A9 Dualling Programme

Thursday 16 January 2025 Meeting of the Parliament Debate 58 contributions · 17 speakers Watch on Scottish Parliament TV

Speakers

Showing Maurice Golden only · show everyone

Maurice Golden’s contributions

3 contributions
Maurice Golden Con North East Scotland
link

As a member of the Citizen Participation and Public Petitions Committee, I thank all those who have participated in the inquiry and those who have supported the committee in its work, as well as the petitioner, Laura Hansler. I also recognise and pay tribute to all those who have tragically lost their lives on the A9 during the preceding years and decades.

I drive on the A9, which is north of Perth, maybe a couple of times a year. When driving that road, there is always a slight sense of unease. There is a feeling that is not experienced on other roads. Almost without fail, you will see something; it may be a car pulling across the carriageway with barely enough time or a tight overtaking manoeuvre. There will always be something that makes you take a deep intake of breath.

However, the communities that live nearby and rely on the A9 do not have to deal with driving on that road a couple of times a year; for some, it is a daily experience, and it is taking its toll on those communities—emotionally and economically, and tragically, with far too many people seriously injured or worse as a result of road traffic incidents.

The reality is that the communities have been badly let down by the Scottish Government and Transport Scotland in their handling of the A9 dualling. That is why the findings of the inquiry are important. The communities deserve answers, and we owe it to them and to all future users of the A9 to learn from the failures of the past and to ensure that the project now moves forward. If the Scottish Government can do that, it can begin to rebuild the public’s trust.

I have reviewed the Government’s written response to the committee’s report and, unfortunately, it is far from clear about the degree to which it is willing to accept and learn from the failings of the past. When we look at those failings, we see that the Government’s approach to transparency has been seriously lacking and that it has contributed significantly to the current state of the project. When ex-First Minister Nicola Sturgeon accepted that, she said to the committee:

“I would ask myself whether we were as candid as we should have been with ourselves, as well as with the public, about just how challenging it would always have been to meet the target”—[Official Report, Citizen Participation and Public Petitions Committee, 29 May 2024; c7-8.]

When we consider transparency, we have to look at the timeline. It was 8 February, 2023—less than two years ago—when the Scottish Government came clean and said that the 2025 completion date was no longer achievable. There is a massive disconnect between saying less than two years ago that it would not be complete by 2025 and now saying that it will not be completed until 2035.

During the past couple of days, Transport Scotland has doubled down on that and has said that the 2035 timeline cannot be accelerated, effectively claiming that any attempts to accelerate the project might slow it down further. That seems like a staggering and bizarre claim, but if it is the case, it points to the degree to which the Scottish Government deceived the public by keeping up the pretence—until two years ago—that the project could be completed this year. Whether the Scottish Government is willing to accept it or not, the reality is that either hanging on to the 2025 timeline for so long was an attempt at deceit or the revised and moveable 2035 timeline is an attempt to deceive. Which is it? Of course, it could be both.

The Government has acted in bad faith for too long, and we can have no more deceit. We need an evidence-based and transparent timeline, and we need parliamentary scrutiny. The committee was clear that the Government had evaded scrutiny in the past. In reading the Government’s response to the committee, it appears that the Government is trying to water down the role of parliamentary scrutiny and has dodged the question of establishing a committee that could oversee the dualling of the A9 and other major projects.

Maurice Golden Con North East Scotland
link

The cabinet secretary will be aware that I sat on the Parliamentary Bureau—

Maurice Golden Con North East Scotland
link

—and I am aware of the voting on that issue. The bureau is where the Scottish National Party could back the establishment of a specific committee or, as part of the bureau process, could consider the Net Zero, Energy and Transport Committee covering such a large portfolio. That would help—that is the fundamental point of the committee’s report.

The committee also came to the conclusion that the Government’s failure to reach agreement on programme funding was a significant factor contributing to the delays that we are now experiencing. Looking to the future, the committee is not confident that the funding is in place to ensure completion by 2035. It calls on the Government to be clear with its future funding plans and the timescales for those plans and to ensure that those funding plans can be scrutinised.

15:27

Motions, questions and votes

Linked from this item of the Official Report

No recorded division on this motion that day: decisions taken without a vote are not in the divisions feed.

  1. General Question Time Questions · 1
  2. Changing Places Toilet Fund Questions · 8
  3. Child Poverty Questions · 8
  4. Swimming (Children and Young People) Questions · 6
  5. Budget 2025-26 (Drug and Alcohol Services) Questions · 6
  6. NHS Dumfries and Galloway (Delayed Discharge) Questions · 4
  7. Bovaer Questions · 5
  8. Royal College of Nursing Report First Minister’s Questions · 10
  9. Royal College of Nursing Report First Minister’s Questions · 8
  10. Climate Action First Minister’s Questions · 6
  11. Copenhagen Infrastructure Partners First Minister’s Questions · 6
  12. Bowel Screening Programme (Extension) First Minister’s Questions · 8
  13. Sexual Assault (Hospitals) First Minister’s Questions · 7
  14. Scottish National Investment Bank (XLCC) First Minister’s Questions · 2
  15. Urgent Cancer Referrals (Timeframes) First Minister’s Questions · 2
  16. Diabetes Technology (Guidelines) First Minister’s Questions · 2
  17. Department for Work and Pensions (Data) First Minister’s Questions · 3
  18. Lloyds Banking Group Dunfermline (Closure) First Minister’s Questions · 2
  19. Exploration of Oil and Gas First Minister’s Questions · 2
  20. Foot-and-mouth Disease First Minister’s Questions · 3
  21. Economic, Social and Cultural Rights (Highlands and Islands) Members’ business · 29
  22. Net Zero and Energy, and Transport Questions · 1
  23. Rail Services (Trains Between Fife and Edinburgh) Questions · 8
  24. Road Improvements Questions · 6
  25. Borders Railway (Extension) Questions · 6
  26. Service Quality Inspection Regime Data (ScotRail Ticket Offices) Questions · 6
  27. Decarbonising Social Housing (Rural Areas) Questions · 6
  28. Conservancy Fee (Leisure Vessels on the River Clyde) Questions · 6
  29. Renewable Energy Output (Value to United Kingdom Economy) Questions · 7
  30. Energy Efficiency Area-based Grants (Reallocation of Unused Funds) Questions · 5
  31. UK Covid-19 Inquiry Module 1 Report (Scottish Government Response) Statement · 29
  32. A9 Dualling Programme Debate · 58
  33. Decision Time Decision time · 2
  34. Health and Social Care (Rural Scotland) Members’ business · 53

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.