Question thread · 4 questions
Whether it has carried out, or plans to carry out, a full Gateway Review for the Deposit Return Scheme in February 2023, or close to that date, as recommended in the Gateway Review: Assurance of Action Plan report, whic…
Started with S6W-15390 on 24 Feb 2023; latest 21 Jun 2023. Each later question says it follows up an earlier answer.
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Government whether it has carried out, or plans to carry out, a full Gateway Review for the Deposit Return Scheme in February 2023, or close to that date, as recommended in the Gateway Review: Assurance of Action Plan report, which was published in December 2022, and, if so, whether it will commit to publishing the full Gateway Review as a matter of critical urgency to enable sufficient scope and…
Lorna Slater, 21 Mar 2023: The Scottish Government plans to carry out a further Gateway Review during week commencing 13 March 2023, in line with the last Assurance of Action Plan report’s recommendations for a review to take place in February 2023, or close to that date. The Scottish Government will consider carefully the recommendations from … -
Whether it will now publish in full details of the gateway review that commenced in March 2023, and whether there have been any additional reviews instructed or carried out that the public has not been made aware of.
Lorna Slater, 31 May 2023: The Scottish Government has taken into account the findings of the gateway review commenced in March 2023 and has taken action to address the issues raised. A letter and plan of action which outline how the Scottish Government has addressed or plans to address the recommendations will be sent to the Net Zero, Energy a… -
Whether the (a) gateway review and (b) letter that the Minister will send to the Committee will be made publicly available, and, if this is not the case, what the reasons are for its position on this matter.
Lorna Slater, 15 Jun 2023: All correspondence received by the Committee is published on the Parliament’s website and is therefore publicly available. Gateway reviews are routine components of the Scottish Government’s approach to project management, providing a snapshot of implementation progress. As I set out in my letter of 9 June to the Comm… -
Whether it will provide the information requested, specifically regarding whether or not the gateway review will be made publicly available, and what its reasons were for not providing this information in its answer.
Lorna Slater, 18 Jul 2023: As stated in my answer to S6W-18715 all correspondence with the Committee will be made publicly available. My letter of 16 June setting out the findings of the gateway review and the Scottish Government response is available on the Scottish Parliament website at: https://www.parliament.scot/chamber-and-committees/comm…
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.