Good afternoon. Welcome to this, our second meeting dealing with the costs and management of the Holyrood Parliament building project. Our witnesses today are Mr Paul Grice, the clerk to the Parliament—who, I believe, has risen Lazarus-like from his sick bed to be with us this afternoon—and Mr Martin Mustard, who is the project team manager. Last week we heard evidence from the permanent secretary and principal accountable officer of the Scottish Executive, who was the official responsible for the project in the period before 1 June 1999, at which point client responsibility passed from the First Minister to the Scottish Parliamentary Corporate Body. Since that date, Mr Grice has been the project owner and is the most senior official responsible for the successful delivery of the project.As we did last week, we will ask questions in five main areas: evidence about the state of the project at the time of the handover to the SPCB; project management arrangements more generally, including the interaction between project management and the corporate body as a client; arrangements for cost reporting for the project; managing project risk; and the current state of the project and its prospects over the two years to the forecast completion date of December 2002.Mr Grice, I have been apprised of the fact that you do not intend to make an opening statement. Would you like to go straight into questions?
Official Report · Committee
Holyrood Project
Speakers
Showing Nick Johnston only · show everyone- Paul Grice Clerk and Chief Executive, Scottish Parliament 121
- Nick Johnston Con 39
- Brian Adam SNP 39
- Margo MacDonald SNP 21
- Martin Mustard Holyrood Project Team 16
- Karen Whitefield Lab 13
- Paul Martin Lab 12
- Euan Robson LD 11
- Annabel Goldie Con 10
- Cathie Craigie Lab 7
- Scott Barrie Lab 6
Nick Johnston’s contributions
39 contributionsBefore we get on to detailed questions, I would like you to provide us with some background. What was your role in the Scottish Office before you took responsibility for the SPCB?
If you have read the evidence that we took at last week's meeting, as I am sure you have, you will have seen that Muir Russell said of the project:"There was a lot about it that was pretty firm and credible. That is why I think the project was viable and in good health when it was handed over."—Official Report, Audit Committee, 26 September 2000; c 359.What were the procedures for the handover of the project in June 1999? What information on the key aspects of it did you and the corporate body receive from the Executive at that point?
In his evidence last week, the permanent secretary told us that he had handed over a doable and robust project that could have been completed for £62 million. During the period immediately after handover in June 1999, many things took place. What was your view of the state of the project when you became responsible for it in June 1999?
Should you have been handed a completed design at that stage?
Are you happy that the fact that you were not handed a completed design did not leave you in a position where you had to redesign virtually from scratch?
How much did the revised design of the chamber change the forecast construction costs? Can you put a figure on it?
I am sorry, Margo. The choice of architect does not fall within Mr Grice's remit.
Mr Grice, you are answering questions as the accountable officer from 1 June 1999. However, are you happy to answer that question as a point of background information?
Mr Grice, would you have had any choice? Was it possible for the corporate body to revisit the whole thing and decide to do it under a different regime and not go with the construction management approach?
We will probably come back to this line of questioning later.
Paragraph 1.18 of the Auditor General's report refers to the identification in August 1999 of"serious difficulties with the project".There are a number of bullet points in that paragraph. Is it possible to identify, in relation to each point, the extent to which they were either new problems or inherited from the Executive's earlier period of stewardship and control?
Whichever way is more comfortable. Going through them one at a time might be more useful in providing clarification to the committee. I think that you have covered the first bullet point, which deals with delay.
If I understand correctly, the design team took its instructions from the corporate body and produced the extra 4,000 sq m that were needed. Is that the way round it happened?
Did you find out where the 4,000 sq m had come from?
We have covered that point Margo.
I am sure that there is a question in there somewhere, Mr Grice. Was the design team prescient in realising that you were going to need more space, or did it produce 4,000 sq m that were not asked for, but which subsequently you found you needed anyway?
Are you asking whether the corporate body considered having a completely independent audit?
I would like to move on, as time is pressing.
Is that in terms of not having a fully agreed design and cost plan in place at the time of the handover?
That would be very helpful. I am going to pull this section of questions to a close. I want to move on to the project management phase because I expect many issues to flow into that from the handover phase.I intend to spend half an hour on the project management questions before we have a brief adjournment.
Before you answer the question, Mr Grice, could you say what responsibility or ability the corporate body had to renegotiate the architects' fees?
That is a good point on which to bring this part of the meeting to a close. We will resume at a quarter to four.
We will move on to aspects of cost reporting. Mr Grice has, to a greater or lesser extent, answered some of the questions that arose over cost reporting, so I ask members to keep their questions fairly brief. Mr Grice, if you feel that you have already answered a question, please feel free to say so. We will try to gallop along. I would like to bring the meeting to a close at half-past 4, as several members have indicated that they have other commitments.
Excuse me. Mr Martin is still asking questions.
Paragraph 3.50 on page 41 of the report says:"Later, during the second half of 1999, project management did not report various estimates from the cost consultant to the Corporate Body as the client."It appears that you were aware of the anomalies in the costing. What hat were you wearing at the time?
I take that point. Paragraph 3.50 seems to criticise the project management for not reporting the cost overruns. Did project management think that, by making you aware of those cost estimates, they were making the corporate body aware of them?
I think that you have answered the question to the full extent of your abilities.We will move on to accounting for risk. Bearing in mind that I want to draw this meeting to a close at 4.30 pm, I ask members to be brief in their manner of questioning.
Please do.
We will move on to the current state of the project.
It would be appropriate, if Mr Grice could arrange for that.
For the purposes of the Audit Committee, pluses and minuses would be useful and not commercially confidential. If we needed other information lying behind that, we should probably discuss that with you and the lawyers to see what is acceptable in the light of commercial confidentiality.
Thank you, we like short answers.
It would probably be helpful if you could drop us a note of where you are with recommendations a to h.
I am sorry; we are not going to wander along that path any further. Mr Adam can have one very brief final question.
Mr Grice, Mr Mustard, thank you for your evidence to the committee.It might be helpful to run through the written notes that we have agreed you will provide to the committee. First, you will provide a breakdown of the rising costs from £62 million to £109 million and specifically details of what proportion of the increase is attributable to the fact that we are dealing with a bigger complex, to problems with Queensberry House and to the higher specification, particularly the security aspects.Furthermore, you will confirm when you were made aware that you had a construction management contract; that the SPCB considered taking an independent audit of the project at the time of the handover; and that the SPCB had at least considered the option of housing the new Parliament on a split-site basis. You will also provide information on the establishment and operation of the reporting mechanisms; and on the values of contracts and how those figures relate to pre-tender estimates and budgets. Finally, you will provide a response to the recommendations on page 8 of the Auditor General's report.
I will change the clerk's note, although I hesitate to do so.
I think that is correct. We asked Muir Russell the same question.
Thank you.
In this meeting
Everything on 3 Oct 2000 →- Scottish Parliament Audit Committee Tuesday 3 October 2000 (Afternoon) Committee business · 2
- Holyrood Project Evidence session · 298
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.