A9 Dualling Programme

Thursday 16 January 2025 Meeting of the Parliament Debate 58 contributions · 17 speakers Watch on Scottish Parliament TV

Speakers

Showing Jamie Halcro Johnston only · show everyone

Jamie Halcro Johnston’s contributions

1 contributions
Jamie Halcro Johnston Con Highlands and Islands
link

Goodness—follow that!

As others have done, I thank the committee for all its work. I also thank the committee clerks and, of course, Laura Hansler for her work and commitment to this vitally important cause. The debate is undoubtedly important for me and for my constituents, but it is a disgrace that we are having to have it again. It is a shameful indictment of the Government’s abject failure to deliver on its promises to my constituents.

At the beginning of 2025, the original target date for delivery, we should be preparing for the final stretch of dualling to be completed. Instead, we are here in Parliament, listening to more excuses from the Scottish Government on why it is not complete.

Many of us on the Conservative benches, along with the stalwart campaigners, some of whom are in the gallery today, have been campaigning to get the road dualled between Inverness and Perth for far too many years. My colleague Murdo Fraser and I launched our campaign for the dualling as far back as 2006, when we were both young, fresh-faced and full of hope—that should give you an idea of how long ago it was. Our petition attracted well over 20,000 signatures and clearly played a role in encouraging the SNP, which included the A9 dualling in its 2007 manifesto. However, here we are, 18 years later, still waiting.

I have been using the A9 all my life. I still just about remember heading up the old road on the way home to Orkney via the Kessock ferry and the long and winding route up to Scrabster. There have been major improvements since then, including new bridges and new stretches of dualled road. Between 1979 and 1997, under the Conservatives, 25 miles of the A9 were dualled between Inverness and Perth, and 12 miles of it were dualled between 2007 and 2022 under the SNP.

Although that work has undoubtedly made the journey shorter and safer than it was, the SNP promised us a fully dualled A9 between Inverness and Perth—and a safer road. However, travelling on the road last year, particularly during the summer, it felt as though almost every journey was disrupted by an accident. There is, of course, inconvenience in a journey delayed, but far worse is sitting in stationary traffic as emergency services pass or an air ambulance flies over, desperate to get as quickly as possible to the scene of another accident—sitting in the car with the fear that, just ahead, yet another incident may have been serious enough that another family or community will have to be told of the loss of a loved one. Too many have already lost their lives, and too many will probably experience that in the next few years.

We did not need to be here. All major projects face challenges and issues with the terrain or economic factors, as other members have said. That must always be considered. However, dualling the A9 is not some engineering marvel. Put simply, it is the building of a road where there is already a road; it should not challenge, as it has done, the abilities of a country with the engineering heritage and expertise of Scotland.

What galls most about this shameful saga is the dishonesty of the Scottish Government. The communities that are most reliant on the road could have accepted some delay to the project if real progress had been made or been obvious but, time and again, they were told by SNP ministers—or by SNP MSPs quoting SNP ministers—that all was fine and on track and that dualling would be completed, as promised, by 2025. Nothing has changed.

The deception went to the very top. Following his budget statement to the Parliament on 15 December 2022, I asked John Swinney, the then Deputy First Minister and Acting Cabinet Secretary for Finance and the Economy:

“Will the cabinet secretary finally admit what my Highlands and Islands constituents and his Perthshire constituents know, which is that the promised dualling of the A9 between Inverness and Perth will not be completed in 2025 or, indeed, any time soon?”

He responded:

“The Government’s position on the completion of the dualling of the A9 remains intact.”—[Official Report, 15 December 2022; c 86.]

To some people—possibly more charitable people than me—that response might be acceptable, if, ignoring the evidence of his own eyes on the lack of progress on the dualling, John Swinney was still naive enough to think that an engineering miracle could happen and the project could still be completed as promised.

However, that was not the case, because more than a week before John Swinney gave me that response in the chamber, the Scottish Government had been told that the dualling would not be completed by 2025. An email had been sent that said:

“it should be made clear that the current published completion date of 2025 will no longer apply to the Programme.”

That email was sent directly to the then Deputy First Minister, John Swinney. When John Swinney told me that nothing had changed, that was not true. He knew that the 2025 date would not be met, but he kept the deception going that it would. John Swinney, the then Deputy First Minister and now First Minister, misled the Parliament when he said that the SNP promise to dual the A9 would be delivered.

If John Swinney is confident that he did not mislead the Parliament—or the communities or campaigners who will have heard his comments—he should refer himself to his own newly appointed independent adviser on the ministerial code, surely confident that they will clear him of any breach. Of course, I doubt that he will, because this Government does not do accountability or transparency. Even when it knew definitively that the dualling would not happen as promised, it refused to be honest with Parliament and the public. As has been the case far too often with this Government—the ferries fiasco is an obvious example—no one has lost their job.

This has been a shameful saga that has involved endless broken promises, deadlines missed, communities lied to, lives ruined and, of course, lives lost. Too many families now mourn loved ones who have been lost on the A9. So, my message to the SNP Government is simple: no more failures, no more excuses—get the A9 dualled.

Motions, questions and votes

Linked from this item of the Official Report

No recorded division on this motion that day: decisions taken without a vote are not in the divisions feed.

  1. General Question Time Questions · 1
  2. Changing Places Toilet Fund Questions · 8
  3. Child Poverty Questions · 8
  4. Swimming (Children and Young People) Questions · 6
  5. Budget 2025-26 (Drug and Alcohol Services) Questions · 6
  6. NHS Dumfries and Galloway (Delayed Discharge) Questions · 4
  7. Bovaer Questions · 5
  8. Royal College of Nursing Report First Minister’s Questions · 10
  9. Royal College of Nursing Report First Minister’s Questions · 8
  10. Climate Action First Minister’s Questions · 6
  11. Copenhagen Infrastructure Partners First Minister’s Questions · 6
  12. Bowel Screening Programme (Extension) First Minister’s Questions · 8
  13. Sexual Assault (Hospitals) First Minister’s Questions · 7
  14. Scottish National Investment Bank (XLCC) First Minister’s Questions · 2
  15. Urgent Cancer Referrals (Timeframes) First Minister’s Questions · 2
  16. Diabetes Technology (Guidelines) First Minister’s Questions · 2
  17. Department for Work and Pensions (Data) First Minister’s Questions · 3
  18. Lloyds Banking Group Dunfermline (Closure) First Minister’s Questions · 2
  19. Exploration of Oil and Gas First Minister’s Questions · 2
  20. Foot-and-mouth Disease First Minister’s Questions · 3
  21. Economic, Social and Cultural Rights (Highlands and Islands) Members’ business · 29
  22. Net Zero and Energy, and Transport Questions · 1
  23. Rail Services (Trains Between Fife and Edinburgh) Questions · 8
  24. Road Improvements Questions · 6
  25. Borders Railway (Extension) Questions · 6
  26. Service Quality Inspection Regime Data (ScotRail Ticket Offices) Questions · 6
  27. Decarbonising Social Housing (Rural Areas) Questions · 6
  28. Conservancy Fee (Leisure Vessels on the River Clyde) Questions · 6
  29. Renewable Energy Output (Value to United Kingdom Economy) Questions · 7
  30. Energy Efficiency Area-based Grants (Reallocation of Unused Funds) Questions · 5
  31. UK Covid-19 Inquiry Module 1 Report (Scottish Government Response) Statement · 29
  32. A9 Dualling Programme Debate · 58
  33. Decision Time Decision time · 2
  34. Health and Social Care (Rural Scotland) Members’ business · 53

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.