Parliament Workbench
Data: Official Report to 24 Nov 2026

Official Report · Chamber

A9 Dualling Programme

Thursday 16 January 2025 Meeting of the Parliament Debate 58 contributions · 17 speakers Watch on Scottish Parliament TV

Speakers

Showing Fiona Hyslop only · show everyone

Fiona Hyslop’s contributions

14 contributions
Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

I begin by thanking all who contributed to the committee’s work on this inquiry, which arose from its consideration of petition PE1992, which was lodged in 2022. In my response to the committee, which was issued on 9 January, in my covering letter and again today, I welcome the committee’s consideration of the issues relevant to the future progress of the dualling programme.

Much has changed since the committee began its consideration of the petition, and its report recognises that. The delivery plan for completion of the A9 dualling programme was announced in December 2023. That plan involves the procurement of four design and build contracts as well as, subject to further decisions to be made in late 2025, the procurement of two mutual investment model—MIM—contracts. That approach was supported by a Cabinet decision to prioritise the completion of the A9 dualling programme within its budgets.

Since the announcement of that plan, the Government has made good progress, including through commencing procurement of the Tay crossing to Ballinluig project in May 2024; the awarding of the contract for the Tomatin to Moy project in July 2024; publication of orders for the Killiecrankie to Glen Garry and Dalraddy to Slochd projects; and progression of the land acquisition processes for the Tay crossing to Ballinluig, Pitlochry to Killiecrankie, Glen Garry to Dalwhinnie and Dalwhinnie to Crubenmore projects.

I will say more in my closing speech about the progress that has already been made and the further progress that is expected during 2025.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

I would like to move on.

On Tuesday of this week, Transport Scotland published a report on its assessment of rescheduling and acceleration proposals for the A9 dualling project, which was an issue that the committee referred to in its report.

On the basis of the assessment’s findings, Transport Scotland’s report did not recommend rescheduling or trying to accelerate the dualling programme, although it did recommend that further assessment should be made of the potential for an advanced works contract at Dalnaspidal junction. I have asked Transport Scotland to take that forward.

It should be borne in mind that the potential rescheduling opportunities are limited. The first two contracts for the A9 dualling programme have already been constructed and are operational, the third contract reached the contract award stage in July 2024, and the contract award for the fourth contract is expected in summer 2025. Rescheduling is therefore feasible only in respect of the fifth, sixth, seventh and eighth contracts, which are due to begin procurement in summer 2025, winter 2026-27, summer 2027 and winter 2028-29 respectively.

However, as the seventh contract, for the section from the pass of Birnam to the Tay crossing, is already scheduled to start at the earliest date possible, based on the expected date of completion of that project’s statutory processes, and is not dependent on any other project, any change of date would mean delaying completion beyond the currently expected date. In practical terms, the scheduling options are therefore limited to the timing of procurement and construction of the fifth contract, for the section from Pitlochry to Killiecrankie, of the sixth contract, which is the A9 north MIM contract, and the eighth contract, which is the A9 central MIM contract.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

I will come to you shortly, Mr Ewing.

The report published earlier this week shows that rescheduling and reversing the procurement sequence of the sixth and eighth contracts would result in an expected delay of around a year in the overall completion of the dualling programme. That is due to the need to delay procurement and construction of the fifth contract to avoid an overlap that the current delivery plan was developed to avoid because of the implications for road user disruption. Those changes in the procurement sequence would also reduce continuity of the bidding pipeline for those projects, making them likely to be less attractive to bidders.

I appreciate that there is a range of views about how completion of the dualling programme should be achieved. On that note, I will take an intervention from Mr Ewing.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

Thank you, Deputy Presiding Officer.

There were a number of points in Fergus Ewing’s intervention. As he will know, because he has attended the briefings that I have provided on the A9 project, the work on the sections will not happen one by one. The whole point is that work will happen concurrently across the A9. Work will happen on the south of the A9 at the same time as work on the north of the A9, and the processes for them will happen simultaneously. That is why trying to reorder the current scheduling would have an impact. There would be a danger of concurrent issues that would affect both price and certainty of delivery. Certainty is something that the committee was very keen on.

