Parliament Workbench
Data: Motions & questions to 19 Nov 2026

General Question · S7O-00091 · Session 7

What its current estimates are of the cost and timescale required to complete the remaining sections of the A9 dualling programme that are …

Oral Asked by Daniel Johnson Lab Lodged 10 Jun 2026

The question

To ask the Scottish Government what its current estimates are of the cost and timescale required to complete the remaining sections of the A9 dualling programme that are still to be upgraded.

The answer

This is an oral question, answered in the chamber on 18 Jun 2026. The answer is in the Official Report, linked below.

In the Official Report

1 contribution mention S7O-00091
  1. 18 Jun 2026
    General Question Time
    Daniel Johnson Lab Meeting of the Parliament

    To ask the Scottish Government what its current estimates are of the cost and timescale required to complete the remaining sections of the A9 dualling programme that are still to be upgraded. (S7O-00091)