To ask the Scottish Government what its current estimates are of the cost and timescale required to complete the remaining sections of the A9 dualling programme that are still to be upgraded. (S7O-00091)
Official Report · Chamber
General Question Time
This is the draft Official Report. The final version may differ.
link
To ask the Scottish Government what its current estimates are of the cost and timescale required to complete the remaining sections of the A9 dualling programme that are still to be upgraded. (S7O-00091)
link
The latest tenders are clearly welcome, as they give some clarity about the completion of the A9, albeit some 28 years after it was originally promised. However, the costs require some examination. On a per kilometre basis, the latest sections will come in at around £20 million per kilometre, compared with £6.4 million per kilometre, adjusted for inflation, for the Kincraig to Dalraddy section. Looking internationally, I note that the Faroese Government has built tunnels—new roads under the sea—for £10 million per kilometre. Does the minister agree that it is vitally important that we have cost-effective delivery of infrastructure for economic growth? What lessons is the Scottish Government seeking to learn from international best practice, such as the Faroese example?
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.