I believe that the Transport Scotland report demonstrates that the plan that was established and published in December 2023 is robust and represents a practical way to undertake this large programme of works in the years ahead. We remain fully focused on and committed to delivering dualling of 50 per cent of the A9 between Perth and Inverness by the end of 2030, 85 per cent by the end of 2033 and 100 per cent by the end of 2035.

As I noted in my response to the committee, the Government considers that many of the committee’s conclusions and recommendations in its inquiry report relate to two main themes: transparency and certainty. I hope that the various activities that I have outlined in my response demonstrate the action that we are taking on those themes. I am wholly committed to progressing the programme and to listening to Parliament, local residents and businesses, and keeping them informed and engaged. We have regular meetings and publish newsletters and there is a new A9 dualling website.

I also noted the committee’s recommendation regarding the establishment of a new parliamentary committee. The Government is clear that that is a matter for Parliament to determine. The Government will, of course, direct its reporting to the appropriate committee, which is currently the Net Zero, Energy and Transport Committee. The first of the six-monthly update reports to that committee was issued on 21 November 2024, and I have written to it on six other occasions with updates.

It is essential that there is a sound evidence base for decision making on the use of mutual investment model contracts for the contracts to be procured, in line with the requirements of the Scottish public finance manual and the Treasury green book. The work on that, which has already started, involves updating cost estimates, undertaking further market consultation with contractors and financial investors, updating the outline business case for the programme and undertaking the necessary assurance reviews of that work. There is continuous engagement with contractors, as members might appreciate.

Once those activities have been completed, ministers will be in a position to determine whether the current delivery plan intention to procure two MIM contracts will be confirmed. The Government will then ask to make a statement to Parliament to set out the conclusion of the further decision-making processes. I want to be very clear to Parliament about the Government’s position on that work. If a decision is taken not to make use of MIM contracts on the A9 dualling programme, we will implement an alternative approach such as use of capital-funded design and build contracts, and there is a Cabinet decision to prioritise the completion of the A9 dualling programme within Scottish Government budgets.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

I was about to close, but, if I have time, I will take the intervention, Deputy Presiding Officer.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

I am not sure where the member’s comment that the statement would be brought forward into 2026 came from. That would be a matter for Parliament. I am very keen to move things forward, so I take responsibility for trying to bring the statement to Parliament in such a state that there can be proper accountability, which is required in relation to such a major decision.

I have been updating Parliament since December 2023 and I will continue to update it and local MSPs on progress. The design and development of the different sections will involve engagement with and input from local residents, businesses and communities. With the Tomatin to Moy construction work starting in earnest in the autumn, following preparatory works that have already started, there will be continuous dualling work until 2035. I reiterate that, as I said to Mr Ewing, there will most often be work on more than one site on the A9 at any given time. I trust that that will be recognised in members’ contributions today.

15:19

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

I am already accountable to Parliament. I answer questions and I respond. I have given statements and will continue to do so. I report to the Net Zero, Energy and Transport Committee. It would be wrong for the Government to tell Parliament what to do in carrying out its scrutiny and accountability responsibilities. I, and anyone else related to this issue, will absolutely respond and be accountable to the relevant committee. Having been the deputy convener of the Net Zero, Energy and Transport Committee under the convenership of Edward Mountain, I know that it is a very strong committee, and I am happy to report to it unless the committee and Parliament decide otherwise. It is for the Parliament and not the Government to decide whom the Government is accountable to. That is how Parliament works.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

So did I.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

Edward Mountain noted that Keith Brown was a transport minister. He had responsibility for transport between 2010 and 2018. Alex Neil led on the project from 2010 to 2012 and, when Nicola Sturgeon became First Minister, Keith Brown took over lead responsibility. He was not called to the committee to give evidence, but his written submission, which I have read, gives an interesting perspective on the issues. Mr Mountain might want to acknowledge that there was continuity of ministerial responsibility for transport, albeit that that minister did not always have lead responsibility for the A9.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

On a point of factual accuracy, there was a separate committee for the legislative aspects of the Queensferry crossing, but the monitoring thereafter reverted to the relevant committee.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

I refer to my opening remarks—that issue absolutely will not cause a delay. In my opening statement, I made a point of providing assurance on funding.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

I have listened carefully to the range of points that have been raised in the course of the debate. As I am sure that all members will have done, I have reflected on Maurice Golden’s contribution on the impact of fatalities on families and local communities. Before I turn to addressing members’ other points, I want to highlight the strategic importance of the delivery plan that the Government announced in December 2023, which was the first such plan ever to be published setting set out the milestones, dates and actions for progressing delivery of the A9 project. I will comment further on the progress that has been achieved and on what is expected in the year ahead, because we are getting on with all those actions.

