators, especially with a unique building. John Spencely had a bit of a go at that, and Portcullis House is a helpful comparator, because it is a lot more expensive, although it is fundamentally a simpler building, as it is not a complete parliamentary complex. Normally, we would try to benchmark such things. The original benchmark was with a high court, a public building with a high spec. On the cost per square metre, which is probably the best comparison that we can draw, it compares reasonably well. In terms of space standards, another area that might be considered in terms of value for money, the space standards for members are not hugely generous, although they are adequate. I think that we can defend that on value-for-money grounds. The space standards for staff are based around pretty normal space standards for public sector staff. We have sought and can give a number of reassurances that the project, in general terms, represents decent value for money.
I am interested that Portcullis House has come up. It is probably the best example of a public building that has gone way over budget, but perhaps we can leave that.I appreciate that I may be straying into commercially confidential areas and may be asking questions that are difficult to answer, but I would like to ask about fees. We are aware that fees for various consultants are in the process of being negotiated between the corporate body and the consultants themselves. Are you in a position to give us a general indication of how fees being set as a proportion of construction costs might affect the subsequent or continuing negotiations?
We have taken the opportunity at any formal break point in the project to renegotiate fees. I do not think that I can hold out any prospect that the fees will be substantially lower than they are now. The design team has undertaken significant and proportionate work. The Bovis fees relate very much to time on site. They are called fees, but they are mostly reimbursed costs, and we cannot really argue with that. You look perplexed, Mr Barrie.
I am perplexed by the phrase "bogus fees", which would suggest—
I said Bovis. I meant Bovis Lend Lease (Scotland).
Sorry. That is why I was perplexed.
We have tried to renegotiate fees, but I would be misleading you if I gave you to understand that there was a real prospect of negotiating those fees down significantly.
Were you able to reduce the fees to the lead architects after Señor Miralles died? I presume that his fees reflected the fact that he was taken on as a signature architect. As far as I know, his wife is not counted among the signature architects. She is now named along with RMJM as a lead architect. Was there a renegotiation of fees to reflect the changed status of the lead architects?
No, I am afraid that it does not work that way. Yes, Señor Miralles was the lead architect. I did not set up the original contracts, so I am making a supposition. I think that fees were negotiated with EMBT/RMJM, which is the company created by Enric Miralles, Benedetta Tagliabue, Brian Stewart and Mick Duncan from the two firms. I do not think that the reason Miralles was named as lead architect was anything to do with fees; it was to ensure that what we got was a Miralles building and not a Mick Duncan building, which is not meant as an insult to him. When Miralles died, we had the concept—and even at stage D, which was more than a concept—of what a Miralles building was.I checked this fact yesterday. The design team, which includes the structural engineers, had 123 people working on the project.
I think that you have answered the question to the full extent of your abilities.We will move on to accounting for risk. Bearing in mind that I want to draw this meeting to a close at 4.30 pm, I ask members to be brief in their manner of questioning.
The Auditor General's report was critical of the project's insufficient accounting for risk. When you took over the project in June last year, there must have been a number of risk elements that could have delayed the delivery of the project and increased its cost. What did you do to assess those risks, and how you would deal with them if they arose?
One of Martin Mustard's jobs has been risk management. Would it be all right if I asked him to answer?
Please do.
Risk assessment has been an continuing part of the project. Two risk assessment workshops were held last year, which identified risks at a strategic level. That is one part of the risk analysis. The other part was through DLE, the cost consultants, which looked specifically at design risks.Since we formed the cost plan we have moved to a more robust form of risk analysis. We can assess risk per contract and draw down contingency to meet those risks on every occasion, so if a risk arises, it will be covered. There has been a continuum of risk assessment through the project, which can only become effective at this point with the cost plan and a settled design.
So you have made the mechanisms more robust. Why did you believe that there was a need to do that?
This is almost circular—we come round to the same things—but not to bore you, the settled design and cost plan now provide the basis for proper risk assessment.
Last week, we heard from the permanent secretary at the Scottish Executive about his interpretation of the Treasury guidance on risk assessment. What is your interpretation of the importance of that guidance, and how did it relate to the project when you took over in June last year?
The Treasury systems for risk assessment are extremely good. Over the years I have found that most Treasury guidance is extremely good, but I would also agree that it is guidance, and there are many ways of developing risk analysis. For example, in the Treasury guidance there is a particular type of risk assessment, but there are lots of effective variations across this industry, and other industries, that are equally as good. I share the view of the permanent secretary that Treasury guidance often is good, but it is still guidance. It is not a standard or a rule.
