To ask the Scottish Government what its current estimates are of the cost and timescale required to complete the remaining sections of the A9 dualling programme that are still to be upgraded. (S7O-00091)
Official Report · Chamber
General Question Time
This is the draft Official Report. The final version may differ.
link
To ask the Scottish Government what its current estimates are of the cost and timescale required to complete the remaining sections of the A9 dualling programme that are still to be upgraded. (S7O-00091)
link
The Scottish Government remains committed to dualling the A9 between Perth and Inverness by 2035. The programme is estimated to cost £3.97 billion at April 2025 prices. When adjusted for inflation, that is broadly similar to the £3.7 billion at April 2023 prices that was reported in December 2023 and below the original estimate of £3 billion at 2008 prices. The 2026 delivery plan will see the proportion of dual carriageway between Perth and Inverness increase to 50 per cent by the end of 2030, 67 per cent by the end of 2032, 91 per cent by the end of 2034, and 100 per cent by the end of 2035.
link
The latest tenders are clearly welcome, as they give some clarity about the completion of the A9, albeit some 28 years after it was originally promised. However, the costs require some examination. On a per kilometre basis, the latest sections will come in at around £20 million per kilometre, compared with £6.4 million per kilometre, adjusted for inflation, for the Kincraig to Dalraddy section. Looking internationally, I note that the Faroese Government has built tunnels—new roads under the sea—for £10 million per kilometre. Does the minister agree that it is vitally important that we have cost-effective delivery of infrastructure for economic growth? What lessons is the Scottish Government seeking to learn from international best practice, such as the Faroese example?
link
The Scottish Government is always open to learning from best practice internationally. Daniel Johnson is absolutely right to highlight the importance of cost effectiveness, but that has to be balanced with ensuring that the project can be delivered in a way that is cognisant of market capacity and ensures a minimum amount of disruption for road users. That balance is reflected in the process that the Scottish Government has undertaken.
link
There is some concern that the contracts will not deliver significant community and supply chain benefits. Can the minister set out what work has been done in that regard and say what lessons have been learned from the likes of the lower Thames crossing, which provides good examples of the delivery of such benefits?
link
As I hope that Willie Rennie recognises, the framework under which procurement is governed in this country was very much ahead of its time when it was brought in and has stood the test of time with regard to issues beyond the delivery of the infrastructure—which is of course the central focus and concern—such as ensuring that significant investment of public money delivers community benefit and other lasting benefits.
The procurement framework for the work on the A9 was launched by the Cabinet Secretary for Economy, Tourism and Transport earlier this month, and it sets out the broad provisions as we move towards the completion of the A9 over the next nine years.
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.