I have absolutely learned the lessons about transparency and certainty. Edward Mountain seemed to be surprised that I focused on those aspects in my opening remarks, but I did so because those were the committee’s themes and the focus of its recommendations for improvements. While I am on the subject of Edward Mountain, I also reflect on his point about the work capacity of the Net Zero, Energy and Transport Committee—and that was before land reform matters were allocated to it. A future Parliament might want to consider those points when looking at transport and infrastructure.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

If the member had listened to my previous point, he would have heard me say that there is merit in transport and infrastructure being dealt with separately. It would be for a new Parliament to decide where those areas should be dealt with, precisely because of the workload issues that he has mentioned.

The delivery plan that we produced in December 2023 was developed to balance three key factors: market capacity to bid for and construct the projects making up the A9 dualling programme, disruption to road users and challenging financial constraints. The delivery plan provides much-needed certainty for road users, local communities and the construction industry on when works are expected. It transparently identifies key milestones when critical decisions are required to progress with procurement or make a contract award, and it identifies when dualling works on individual contracts are expected to become operational. The delivery plan was, and continues to be, supported by a Cabinet decision to prioritise completion of the A9 dualling programme within its budgets. It remains the Government’s focus to complete the A9 dualling programme in line with that plan.

On progress, in addition to the significant milestones that have been achieved, which I mentioned earlier, a number of advanced contracts have been procured for works such as ground investigations. Those are each important in helping to de-risk the main construction contracts.

The Government has also taken steps to engage with interested parties. In January 2024, a briefing was held for MSPs, and in February 2024, a stakeholder briefing was held in Inverness, followed by a public exhibition that visited Inverness, Aviemore, Dalwhinnie, Pitlochry and Perth. At the end of February 2024, the dedicated A9 dualling website was launched, and quarterly newsletters were issued in spring, summer and autumn 2024. In November 2024, the first of what will be regular updates on progress was issued to the Net Zero, Energy and Transport Committee, and a briefing for MSPs was held in December 2024, where there was extensive discussion with Fergus Ewing on the pros and cons of framework contracts. I heard the points that he raised on framework contracts during the debate. I am prepared to continue that conversation, but, in the spirit of candour, I cannot imply that that will definitely happen, but we want to go ahead and provide certainty with the plan that we have. I am open to those discussions.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

On that point, it is wrong for Fergus Ewing to imply that Transport Scotland has somehow produced the December 2023 plan without having continuous, regular engagement with the industry to identify capacity. That is part of the work of identifying what would be sustainable.

I will move on to some of Jackson Carlaw’s points, but I also want to look ahead. I confirm that made orders will be published tomorrow for the Crubenmore to Kincraig project, which will mean that made orders will have been published for 92 per cent of the length of the A9 dualling programme, which might address Murdo Fraser’s points about issues for properties.

Other significant milestones on the A9 dualling programme that the Government is working towards during 2025 include the commencement of statutory procedures for the Pass of Birnam to Tay crossing project and the commencement of main construction works on the third contract, for Tomatin to Moy, both in spring 2025. They also include the award of the fourth contract, for Tay crossing to Ballinluig, and the commencement of procurement for the fifth contract, for Pitlochry to Killiecrankie, both in summer 2025. Another milestone is concluding the process of further decision making on the use of MIM in late 2025. Achievement of those milestones will represent real practical progress.

Mark Ruskell raised issues around Dunkeld. He knows that I am alive to those issues and active in discussing with Transport Scotland what might be possible. Of course, remember that that roundabout was not part of the original proposals, but after discussion with the community, it was a response to a co-created request.

In parallel with that work, the Government will progress towards the completion of its £5 million package of additional engineering measures that are intended to address the perceived contributory factors to collisions, and I say to Beatrice Wishart that those measures are expected to be completed in March this year.