I appreciate what you say, but it was evident from the Auditor General's report that he believed that there was a shortfall in the project's risk assessment. The Treasury guidance is clear about the importance of risk assessment in cost accounting and project management from the start of a project. Do you agree with that guidance, and is that one of the reasons that you have now implemented much better risk assessment? Was it that risk assessment was missing, which you have now remedied?
No. In the previous phase of the project, not having a settled design and cost plan prevented applying the most robust form of risk assessment. Now we have a settled design and cost plan, and from now on in the risk assessment will be extremely tight.
If I remember, the risk that crystallised in November 1999 was that the area specified in the design brief was going to be 10 per cent less than experience showed was actually needed. That problem took six months to sort out. It was costly and disruptive. Surely it would have been better value for money to allow for a more generous area at the outset to reduce the impact of last-minute changes, which are always expensive to implement?
If I understand the question, it is whether you should add space at the outset. That is a fair point, but it requires a judgment to be made. When you are undertaking anything, but especially a major building project, you do a brief. The Auditor General was reasonably happy with the way in which the brief was put together, but he was less happy with the lack of risk allowance in it.Whenever you do anything like this project, there is always a question about the space contingency that you build in. It is tempting to build it big, then it will be easy, but equally you have a responsibility, especially in the public sector, to make it as small as you can, because that will lead to a building that is fit for purpose. There are judgments to be made. When we did the feasibility study this time round, we included a contingency element for space. In other words, we did not build it exactly to the right size; we assumed that there would be a continuing demand for extra space. But yes, if we had inherited a bigger building, it stands to reason that we would not have had to redesign it in the way that we did, although that is not to say that the wrong decision was taken.
Given that the contingency of 10 per cent clearly was inadequate, because we ended up with 47 per cent, does that show the value of a formal risk analysis as opposed to the technique that you used? You chose not to accept what you recognised as good Treasury guidance. With hindsight, would the more formal risk analysis approach to space have given us a much more robust project from the beginning?
You used the word "formal", but that is not right. The risk assessment was formal, in the sense that it was part of the management process. The point that Martin Mustard made, and which I endorse, concerns what risk you are assessing at the time. You are trying to assess a design risk and come to a view on the appropriate design. That is not easy. Risk assessment is educated guesswork; it is not a science. It was part of the process, and it was undertaken last summer, so it was built in. What materialised later in the year was a decision by the corporate body to take action as some of that risk crystallised. Assessing risk does not remove the need for action unless you take a view that notwithstanding risk you are not going to take any action. The SPCB took the view that it would take action, and it instructed a redesign to find the extra space, because the project design as it stood was not big enough.That is the purpose of risk management, but I do not see how, given where we started in June of that year, we could have ended up at a different point. The SPCB identified demands and instructed a redesign so that the building was fit for its purpose. That was the only sensible course of action open to it. The redesign was costed, independently evaluated and put to the Parliament.
We will move on to the current state of the project.
The deadline for completion is December 2002 and, we hope, within the target of £195 million. I refer you to paragraphs 1.36 to 1.38 of the Auditor General for Scotland's report. The report states that meeting the financial target of £195 million will be a challenge because of estimating uncertainty and inflation risks. You are to review this in the light of tendering major works packages. What are those major packages and what are the results of tendering so far?
The major packages immediately in sight are the substructure at the east end of the site, the superstructure at the east end of the site and the cladding packages. Martin Mustard could probably give you a precise figure, but those account for tens of millions of pounds. The cladding package will be for the MSP block. It will give us a great deal of intelligence as to what the market is likely to supply for the rest of the site because the cladding is essentially the same throughout it. Those are the major packages. As each comes in, it is evaluated. Now that we have a package-based cost plan we can look precisely at what the package should be and whether it is over or under.
Are there any tender results to comment on?
None of the real biggies.
So we cannot answer the question.
It is a bit early.Martin Mustard is better placed to comment than me. As I understand it, the results have been relatively modest so far. They are above and below the line. The progress group, which is fully informed on this, is comfortable that we remain on course.By Christmas, when we will have some of the big packages in, we will be in a much better position to answer that question. I accept the Auditor General for Scotland's proposal on this. It is right and it is the way that we are running it.
Would it be appropriate, convener, to ask if we, as a committee, can be given details of these major packages as they crystallise and as information about tender values becomes available in the next few months?
It would be appropriate, if Mr Grice could arrange for that.
