Further to the answer to question S6W-15390 by Lorna Slater on 21 March 2023, whether it will now publish in full details of the gateway re…

Answered Asked by Fergus Ewing SNP Lodged 12 May 2023

The question

To ask the Scottish Government, further to the answer to question S6W-15390 by Lorna Slater on 21 March 2023, whether it will now publish in full details of the gateway review that commenced in March 2023, and whether there have been any additional reviews instructed or carried out that the public has not been made aware of.

The answer

Answered by Lorna Slater on 31 May 2023 · 19 days after it was lodged, on time

The Scottish Government has taken into account the findings of the gateway review commenced in March 2023 and has taken action to address the issues raised. A letter and plan of action which outline how the Scottish Government has addressed or plans to address the recommendations will be sent to the Net Zero, Energy and Transport Committee imminently.