The A9 safety group will continue to meet, and I encourage everyone to access the new A9 safety web portal. We will continue to have engagement plans and there will be a briefing in Perth in May or early June. As I indicated earlier, there will be regular committee responses and updates.

Jackson Carlaw made an important point about the capacity of the workforce. I have met SSEN to discuss issues across Scotland, not just about roads or the A9, but about capacity for the renewable sector, and there has been engagement and careful consideration of workforce capability. The committee made the point that it is easier to plan when there is certainty. If there is chopping and changing and things are reordered and rescheduled, that does not provide certainty. We will have to strike a balance in our delivery. Jackson Carlaw also assumed that an acceleration of the project would allow an increase in capacity, although it might do the reverse, which the report has highlighted. It could pose a risk for workforce issues and compound things, which could inadvertently cause delay.

Foysol Choudhury made a number of points about funding. I refer him to my earlier remarks.

I am conscious that I need to bring my remarks to a close. I reiterate my commitment to providing transparency and certainty on the progress of the A9 dualling programme as it moves forward in the months and years ahead. I encourage members to take advantage of the regular updates and briefings, and to sign up for the newsletters and publicise them to their constituents so that they can remain informed on the progress of this vital programme of work. The committee did its job of scrutiny. Although it looked at the past, it also made recommendations for the future.

I have been in post for 18 months, and was involved in the work to publish the plan in December 2023. I am very conscious of my duty to the Parliament on transparency, accountability and scrutiny. I take those responsibilities very seriously, which I hope that I have evidenced in what I have said and in the actions that I have taken, as Emma Roddick reflected.

Motions, questions and votes

Linked from this item of the Official Report

No recorded division on this motion that day: decisions taken without a vote are not in the divisions feed.

  1. General Question Time Questions · 1
  2. Changing Places Toilet Fund Questions · 8
  3. Child Poverty Questions · 8
  4. Swimming (Children and Young People) Questions · 6
  5. Budget 2025-26 (Drug and Alcohol Services) Questions · 6
  6. NHS Dumfries and Galloway (Delayed Discharge) Questions · 4
  7. Bovaer Questions · 5
  8. Royal College of Nursing Report First Minister’s Questions · 10
  9. Royal College of Nursing Report First Minister’s Questions · 8
  10. Climate Action First Minister’s Questions · 6
  11. Copenhagen Infrastructure Partners First Minister’s Questions · 6
  12. Bowel Screening Programme (Extension) First Minister’s Questions · 8
  13. Sexual Assault (Hospitals) First Minister’s Questions · 7
  14. Scottish National Investment Bank (XLCC) First Minister’s Questions · 2
  15. Urgent Cancer Referrals (Timeframes) First Minister’s Questions · 2
  16. Diabetes Technology (Guidelines) First Minister’s Questions · 2
  17. Department for Work and Pensions (Data) First Minister’s Questions · 3
  18. Lloyds Banking Group Dunfermline (Closure) First Minister’s Questions · 2
  19. Exploration of Oil and Gas First Minister’s Questions · 2
  20. Foot-and-mouth Disease First Minister’s Questions · 3
  21. Economic, Social and Cultural Rights (Highlands and Islands) Members’ business · 29
  22. Net Zero and Energy, and Transport Questions · 1
  23. Rail Services (Trains Between Fife and Edinburgh) Questions · 8
  24. Road Improvements Questions · 6
  25. Borders Railway (Extension) Questions · 6
  26. Service Quality Inspection Regime Data (ScotRail Ticket Offices) Questions · 6
  27. Decarbonising Social Housing (Rural Areas) Questions · 6
  28. Conservancy Fee (Leisure Vessels on the River Clyde) Questions · 6
  29. Renewable Energy Output (Value to United Kingdom Economy) Questions · 7
  30. Energy Efficiency Area-based Grants (Reallocation of Unused Funds) Questions · 5
  31. UK Covid-19 Inquiry Module 1 Report (Scottish Government Response) Statement · 29
  32. A9 Dualling Programme Debate · 58
  33. Decision Time Decision time · 2
  34. Health and Social Care (Rural Scotland) Members’ business · 53

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.