“The 2018/19 audit of NHS Lothian: Delay to the opening of the Royal Hospital for Children and Young People”

Thursday 16 January 2020 Public Audit and Post-legislative Scrutiny Committee About 09:45–10:45 Committee business 149 contributions · 10 speakers

Speakers

Showing Anas Sarwar only · show everyone

Anas Sarwar’s contributions

22 contributions
Anas Sarwar Lab Glasgow
link

Good morning, Auditor General. I am keen to understand the level of Government oversight of the project. Given the similarities between this project and the project to build the new Queen Elizabeth university hospital in Glasgow, with regard to not only the constructor but some of the outcomes, why were adequate lessons not learned? Can you give us a quick overview of your understanding of the level of Government oversight of the project to build the new Royal hospital for sick children?

Anas Sarwar Lab Glasgow
link

I will come back to the issue of the water supply and infection. It is important to note that there was an overlap in the timelines, which meant that it was difficult to learn lessons at an early stage.

In general, do you think that there was adequate Government oversight of the project to build the new Royal hospital?

Anas Sarwar Lab Glasgow
link

Let us look at exhibit 1 again to get an understanding of the similarities between the Queen Elizabeth and Lothian projects. Are you aware of whether the same people—not roles—were responsible for Scottish Government oversight of those projects?

Anas Sarwar Lab Glasgow
link

If it was the same team, would the same person be responsible for the team?

Anas Sarwar Lab Glasgow
link

The programme board had day-to-day responsibility for managing the project. You said that the Scottish Government was a member of the programme board, but quite often did not attend its meetings. Do you know how many meetings were held and how many times the Scottish Government failed to attend?

Anas Sarwar Lab Glasgow
link

Excellent. Did the same team represent the Scottish Government on the programme boards for the Lothian and Queen Elizabeth projects?

Anas Sarwar Lab Glasgow
link

Would a team from the same area of responsibility in the Scottish Government sit on the programme board? Would that be how it worked?

Anas Sarwar Lab Glasgow
link

Great.

What were the reporting mechanisms for the project team that was responsible for project activities and was located on the site? Was there a Scottish Government representative on that team, as there was on the programme board?

Anas Sarwar Lab Glasgow
link

If there was no Government representative, what were the reporting mechanisms from the project team to the board and the Government?

Anas Sarwar Lab Glasgow
link

Were there individuals from not just the Scottish Government but elsewhere who sat on the programme board and the project team?

Anas Sarwar Lab Glasgow
link

Do we know whether any of same people—from the Scottish Government or elsewhere—sat on the Lothian programme board and project team and on the programme board and project team for the Queen Elizabeth project?

Anas Sarwar Lab Glasgow
link

There are three names listed under “Professional advisors” in exhibit 1. Were any of the three also professional advisers on the Queen Elizabeth project?

Anas Sarwar Lab Glasgow
link

No problem.

Arcadis NV was the independent tester. Is it a regularly used independent tester for new hospital projects across the Scottish national health service?

Anas Sarwar Lab Glasgow
link

I will step back to the project company. Are you aware of what checks were done on Brookfield Multiplex before it was commissioned to carry out the hospital project? For example, has it ever built a hospital, other than the Queen Elizabeth, in the United Kingdom?

Anas Sarwar Lab Glasgow
link

Do we know whether Brookfield Multiplex had ever built a hospital in the UK before it built these two hospitals?

Anas Sarwar Lab Glasgow
link

Okay.

The Auditor General said, quite rightly, that there was an overlap in the two projects starting. The concern about the ventilation system is less about how the problem could have been prevented at the construction stage and more about why it was realised so late on in the process—at the opening stage—that there was an issue with the ventilation system.

Anas Sarwar Lab Glasgow
link

No. I am talking about the hospital in Edinburgh. There is clearly a link between the water supply and the ventilation system, given that water supplies the ventilation system. If there was a concern that the design of the ventilation system was flawed, why was that issue highlighted so late in the process, which meant that NHS Lothian and the health secretary made their decision so late?

Anas Sarwar Lab Glasgow
link

Thank you; it was very helpful.

I have a final question. Is Health Facilities Scotland the responsibility of NHS Scotland, or is there a health facilities part of individual boards as well?

  1. 09:00 Decision on Taking Business in Private Procedure · 1
  2. 09:00 Section 22 Reports Committee business · 187
  3. 09:45 Section 22 Reports Committee business · 149

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.