Parliament Workbench

Question thread · 5 questions

Whether it will provide an update on the progress of the policy review on the future approach to the procurement of lifeline ferry services, as announced by the Minister for Transport and the Islands in his statement to…

Started with S5W-10393 on 19 Jul 2017; latest 12 Sep 2017. Each later question says it follows up an earlier answer.

Follow-ups
4
longest chain 3 steps
Span
55 days
19 Jul 2017 to 12 Sep 2017
Answered
5 of 5
by Humza Yousaf
Asked by
2
MSPs

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S5W-10393 19 Jul 2017 Gail Ross SNP Answered

    To ask the Scottish Government whether it will provide an update on the progress of the policy review on the future approach to the procurement of lifeline ferry services, as announced by the Minister for Transport and the Islands in his statement to Parliament on 2 February 2017.

    Humza Yousaf, 20 Jul 2017: Since my announcement on 2 February, officials have met with counterparts from the European Commission, undertaken a series of meetings with a range of stakeholders across the Clyde and Hebrides (including Gourock–Dunoon) and Northern Isles ferry networks and considered legal and policy implications related to the app…
  2. S5W-10412 20 Jul 2017 Tavish Scott LD Answered

    When it will determine whether to retender shipping services from Shetland and Orkney to Aberdeen or bring them under the direct operational control of ministers.

    Humza Yousaf, 21 Aug 2017: In my answer to S5W-10393 I noted that the timeline for the policy review would be extended and that a report on the emerging findings of the review is due for publication in Autumn 2017. We will set out in that report our plans for ensuring the continued delivery of essential lifeline ferry services to the Northern I…
  3. S5W-10920 24 Aug 2017 Tavish Scott LD Answered

    What its definition of "Autumn" is and whether it will confirm on what date it will publish the emerging findings of the review.

    Humza Yousaf, 12 Sep 2017: Transport Scotland are currently considering the legal, financial and policy implications relevant to the ongoing review into the future approach to the procurement of lifeline ferry services supported by the Scottish Government. Once this consideration has been completed, an interim report will be published setting o…
  4. S5W-11260 12 Sep 2017 Tavish Scott LD Answered

    Whether it will provide the information that was requested regarding what its definition is of the "Autumn" period.

    Humza Yousaf, 22 Sep 2017: The on-going review into the future approach to the procurement of ferry services follows the meteorological autumn period which begins on 01 September 2017 and ends on 30 November 2017.
  5. S5W-11262 12 Sep 2017 Tavish Scott LD Answered follows S5W-10920

    By what date Transport Scotland will complete its consideration of the legal, financial and policy implications relevant to the ongoing review into the future approach to the procurement of ferry services.

    Humza Yousaf, 22 Sep 2017: Consideration of the legal, financial and policy implications that will inform the emerging findings report will be completed in advance of the publication of that report in the autumn of 2017.

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.