Yes. It would have to be on the basis of commercial confidentiality, but I would be happy to do so. At the least, I would be happy to tell you how they are falling with respect to the works package cost plan. If we have said that it should come in at X, I would be happy to tell you whether it has come in at X plus or minus. I would be happy to give you the number as well, but I would like to clear the release of that information with the progress group, if that is acceptable.
For the purposes of the Audit Committee, pluses and minuses would be useful and not commercially confidential. If we needed other information lying behind that, we should probably discuss that with you and the lawyers to see what is acceptable in the light of commercial confidentiality.
I will give you anything we can. I could tell you the value of those contracts because that is relevant. It is instructive to know if it is £30 million, as opposed to £1 million, plus or minus 2 or 3 per cent. Martin Mustard might be able to give more detail.
Substructure east is the first biggish package; the cost plan allowance is about £5.8 million. We should have some information on that soon.As Paul Grice said, the next one is superstructure east, which is the building frame for the east of the site. That is a big package; the cost plan allowance is in the region of £17 million. As Paul said, those should provide a good indication of any trend. It is right that we provide a report to you after the autumn, when we get through the tender period.
Mr Grice, does that mean that you will not have been able to get reliable advice from your cost consultants about the total estimated construction costs?
No. That is not true. A fundamental point about the estimates in the cost plan is that the figures are based on the construction manager working in liaison with the cost consultant, which does an initial market test and provides a pre-tender estimate on each package. The figures that I have given you were the result of that pre-tender estimate exercise. They become the indicator figures for the tender exercise and a comparator when those tenders come in, to enable us to establish whether they represent value for money. We will compare it with the market mean and decide whether we need to take any measures such as value engineering on some of the packages to achieve value for money.
Is where you are at the moment, which seems a little imprecise to me, consistent with the £119 million that has been allocated for construction costs within the £195 million?
Yes is the short answer to that. Risk will decline as we let the major packages, both because we have major elements of expenditure out of the way and because we can use the intelligence that we get from that—cladding is the best example—to check it against the works package estimate for future cladding packages. The short answer to your question is yes.
Thank you, we like short answers.
We think that there is now an agreed cost plan.
There is.
We were given that information last week. Is it in full form, or is it heavily conditional and heavily qualified?
It is in full form.
Did the client agree to it?
It is a package-based cost plan. It has gone down a further level, as we have identified the works packages within it; it adds up to £108 million, not £119 million, because we keep the contingency aside from that.
What is the latest advice from the construction manager about the possibility of the project being completed by the deadline of December 2002?
The construction manager is still reporting that December 2002 is the date of completion for the building.
Will we be able to move into the building then? Will the fittings have been completed as well?
The fit-out period will follow that. One of the diagrams in the Auditor General for Scotland's report indicates that.
When will the building be ready to accommodate MSPs and parliamentary staff?
I expect around about April 2003.
The progress group is examining that. Elements of the building, such as Queensberry House and the MSP block, will be finished much earlier than that, so it might make sense—although we will have to evaluate the cost—to commission some of those parts of the building earlier. Some of the fit-out commissioning could happen on parts of the site when other parts of the building are still being finished. That would compress that period. The progress group is examining that, but has not come to a view. I dare say that it will do so over the next few months.
I hope that it does not happen, but if you were to experience building delays what contingency plans do you have? Have you built in flexibility to allow you to absorb delays?
Martin Mustard could talk in more detail about how the programme is put together. Issues around quality, cost and programme are interrelated. One option that you often have is to accelerate the programme at the price of cost. You might use a contingency to do that. It can work the other way: if you slip your programme a bit you can get a lower price. You might take another fortnight to do more work on a tender package before you put it out because the better defined the tender is, the greater is the likelihood that you will get value for money. There is a constant tension between those. The cash contingency allows you to buy back some time. As this is a complex project across a range of buildings, we pay Bovis to find ways of gaining in other places if we slip in a certain area. We rely very heavily on the company's estimate of completion time, as it manages all the packages in a parallel way to allow the critical path to end in December 2002.
Is the type of contract that you have more useful in managing the project better, especially if delays occur?
Although the potential downsides of the project have already been highlighted, one of the main advantages of the contract is that it gives you tremendous flexibility in that respect. That could be quite a considerable advantage at this phase of the project.
The Auditor General's report made a number of recommendations. Do you agree with them, particularly recommendations a and b about risk assessment and management; and have you implemented them?
Yes.
Have they all been fully implemented?
They have either been done or are in train. However, although the recommendations have been extremely helpful, I will say in defence of the project team that I would like to think that we would have been doing most of them anyway. That said, the recommendations provide a helpful checklist for the progress group. I am happy to submit as evidence my own copy of the report's recommendations, which I have annotated with "Done" or "In train".
