A96 Dualling (Inverness-Nairn Timeline) (PE2132)

Wednesday 19 February 2025 Citizen Participation and Public Petitions Committee About 10:45 Petitions 8 contributions · 2 speakers

Speakers

Choose an MSP to read only their contributions

The record

8 contributions
Jackson Carlaw Con The Convener · Eastwood
link

That brings us to the last of the new petitions. PE2132 was lodged by the Inverness Courier and calls on the Scottish Parliament to urge the Scottish Government to publish a clear timeline for the dualling of the A96 between Inverness and Nairn and the construction of a bypass for Nairn, by Easter 2025. I presume that the Inverness Courier is known to Mr Ewing, given his earlier intervention.

As the background to the petition reminds us, the Scottish Government committed in 2011 to dualling the full length of the A96 between Inverness and Aberdeen by 2030. At that time, the expectation was that work to dual the A96 would follow the completion of the dualling of the A9, which, as the committee knows all too well from our inquiry, has not progressed as originally timetabled—to put it mildly.

In 2018, a public inquiry was held to consider objections to specific proposals in the draft orders for the section of the road between Inverness and Nairn. The outcome of the public inquiry was that Scottish ministers agreed that the orders could be made subject to amendment. The road orders and compulsory purchase order were subsequently made on 22 February 2024, signalling the completion of the statutory process for dualling the A96 between Inverness and Nairn.

In its response to the petition, Transport Scotland referred to the Cabinet Secretary for Transport’s statement in November 2024, in which she confirmed that the Government’s favoured position is to fully dual the A96, and it stated that the dualling process from Inverness to Nairn, including the Nairn bypass, is under way. Transport Scotland’s response also states:

“work is also underway to determine the most suitable procurement option”—

heavens—

“for delivering the A96 Inverness to Nairn including Nairn bypass dualling scheme ... It is expected that the work ... will take a further 12 months”

and will be closely aligned

“with the Mutual Investment Model ... assessment work being undertaken on the A9 Dualling”.

Transport Scotland is appearing to suggest that is only after the procurement option is identified that a timetable for progress can be set.

Well, well. Do members have any comments or suggestions for action? Do I need to even look up before I call Mr Ewing?

Fergus Ewing SNP Inverness and Nairn
link

I am pleased that the Inverness Courier, in its wisdom, has chosen to lodge the petition. I thank it for doing so and for championing the issue, which is of massive concern to everyone in Nairn as well as the wider north-east. In one way, it is quite a modest ask. It is not demanding that the whole project be completed by a certain time. It is simply asking for the Government to publish a clear timeline for the dualling of the A96 between Inverness and Nairn, and for the construction of a bypass for Nairn.

You have outlined the sad history of the work to dual the A96 by 2030. Thus far, £90 million has been spent on preparatory work for the dualling of the A96, but not one centimetre of tarmac has been laid. Many people, including me, find that almost incomprehensible.

In the Government response in defence of the lack of a timeline, a number of points are made, which I will cover briefly, in the hope that the cabinet secretary might appear before us to give evidence on that and other transport measures, as we might have mooted before. I hope that that will give her some indication of the issues with which she will be concerned and which will certainly be put to her.

The first point is on the made orders, which are an important milestone in the statutory process to determine which properties require to be compulsorily purchased and which ancillary roads need to be adjusted to fit in with the new road. Those are the two main made orders, although there are subsidiary ones. The response says that they were made on 12 March 2024, which is quite true.

There is something that the response does not say, however. I have a document here—I believe that we are not allowed to brandish documents, otherwise I would do so right now—from Transport Scotland. It is a 2016 document, which states that the made orders were expected to be published later that year. Well, that was 2016; we then got to 2024. What happened?

It used to be that draft made orders were displayed on the Transport Scotland website. They were displayed in draft, and they were ready for ages in draft. The year in the provisional date on this draft was 2-0-1-blank. In other words, it was planned that this work would be done nearly a decade ago. It was also promised in the 2011 manifesto and slightly before that by Alex Salmond.

