On that point, it is wrong for Fergus Ewing to imply that Transport Scotland has somehow produced the December 2023 plan without having continuous, regular engagement with the industry to identify capacity. That is part of the work of identifying what would be sustainable.
I will move on to some of Jackson Carlaw’s points, but I also want to look ahead. I confirm that made orders will be published tomorrow for the Crubenmore to Kincraig project, which will mean that made orders will have been published for 92 per cent of the length of the A9 dualling programme, which might address Murdo Fraser’s points about issues for properties.
Other significant milestones on the A9 dualling programme that the Government is working towards during 2025 include the commencement of statutory procedures for the Pass of Birnam to Tay crossing project and the commencement of main construction works on the third contract, for Tomatin to Moy, both in spring 2025. They also include the award of the fourth contract, for Tay crossing to Ballinluig, and the commencement of procurement for the fifth contract, for Pitlochry to Killiecrankie, both in summer 2025. Another milestone is concluding the process of further decision making on the use of MIM in late 2025. Achievement of those milestones will represent real practical progress.
Mark Ruskell raised issues around Dunkeld. He knows that I am alive to those issues and active in discussing with Transport Scotland what might be possible. Of course, remember that that roundabout was not part of the original proposals, but after discussion with the community, it was a response to a co-created request.
In parallel with that work, the Government will progress towards the completion of its £5 million package of additional engineering measures that are intended to address the perceived contributory factors to collisions, and I say to Beatrice Wishart that those measures are expected to be completed in March this year.
The A9 safety group will continue to meet, and I encourage everyone to access the new A9 safety web portal. We will continue to have engagement plans and there will be a briefing in Perth in May or early June. As I indicated earlier, there will be regular committee responses and updates.
Jackson Carlaw made an important point about the capacity of the workforce. I have met SSEN to discuss issues across Scotland, not just about roads or the A9, but about capacity for the renewable sector, and there has been engagement and careful consideration of workforce capability. The committee made the point that it is easier to plan when there is certainty. If there is chopping and changing and things are reordered and rescheduled, that does not provide certainty. We will have to strike a balance in our delivery. Jackson Carlaw also assumed that an acceleration of the project would allow an increase in capacity, although it might do the reverse, which the report has highlighted. It could pose a risk for workforce issues and compound things, which could inadvertently cause delay.
Foysol Choudhury made a number of points about funding. I refer him to my earlier remarks.
I am conscious that I need to bring my remarks to a close. I reiterate my commitment to providing transparency and certainty on the progress of the A9 dualling programme as it moves forward in the months and years ahead. I encourage members to take advantage of the regular updates and briefings, and to sign up for the newsletters and publicise them to their constituents so that they can remain informed on the progress of this vital programme of work. The committee did its job of scrutiny. Although it looked at the past, it also made recommendations for the future.
I have been in post for 18 months, and was involved in the work to publish the plan in December 2023. I am very conscious of my duty to the Parliament on transparency, accountability and scrutiny. I take those responsibilities very seriously, which I hope that I have evidenced in what I have said and in the actions that I have taken, as Emma Roddick reflected.