It would probably be helpful if you could drop us a note of where you are with recommendations a to h.
Perhaps in conclusion, what lessons for future major projects have you learned from this experience?
That is always a difficult question, especially when it is asked halfway through a project. However, there are clearly lessons to learn. The way we restructured the team has provided a more dedicated client control. Furthermore, we have learned lessons about reporting and risk management that I hope we are now putting into practice.I have learned a lesson about the amount of time one must dedicate to such a project to provide support and input to a team without interfering overly much. We have certainly learned lessons about structures and reporting. Recently, the Spencely report and the Auditor General's report have been extremely useful in crystallising ideas that we were perhaps moving towards and in providing some helpful checklists. We know that we need to implement those lessons if we are to bring the project in on time and on budget.
I have a question about the cost packages. Is the superstructure on the east end of the site the Parliament building itself?
Yes.
You said that that would cost seventeen point something million pounds. Does that figure come from recent market testing?
Yes.
How does that figure relate to the original estimate?
I would have to go back to previous cost reports to work that out, as the previous estimates were elemental rather than package based. That £17 million is package based and purely for the frame of the building.
I take the point about the pluses and minuses as read, because that concerns the management of the project. However, with current inflation, particularly in the building industry in Edinburgh, can you be absolutely confident about that figure?
That is part of our risk assessment and part of what we allocate to that particular package as a contingency to allow for such elements.
Do you allocate a percentage for contingencies?
I am sorry; we are not going to wander along that path any further. Mr Adam can have one very brief final question.
My question is in a similar vein. We have a final figure of £195 million for the total package for which the Parliament is responsible. To what extent has allowance been made for aspects such as construction costs and inflation in Edinburgh, which are currently unique? Can the contingencies contain those costs?
Allowance has been made as part of risk. We recognise with the Auditor General that there are a number of risks, one of which is inflation, and we have to manage that. However, it is worth putting on record the fact that, although Government procurement policy is to deal with constant prices—in this case, with March 1998 prices—the Holyrood progress group is clear that £195 million is a cash target. Furthermore, the group is clear that, if the project is brought in at that price, that will be less in real terms than £195 million. However, the group feels that it provides the right approach and discipline to manage inflation. As the Auditor General pointed out, the contingency is there if necessary, although it must cover other eventualities. I assure the committee that we are monitoring the situation very carefully with the progress group as we go along. If there is a need for additional cover to provide for inflation along the track, the progress group will report on that to the SPCB and ultimately the Parliament. However, from our current position, the market intelligence is quite good. Although we are certainly well aware of Margo MacDonald's point about price inflation, we are procuring on a global basis.
Do not open that can of worms.
Well, the SPCB made an important decision to procure on a global basis. One reason for doing so is the recognition that the Edinburgh construction market is pretty tight at the moment. Using a massive company such as Bovis and procuring on a worldwide basis gives some guard against that situation—without getting into issues of sandstone and granite.
Mr Grice, Mr Mustard, thank you for your evidence to the committee.It might be helpful to run through the written notes that we have agreed you will provide to the committee. First, you will provide a breakdown of the rising costs from £62 million to £109 million and specifically details of what proportion of the increase is attributable to the fact that we are dealing with a bigger complex, to problems with Queensberry House and to the higher specification, particularly the security aspects.Furthermore, you will confirm when you were made aware that you had a construction management contract; that the SPCB considered taking an independent audit of the project at the time of the handover; and that the SPCB had at least considered the option of housing the new Parliament on a split-site basis. You will also provide information on the establishment and operation of the reporting mechanisms; and on the values of contracts and how those figures relate to pre-tender estimates and budgets. Finally, you will provide a response to the recommendations on page 8 of the Auditor General's report.
I should make one point. The SPCB considered seeking independent advice, not an independent audit. I think that I was quite careful to make that distinction.
I will change the clerk's note, although I hesitate to do so.
We also asked Mr Grice to provide as much information as he can on how much of the additional costs happened before and after the handover.
I think that is correct. We asked Muir Russell the same question.
As I said, I entirely accept the question and can—and will—do my best to answer for what happened after the handover. However, it is somewhat harder to speculate on what happened before, although I will certainly have a look at the matter.
Thank you.
Meeting continued in private until 17:07.
In this meeting
Everything on 3 Oct 2000 →- Scottish Parliament Audit Committee Tuesday 3 October 2000 (Afternoon) Committee business · 2
- Holyrood Project Evidence session · 298
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.