The first point that I want to make is that no explanation has ever been given as to why there was a delay of eight years, which is the longest delay ever in respect of reaching this important stage of the proceedings. That is point 1.

The Cabinet Secretary for Transport has a personal enthusiasm for taking the issue on, to be fair to her. She is the fourth transport minister that we have had in four years, which is not terrific. Setting that aside, the submission says that the reason for the delay is that

“It is fundamental that ... authorities allow sufficient time to properly consider the range of procurement routes available”.

How much more time do they need? I do not want to be too political, but the Government has had four years of this parliamentary session, and I have raised the issue, as members will appreciate, fairly frequently during those four years. That is point 2.

There are two final points that I want to make. I do not want to go on forever, convener—I have a habit of doing that.

Fergus Ewing SNP Inverness and Nairn
link

There is a proposal, which is that fair notice be given to the cabinet secretary.

Jackson Carlaw Con The Convener · Eastwood
link

She is coming to the committee to address a tapestry of transport issues.

Fergus Ewing SNP Inverness and Nairn
link

Yes—a rich tapestry of transport issues.

On a practical level, Nairn is really a one-horse town, in the sense that there is one road in and one road out. There are various rabbit runs, which contain diverted traffic and cause danger, because people drive far too fast on them, particularly in the south of Nairn. However, it is basically a one-road town and, in the summer, with tourism and an increased number of visitors, it can take up to an hour to get from one end of it to another, which is about a mile and a half. I do not know whether there is another town in Scotland that has such a serious congestion problem. Nairn feels that it is a forgotten town.

The final point that I want to make—this is important, and I have put it to the cabinet secretary, but we have not really had an answer—is that the cabinet secretary says that she cannot announce a plan because the Government has not decided how to fund it. Well, it has announced a plan and a timeline for the A9, but it has not decided how to fund those sections north of Drumochter, for exactly the same reasons as for the A96. If the argument is that it cannot publish a plan because it does not quite know how it should be financed, I note that the A9 is in exactly the same position as the A96. Ergo, that argument is plainly fallacious. I am afraid that, locally, there is cynicism that that argument is just a pretext, because it is dragging its feet.

I believe that the main parties—not the Greens—support dualling. With the commitments to dual the rest of the A9 under question, unless there is a clear timeline, there is a concern that, after the 2026 election, the Inverness to Nairn section commitment will be dropped like those for the rest of the A9. I am sorry to take up so much committee time on a constituency matter, but I cannot allow that to happen. I cannot remain in my current position unless there is a timeline; that is not compatible with my standing up for my constituents. It would be a betrayal, and I am not prepared to be part of that betrayal. I just wanted to put that on the record.

Jackson Carlaw Con The Convener · Eastwood
link

Thank you, Mr Ewing. No doubt the cabinet secretary will take note of the Official Report when we flag up issues that might be raised with her when she gives evidence. I note that Nairn is a one-horse town with rabbit runs and that the traffic moves at the pace of a tortoise, but we will try to move beyond all those metaphors and analogies.

Are we content to include the petition as part of the forthcoming evidence session with the Cabinet Secretary for Transport on the various road transport petitions that we have before us?

Members indicated agreement.

Jackson Carlaw Con The Convener · Eastwood
link

That concludes the public part of our meeting. We next meet on 5 March.

11:11 Meeting continued in private until 11:37.

  1. 09:30 Decision on Taking Business in Private Procedure · 2
  2. 09:30 Continued Petitions Petitions · 46
  3. 09:45 Continued Petitions Petitions · 9
  4. 09:45 Continued Petitions Petitions · 3
  5. 10:15 Continued Petitions Petitions · 3
  6. 10:15 Continued Petitions Petitions · 7
  7. 10:30 Continued Petitions Petitions · 3
  8. 10:30 New Petitions Petitions · 1
  9. 10:30 New Petitions Petitions · 2
  10. 10:45 New Petitions Petitions · 8
  11. 10:45 New Petitions Petitions · 4
  12. 10:45 New Petitions Petitions · 4
  13. 10:45 New Petitions Petitions · 3
  14. 10:45 New Petitions Petitions · 8

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.